DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 24 awarded projects

2026-11-04
22:32:20Live2026-11-04
0.0 Mn

— Mn

Advance Pend (incl. VAT)

19.5 Mn

19.55 Mn

IPCs Pend (incl. VAT)

Portfolio Breakdown — Financial (Exclusive Vat) · Nuwara Eliya · District

171Projects34,005.3Contract Mn
Reset
Nuwara Eliya 24 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency101,668.3347.921% of contract19.577194.3114100.589.4%17.7%
DC - Roads85,116.657.81% of contract—1149.0———0.5%1.0%
DC - Slope61,731.6————————0.0%0.0%
PD(CP) - Slope00.0——————————
Nuwara Eliya248,516.5405.75% of contract19.588243.3114100.537.4%4.0%
Emergency10 projects1,668.3Mn
21% paid347.9 Mn
Pending19.5Mn
Planned Fin89.4%
Actual Fin17.7%
Advance & IPC
Advance paid7 proj · 194.3 Mn
IPC paid4 proj · 100.5 Mn
Open filtered view
DC - Roads8 projects5,116.6Mn
1% paid57.8 Mn
Pending—
Planned Fin0.5%
Actual Fin1.0%
Advance & IPC
Advance paid1 proj · 49.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope6 projects1,731.6Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Nuwara Eliya24 projects8,516.5Mn
5% paid405.7 Mn
Pending19.5Mn
Planned Fin37.4%
Actual Fin4.0%

Avg Physical Progress per Province · Nuwara Eliya

Graphs reflect current view:24 awarded · Nuwara Eliya
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 171 projects

111–120/171

Filter financial register

171 matching projects

S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
111RDA/DRP/NCP/POL/POL/09
Rehabilitation / Improvement and Reconstruction of Culvert No. 104/2, Constructi…
Abeywardhana Construction
94,457,054.6616,284,158.9419,215,307.55——10,001,813.4211,802,139.84——26,285,972.36—
31.02Mn
32.8%
Watch
31.02Mn
32.8%
112RDA/DRP/SAB/RAT/EMB/08
Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Naonagama Road (AA01…
Anura Construction
259,436,963.3546,754,356.9855,170,141.24——————46,754,356.98—
55.17Mn
21.3%
Watch
55.17Mn
21.3%
113RDA/DRP/SAB/RAT/EMB/10
Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Nonagama Road (AA018…
Kanwel Constructions & Civil Engineering…
260,776,583.4347,155,924.2655,643,990.62——11,394,017.6413,444,940.82——58,549,941.90—
69.09Mn
26.5%
Watch
69.09Mn
26.5%
114RDA/DRP/EAS/BAT/BAT/01
Rehabilitation / Improvement and Surfacing from 56+900 km to 58+300km and from 5…
S S K Construction
113,074,919.76————45,270,508.3753,419,199.87——45,270,508.37—
53.42Mn
47.2%
On Track
53.42Mn
47.2%
115RDA/DRP/UVA/BAD/BAD/11
Rehabilitation / Improvement of (1) PASSARA MADULSIMA METIGAHATENNA ROAD (18+03…
Jayanetti Construction
149,405,885.1426,364,706.3931,110,353.54——22,682,127.0126,764,909.87——49,046,833.40—
57.88Mn
38.7%
Watch
57.88Mn
38.7%
116RDA/DRP/UVA/BAD/BAD/09
Rehabilitation / Improvement of (1) ELLA PASSARA ROAD (23+800-27+080)
Nimsara Construction & Engineering (Pvt)…
254,650,056.8945,740,010.3453,973,212.20——————45,740,010.34—
53.97Mn
21.2%
Watch
53.97Mn
21.2%
117RDA/DRP/UVA/BAD/BAD/08
Rehabilitation / Improvement of Dikwella Jagulla Thalpitigala Road (B100) (15+00…
SF Construction (Pvt) Ltd
188,749,480.0034,036,087.2740,162,582.98——————34,036,087.27—
40.16Mn
21.3%
Watch
40.16Mn
21.3%
118RDA/DRP/UVA/BAD/BAD/13
Rehabilitation / Improvement of Ella Passara Road (B113) (9+500 - 27+000)
SF Construction (Pvt) Ltd
290,901,643.5852,711,207.9362,199,225.36——————52,711,207.93—
62.20Mn
21.4%
Watch
62.20Mn
21.4%
119RDA/DRP/SAB/RAT/EMB/05
Rehabilitation / Improvement of Pelmadulla-Embilipitiya-Nonagama Road (30+000-32…
Anura Construction
248,600,718.52————————————
120RDA/DRP/SAB/RAT/EMB/06
Rehabilitation / Improvement of Pelmadulla - Embilipitiya-Nonagama Road (33+500-…
Anura Construction
237,998,681.32————————————
Total34,005,299,486.172,787,819,645.293,289,427,166.63113,218,826.01133,598,214.691,049,943,508.601,238,847,524.5163,842,351.1873,647,937.023,837,763,153.89177,061,177.19
4,528.27Mn
13.3%
4,735.52Mn
13.9%
Showing 111–120 of 171 projects · page 12/18