DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 23 awarded projects

2026-11-05
03:11:53Live2026-11-05
0 / 23Advance Pendingpending advance projects / total projects
0 / 23IPC Pendingpending IPC projects / total projects
0 / 23Advance Paidadvance paid projects / total projects
0 / 23IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Uva Province · Province

579Projects23,829.3Contract Mn
Uva Province 23 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn272.658.380% of contract14.3——————0.0%0.0%
Tender Below 50Mn11176.2125.671% of contract50.7——————27.3%0.0%
PIU00.0——————————
Tender Total13248.8183.974% of contract65.0000.0000.023.1%0.0%
Direct LabourDL Stage 016278.4226.881% of contract51.6——————100.0%0.0%
DL Stage 02499.299.1100% of contract0.1——————0.0%0.0%
DL Stage 0300.0——————————
DL Stage 0400.0——————————
Direct Labour Total10377.6325.986% of contract51.7000.0000.060.0%0.0%
—Uva Province23626.4509.881% of contract116.6000.0000.039.1%0.0%
Tender Above 50Mn2 projectsTender72.6Mn
80% paid58.3 Mn
Pending14.3Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn11 projectsTender176.2Mn
71% paid125.6 Mn
Pending50.7Mn
Planned Fin27.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projectsTender0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 016 projectsDirect Labour278.4Mn
81% paid226.8 Mn
Pending51.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 024 projectsDirect Labour99.2Mn
100% paid99.1 Mn
Pending0.1Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projectsDirect Labour0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projectsDirect Labour0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Uva Province23 projects626.4Mn
81% paid509.8 Mn
Pending116.6Mn
Planned Fin39.1%
Actual Fin0.0%

Avg Physical Progress per Province · Uva Province

Graphs reflect current view:23 awarded · Uva Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

51–60/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
51RR/RDA/17/25/11/EP/TRN
Development of Road from near the Fair
MS Construction
25,280,343.60————————————
52RR/RDA/17/25/19/EP/TRN
Periya Suwami Kovil Road-Concrete
Motec Engineering & Construction
25,774,146.00————————————
53RR/RDA/SP/17/25/03/EP/TRN
Hajra Road (Alhira Jalaira Road)
STAAR Construction
38,692,742.00————————————
54RR/RDA/17/25/10KM/04/EP/TRN
Kajuwaththa gama meda road
NMST Construction
22,770,000.00————————————
55RR/RDA/17/25/10KM/06/EP/TRN
Budu pilima and 4th lane road
RS Construction
17,520,285.64————————————
56RR/RDA/17/25/10KM/08/EP/TRN
Paththini Amman Kevil road
Alpha Engineering Services & Suppliers
30,365,709.00————————————
57RR/RDA/17/25/10KM/09/EP/TRN
Bazar mosque road
MTA Construction
32,616,074.70————————————
58RR/RDA/20/25/01/NCP/ANP
Road from Thambuttegama - Nochchiyagama road to the road near the DIG's office o…
Creates Consultant and Construction
96,940,000.00————————————
59RR/RDA/20/25/03/NCP/ANP
Thalawa - Eppawala margaye kele Amunukola handiyen aramba vee kele amunukola vid…
Dissanayaka Builders
26,155,768.37————————————
60RR/RDA/20/25/04/NCP/ANP
A - 9 maragayen aramba vee wale kade dakwa margaya
Dissanayaka Builders
27,008,370.51————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 51–60 of 218 projects · page 6/22