DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 6 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:6 awarded · Ampara · EE: Ampara

Portfolio Breakdown · Ampara · EE: Ampara · EE Office

25Awarded26Total
Ampara 6 awarded of 6 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn110100%306.5222.2222.2105.347% of contract100.0%34.0%
Tender Below 50Mn440100%82.853.553.59.017% of contract100.0%36.3%
DL Stage 01110100%171.7171.7—100.158% of contract0.0%100.0%
DL Stage 030000%0.00.0————
DL Stage 040000%0.00.0————
Ampara660100%561.0447.4275.7214.348% of contract83.3%46.5%

Avg Physical Progress per EE Division · Ampara · EE: Ampara

Portfolio Timeline· 6 scheduled projects · Ampara · EE: Ampara Toggle
Portfolio · Awarded Works

Awarded Projects

4 projects

4/4 (filtered)

Filter awarded works

4 matching projects1 active

ActiveCritical Delay
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/SP/16/25/01/AKK/AMPRR/RDA/SP/16/25/01
Rectification and Asphalt Surfacing on Ambahagawela -Namaloya Main Road
34%
222,189,859.13306,475,548.92Awarded
2RR/RDA/16/25/10KM/02/AKK/AMPRR/RDA/16/25/10KM/02
Road from Nelum Cafe Junction to Neeththa
20%
19,318,560.1029,760,217.62Awarded
3RR/RDA/16/25/10KM/04/AKK/AMPRR/RDA/16/25/10KM/04
Vevinna Boogas Junction Inner Road
15%
9,692,957.4514,460,000.00Awarded
4RR/RDA/16/25/10KM/05/AKK/AMPRR/RDA/16/25/10KM/05
Road from Dorapaha Junction to Navagiriya Lake
10%
18,058,942.0028,554,939.58Awarded
Showing 1–4 of 4
Per page:
Source: DRRRP • 6 projects • Data updated 2026-11-02 10:30 • 10:39:12