DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 25 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:25 awarded · Puttalam

Portfolio Breakdown · Puttalam · District

579Awarded739Total
Puttalam 25 awarded of 39 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn54180%326.3165.5110.27.95% of contract75.0%57.5%
Tender Below 50Mn2314961%615.2302.4302.488.429% of contract100.0%74.2%
DL Stage 01220100%35.635.635.638.9109% of contract100.0%100.0%
DL Stage 02220100%88.288.2—80.992% of contract0.0%100.0%
DL Stage 03110100%25.225.2—17.971% of contract0.0%100.0%
DL Stage 04220100%30.030.0—28.896% of contract0.0%82.5%
PIU0000%0.00.0————
Not Specified4040%0.00.0————
Puttalam39251464%1,120.6646.9448.3262.841% of contract76.0%77.4%

Avg Physical Progress per EE Division · Puttalam

At-Risk Projects · Puttalam

15
Portfolio Timeline· 22 scheduled projects · Puttalam Toggle
Portfolio · Awarded Works

Awarded Projects

1 projects

1/1 (filtered)

Filter awarded works

1 matching project2 active

ActiveDelayed onlyOn Progress
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/19/25/40
Development of the road from Madurankuliya to Velasiya College
30%
55,254,878.0090,437,412.35Awarded
Showing 1–1 of 1
Per page:
Source: DRRRP • 39 projects • Data updated 2026-11-02 10:30 • 11:43:04