Graphs reflect current view:9 awarded · EE: Kandy

Portfolio Breakdown · EE: Kandy · EE Office

567Awarded667Total
Kandy 9 awarded of 9 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn330100%244.5199.4199.446.423% of contract100.0%40.0%
Tender Below 50Mn440100%136.1117.988.033.128% of contract75.0%55.0%
DL Stage 01110100%40.440.440.440.8101% of contract100.0%100.0%
DL Stage 02110100%8.88.88.85.259% of contract100.0%100.0%
DL Stage 030000%0.00.0————
DL Stage 040000%0.00.0————
Not Specified0000%0.00.0————
Kandy990100%429.8366.4336.6125.534% of contract88.9%60.0%

Avg Physical Progress per EE Division · EE: Kandy

Portfolio Timeline· 9 scheduled projects · EE: Kandy Toggle
Portfolio · Awarded Works

Awarded Projects

9 projects

9/9

Filter awarded works

9 matching projects

#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/04/25/20/CP/KYRR/RDA/04/25/20
Carpeting road Ratemulla to Wendesiwaththa End
45%
36,995,817.1040,119,276.86Awarded
2RR/RDA/04/25/27/CP/KYRR/RDA/04/25/27
Dadahogama pitiye gedara pathibami sahitha Margaya
100%
12,532,355.0014,990,258.08Awarded
3RR/RDA/04/25/28/CP/KYRR/RDA/04/25/28
Dehideniya sita Hedeniya dakwa Margaya
35%
38,495,776.0041,827,394.04Awarded
4RR/RDA/04/25/52/CP/KYRR/RDA/04/25/52
Bokalawela Road from Hapugoda Junction to Ranawana (Drinage System Development and Road)
60%
50,478,905.0072,631,674.77Awarded
5RR/RDA/04/25/53/CP/KYRR/RDA/04/25/53
Road from Amuvandeniya to Magurudeniya (development of the drainage and carpeting of the road)
40%
29,850,460.2039,182,935.51Awarded
6RR/RDA/04/25/54
Development of the Dolapihilla road from Navinnapitiya via Deldeniya
20%
65,808,186.5073,819,405.52Awarded
7RR/RDA/04/25/55
Development of entrance roads, pedestrian rest areas and parking areas of the Sri Dalada Maligawa premises
40%
83,080,000.0098,049,399.56Awarded
8RR/RDA/04/25/45—
Seewalee Kande sits Mahthanna Samadi Senasuna dakwa divena margaya
100%
40,376,466.5640,376,466.56Awarded
9RR/RDA/04/25/12—
Wattaranthenna Sri Sumangala Mawatha
100%
8,793,978.608,793,978.60Awarded
Showing 1–9 of 9