DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 26 awarded projects

2026-11-04
23:54:42Live2026-11-04
0 / 26Advance Pendingpending advance projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

Portfolio Breakdown — Financial (Exclusive Vat) · Team Leader · Consultant

44Projects11,748.0Contract Mn
Reset
Team Leader 26 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency152,082.2381.018% of contract43.877213.4156109.661.9%15.5%
DC - Roads64,137.5————————0.0%0.0%
DC - Slope51,984.7————————0.5%0.0%
PD(CP) - Slope00.0——————————
Team Leader268,204.4381.05% of contract43.877213.4156109.635.8%3.9%
Emergency15 projects2,082.2Mn
18% paid381.0 Mn
Pending43.8Mn
Planned Fin61.9%
Actual Fin15.5%
Advance & IPC
Advance paid7 proj · 213.4 Mn
IPC paid6 proj · 109.6 Mn
Open filtered view
DC - Roads6 projects4,137.5Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope5 projects1,984.7Mn
0% paid0.0 Mn
Pending—
Planned Fin0.5%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Team Leader26 projects8,204.4Mn
5% paid381.0 Mn
Pending43.8Mn
Planned Fin35.8%
Actual Fin3.9%

Avg Physical Progress per Province · Team Leader

Project-wise Financials · Team Leader (92 Projects)

Clear

Project-wise Contract Value vs. Expenditure and Pending Payments · Team Leader (Mn · incl. VAT)

Scroll horizontally — 92 projects

Team Leader · Team Leader (Mn · incl. VAT)

Kandy District Summary (Mn · incl. VAT)

District baseline — overall all categories (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:26 awarded · Team Leader
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 92 projects (filtered from 171)

51–60/92 (filtered from 171)

Filter financial register

92 matching projects1 active

ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
51RDA/DRP/WP/GAM/NIT/22
Rehabilitation / Improvement of Delgoda Dompe Giridara Road (Selected Sections …
Senarath Engineering (Pvt) Ltd
264,745,054.4847,651,364.4556,228,610.05——————47,651,364.45—
56.23Mn
21.2%
Watch
56.23Mn
21.2%
52RDA/DRP/WP/GAM/NIT/23
Rehabilitation / Improvement of Kalagedihena Veyangoda Road (0+000 -3+000), Pas…
Senarath Engineering (Pvt) Ltd
258,218,314.9745,755,884.5453,991,943.76——————45,755,884.54—
53.99Mn
20.9%
Watch
53.99Mn
20.9%
53RDA/DRP/SAB/KEG/RUW/30
Rehabilitation of Dehiovita - Daraniyagala - Nooriya Road (from 23+850 to 27+960…
Accon Engineering (Pvt) Ltd
169,223,910.8030,441,983.7935,921,540.87——9,989,836.6611,788,007.26——40,431,820.45—
47.71Mn
28.2%
Watch
47.71Mn
28.2%
54RDA/DRP/SAB/KEG/RUW/31
Rehabilitation of Kegalle - Bulathkohupitiya - Karawanella Road due to catastrop…
Tudawe Brothers (Pvt) Ltd
269,890,586.8648,845,015.8057,637,118.64——8,891,636.6510,492,131.25——57,736,652.45—
68.13Mn
25.2%
Watch
68.13Mn
25.2%
55RDA/DRP/WP/COL/AVI/02
Rehabilitation / Improvement of Damage Sections on Colombo - Hanwella Low Level …
Keangnam Engineering & Construction (Pvt…
279,374,027.90————6,828,549.848,057,688.81——6,828,549.84—
8.06Mn
2.9%
Behind
8.06Mn
2.9%
56RDA/DRP/WP/COL/AVI/03
Rehabilitation / Improvement and Asphalt Overlaying on Colombo - Horana Road (B0…
Keangnam Engineering & Construction (Pvt…
176,739,557.41382,642.19451,517.79——838,664.06989,623.60——1,221,306.25—
1.44Mn
0.8%
Behind
1.44Mn
0.8%
57RDA/DRP/WP/COL/AVI/04
Rehabilitation / Improvement and Asphalt Overlaying on Mampe Kottawa Road (B267)…
Keangnam Engineering & Construction (Pvt…
94,697,340.0117,192,698.1820,287,383.86——30,212,899.2035,651,221.05——47,405,597.38—
55.94Mn
59.1%
On Track
55.94Mn
59.1%
58RDA/DRP/WP/COL/AVI/05
Rehabilitation / Improvement and Asphalt Overlaying on Panagoda Henpita Road (B3…
Keangnam Engineering & Construction (Pvt…
225,228,168.18————1,635,814.911,930,261.59——1,635,814.91—
1.93Mn
0.9%
Behind
1.93Mn
0.9%
59RDA/DRP/NWP/KURU/KURU/04
Rehabilitation / Improvement of Muththettugala Hiripitiya Road (B300) (10+880 …
TMC Construction (Pvt) Ltd
97,503,423.1716,053,895.1218,943,596.24——11,350,228.2113,393,269.29——27,404,123.33—
32.34Mn
33.2%
Watch
32.34Mn
33.2%
60RDA/DRP/NWP/KURU/MAHO/05
Rehabilitation / Improvement of Galgamuwa - Nikawewa Road (B126) (6+000-20+000),…
St. Anthony's Construction
151,515,024.3627,548,186.2532,506,859.78——————27,548,186.25—
32.51Mn
21.5%
Watch
32.51Mn
21.5%
Total16,799,029,680.142,276,780,837.162,686,401,372.89——905,188,809.071,068,036,979.0652,935,451.9660,777,795.943,181,969,646.2352,935,451.96
3,754.44Mn
22.3%
3,815.22Mn
22.7%
Showing 51–60 of 92 projects · page 6/10