DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 2 awarded projects

2026-11-04
17:43:46Live2026-11-04
0 / 2Advance Pendingpending advance projects / total projects
0 / 2IPC Pendingpending IPC projects / total projects
1 / 2Advance Paidadvance paid projects / total projects
0 / 2IPCs PaidIPC paid projects / total projects
49.0 Mn

48.97 Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

49.0 Mn

48.97 Mn

Total Paid (excl. VAT)

57.8 Mn

57.78 Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

57.8 Mn

57.78 Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

5%

5%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

1.5%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · DC - Roads · Norwood EE · Consultant

8Projects5,116.6Contract Mn
Reset
Norwood EE 2 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency00.0——————————
DC - Roads2979.257.86% of contract—1149.0———1.8%5.0%
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
Norwood EE2979.257.86% of contract0.01149.0000.01.8%5.0%
Emergency0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Roads2 projects979.2Mn
6% paid57.8 Mn
Pending—
Planned Fin1.8%
Actual Fin5.0%
Advance & IPC
Advance paid1 proj · 49.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Norwood EE2 projects979.2Mn
6% paid57.8 Mn
Pending0.0Mn
Planned Fin1.8%
Actual Fin5.0%

Avg Physical Progress per Province · DC - Roads · Norwood EE

Project-wise Financials · DC - Roads · Norwood EE (171 Projects)

Clear

Project-wise Contract Value vs. Expenditure and Pending Payments · DC - Roads · Norwood EE (Mn · incl. VAT)

Scroll horizontally — 171 projects

Norwood EE Division · DC - Roads · Norwood EE (Mn · incl. VAT)

Nuwara Eliya District Summary (Mn · incl. VAT)

District baseline — overall DC - Roads (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:2 awarded · DC - Roads · Norwood EE
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 171 projects

41–50/171

Filter financial register

171 matching projects

S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
41RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenk…
Weebadda Construction
22,481,370.00————————————
42RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Galaha-Pupuressa-Delpiti…
J. Kodithuwakkuarachchi & Sons (Pvt) Ltd
17,724,816.00————————————
43RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Atabage-Ulapane Road (B …
Bandaranayake Builders and Construction
24,796,315.46————————————
44RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenk…
Weebadda Construction
28,806,688.50————————————
45RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Kandy-Mahiyangana-Padiya…
J. Kodithuwakkuarachchi & Sons (Pvt) Ltd
25,255,788.00————————————
46RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Kandy – Mahiyangana – Pa…
J. Kodithuwakkuarachchi & Sons (Pvt) Ltd
19,636,680.00————————————
47RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along KandyMahiyanganaPadiyath…
J. Kodithuwakkuarachchi & Sons (Pvt) Ltd
12,938,500.00————————————
48RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Aladeniya-Eriyagama Road…
Weebadda Construction
26,072,370.00————————————
49RDA/DRP/SAB/KEG/KEG/14
Rehabilitation / Improvement of Damaged Locations in Colombo Kandy Road from 56+…
Tudawe Brothers (Pvt) Ltd
261,228,130.7847,252,023.7855,757,388.06——20,746,920.9124,481,366.67——67,998,944.69—
80.24Mn
30.7%
Watch
80.24Mn
30.7%
50RDA/DRP/UVA/BAD/BAD/02
Rehabilitation / Improvement of Demodara SpringValley Badulla Road (16+145-20+80…
Priyankara Industries & Contractors
241,775,532.44————30,108,187.0035,527,660.65——30,108,187.00—
35.53Mn
14.7%
Behind
35.53Mn
14.7%
Total34,005,299,486.172,787,819,645.293,289,427,166.63113,218,826.01133,598,214.691,049,943,508.601,238,847,524.5163,842,351.1873,647,937.023,837,763,153.89177,061,177.19
4,528.27Mn
13.3%
4,735.52Mn
13.9%
Showing 41–50 of 171 projects · page 5/18