DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 50 awarded projects

2026-11-04
23:14:09Live2026-11-04
0 / 50Advance Pendingpending advance projects / total projects
0 / 50IPC Pendingpending IPC projects / total projects
0 / 50Advance Paidadvance paid projects / total projects
0 / 50IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Sabaragamuwa Province · Province

579Projects23,829.3Contract Mn
Sabaragamuwa Province 50 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn6435.6154.235% of contract281.3——————66.7%0.0%
Tender Below 50Mn29634.2195.831% of contract438.4——————80.7%0.0%
PIU00.0——————————
Tender Total351,069.7350.033% of contract719.8000.0000.078.3%0.0%
Direct LabourDL Stage 015184.5141.877% of contract42.7——————100.0%0.0%
DL Stage 024119.8102.986% of contract16.9——————100.0%0.0%
DL Stage 03234.814.843% of contract20.0——————100.0%0.0%
DL Stage 044335.055.216% of contract279.9——————100.0%0.0%
Direct Labour Total15674.1314.747% of contract359.5000.0000.0100.0%0.0%
—Sabaragamuwa Province501,743.9664.638% of contract1,079.2000.0000.084.8%0.0%
Tender Above 50Mn6 projectsTender435.6Mn
35% paid154.2 Mn
Pending281.3Mn
Planned Fin66.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn29 projectsTender634.2Mn
31% paid195.8 Mn
Pending438.4Mn
Planned Fin80.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projectsTender0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 015 projectsDirect Labour184.5Mn
77% paid141.8 Mn
Pending42.7Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 024 projectsDirect Labour119.8Mn
86% paid102.9 Mn
Pending16.9Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 032 projectsDirect Labour34.8Mn
43% paid14.8 Mn
Pending20.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 044 projectsDirect Labour335.0Mn
16% paid55.2 Mn
Pending279.9Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Sabaragamuwa Province50 projects1,743.9Mn
38% paid664.6 Mn
Pending1,079.2Mn
Planned Fin84.8%
Actual Fin0.0%

Avg Physical Progress per Province · Sabaragamuwa Province

Graphs reflect current view:50 awarded · Sabaragamuwa Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

71–80/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
71—
Development of the road from Punewa Junction to Kudahalmillewa Lake
Priyantha Civil Engineering
28,506,545.00————————————
72—
Development of the road from near Ikirigollawa Muslim Maha Vidyalaya to Ratmalga…
WGL Holdings
10,767,548.00————————————
73—
From Makicchawa Junction to Temple (to Kulumiwakada Junction)
Priyantha Civil Engineering
29,006,146.80————————————
74RR/RDA/21/25/03/NCP/POL
Mahasenpura pradeepika kadaya asala sita Katukeliyawa dakwa margaya Carpart kire…
Nadun Construction (Pvt) Ltd
33,480,137.33————————————
75RR/RDA/21/25/17/NCP/POL
Development of the road from Kaduruwela Muslim Kolaniya road to Pachcha Palliya
Central Engineering Services Pvt Ltd. (C…
53,880,000.00————————————
76RR/RDA/21/25/17/NCP/POL
Development of 1 canal Road from Kadurwela Muslim Kolaniya Road to Parakum Mawat…
Nadun Construction (Pvt) Ltd
54,640,000.00————————————
77RR/RDA/18/25/01/NWP/KRG
Development of Egodagama Talakolawewa road
Sri Ram Constructions
98,323,766.14————————————
78RR/RDA/18/25/04/NWP/KRG
The road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa B…
Shanho Enterprises Pvt Ltd.
59,066,766.74————————————
79RR/RDA/18/25/07/NWP/KRG
Road from Moragolla Junction to Nabadewa Girilla Carpet Road via Kirinda
Jayasinghe Constructions (Pvt) Ltd.
59,247,280.29————————————
80RR/RDA/18/25/09/NWP/KRG
Paving the road from Pahala Galapitiyagama to Tharanagolla Sports Ground
Senerath Engineering (pvt) Ltd
70,405,428.60————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 71–80 of 218 projects · page 8/22