DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 14 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka. · Team Leader
Updated 2026-11-02 15:53Live
Graphs reflect current view:14 awarded · Team Leader · Kandy
100% awarded
0
Awarded
14 total projects in portfolio
Awarded projects14
RDA/DRP/CEN/KDY/KAD/11Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )RDA/DRP/CEN/KDY/KAN/14Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)RDA/DRP/CEN/KDY/KDY/15Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)RDA/DRP/CEN/KDY/KDY/19Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)RDA/DRP/CEN/KDY/KUN/20Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)RDA/DRP/CEN/KDY/KUN/21Pitiyegedara-Waththegama-Iriyagasthenna Road (B369)RDA/DRP/CEN/KDY/KUN/22Weraganthota-Randenigala Road (B474)RDA/DRP/CEN/KDY/KUN/24RKatugastota Madawala Bamberella RoadRDA/DRP/CEN/KDY/KUN/25Katugastota - Madawala - Bamberella RoadRDA/DRP/CEN/KDY/KUN/26RKandy - Jaffna RoadRDA/DRP/CEN/KDY/KUN/27Kandy - Jaffna RoadRDA/DRP/CEN/KDY/KUN/29Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) A026 and Moragahamula victoria damtop B493RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09RDA/DC/DRP/SLOPE/CP/KDY/KUN/PACKAGE 06A
Click to filter the awarded table
2,535.9M
2,535.9 Mn
Contract Value
Awarded projects14
RDA/DRP/CEN/KDY/KAD/11Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )RDA/DRP/CEN/KDY/KAN/14Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)RDA/DRP/CEN/KDY/KDY/15Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)RDA/DRP/CEN/KDY/KDY/19Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)RDA/DRP/CEN/KDY/KUN/20Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)RDA/DRP/CEN/KDY/KUN/21Pitiyegedara-Waththegama-Iriyagasthenna Road (B369)RDA/DRP/CEN/KDY/KUN/22Weraganthota-Randenigala Road (B474)RDA/DRP/CEN/KDY/KUN/24RKatugastota Madawala Bamberella RoadRDA/DRP/CEN/KDY/KUN/25Katugastota - Madawala - Bamberella RoadRDA/DRP/CEN/KDY/KUN/26RKandy - Jaffna RoadRDA/DRP/CEN/KDY/KUN/27Kandy - Jaffna RoadRDA/DRP/CEN/KDY/KUN/29Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) A026 and Moragahamula victoria damtop B493RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09RDA/DC/DRP/SLOPE/CP/KDY/KUN/PACKAGE 06A
Click to filter the awarded table
Avg
29.1%
12
works in progress
0 completed
Avg Progress
Awarded projects14
RDA/DRP/CEN/KDY/KAD/11Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )RDA/DRP/CEN/KDY/KAN/14Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)RDA/DRP/CEN/KDY/KDY/15Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)RDA/DRP/CEN/KDY/KDY/19Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)RDA/DRP/CEN/KDY/KUN/20Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)RDA/DRP/CEN/KDY/KUN/21Pitiyegedara-Waththegama-Iriyagasthenna Road (B369)RDA/DRP/CEN/KDY/KUN/22Weraganthota-Randenigala Road (B474)RDA/DRP/CEN/KDY/KUN/24RKatugastota Madawala Bamberella RoadRDA/DRP/CEN/KDY/KUN/25Katugastota - Madawala - Bamberella RoadRDA/DRP/CEN/KDY/KUN/26RKandy - Jaffna RoadRDA/DRP/CEN/KDY/KUN/27Kandy - Jaffna RoadRDA/DRP/CEN/KDY/KUN/29Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) A026 and Moragahamula victoria damtop B493RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09RDA/DC/DRP/SLOPE/CP/KDY/KUN/PACKAGE 06A
Click to filter the awarded table
329.6M
329.6 Mn
Total Expenditure (incl. VAT)
Awarded projects14
RDA/DRP/CEN/KDY/KAD/11Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )RDA/DRP/CEN/KDY/KAN/14Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)RDA/DRP/CEN/KDY/KDY/15Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)RDA/DRP/CEN/KDY/KDY/19Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)RDA/DRP/CEN/KDY/KUN/20Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)RDA/DRP/CEN/KDY/KUN/21Pitiyegedara-Waththegama-Iriyagasthenna Road (B369)RDA/DRP/CEN/KDY/KUN/22Weraganthota-Randenigala Road (B474)RDA/DRP/CEN/KDY/KUN/24RKatugastota Madawala Bamberella RoadRDA/DRP/CEN/KDY/KUN/25Katugastota - Madawala - Bamberella RoadRDA/DRP/CEN/KDY/KUN/26RKandy - Jaffna RoadRDA/DRP/CEN/KDY/KUN/27Kandy - Jaffna RoadRDA/DRP/CEN/KDY/KUN/29Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) A026 and Moragahamula victoria damtop B493RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09RDA/DC/DRP/SLOPE/CP/KDY/KUN/PACKAGE 06A
Click to filter the awarded table
14.3%
0
On Progress
2 / 14 awarded
On Progress (incl. completed)2
RDA/DRP/CEN/KDY/KDY/19Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09
Click to filter the awarded table
28.6%
0
Delay
4 / 14 awarded
Delay4
RDA/DRP/CEN/KDY/KAN/14Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)RDA/DRP/CEN/KDY/KDY/15Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)RDA/DRP/CEN/KDY/KUN/24RKatugastota Madawala Bamberella RoadRDA/DRP/CEN/KDY/KUN/29Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) A026 and Moragahamula victoria damtop B493
Click to filter the awarded table
42.9%
0
Critical Delay
6 / 14 awarded
Critical Delay6
RDA/DRP/CEN/KDY/KAD/11Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )RDA/DRP/CEN/KDY/KUN/20Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)RDA/DRP/CEN/KDY/KUN/21Pitiyegedara-Waththegama-Iriyagasthenna Road (B369)RDA/DRP/CEN/KDY/KUN/22Weraganthota-Randenigala Road (B474)RDA/DRP/CEN/KDY/KUN/25Katugastota - Madawala - Bamberella RoadRDA/DRP/CEN/KDY/KUN/27Kandy - Jaffna Road
Click to filter the awarded table
0%
0
Completed
0 / 14 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · Team Leader · Kandy · Consultant
Project-wise Progress · Team Leader · Kandy (14 projects in one graph)
Physical Actual vs Planned per project • Click bar to open project
Project-wise Physical Progress: Actual vs Planned (%) · Team Leader · Kandy
Average Physical Progress by EE Division · Team Leader · Kandy
Average District-wise Physical Progress (Kandy District)
Kandy district baseline — all categories (consultant filter excluded for comparison)
At-Risk Projects · Team Leader · Kandy
- RDA/DRP/CEN/KDY/KAD/11Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )Delay42 Days in Delay · 26.5%
- RDA/DRP/CEN/KDY/KUN/22Weraganthota-Randenigala Road (B474)Delay42 Days in Delay · 67%
- RDA/DRP/CEN/KDY/KUN/27Kandy - Jaffna RoadDelay8 Days in Delay · 66%
- RDA/DRP/CEN/KDY/KUN/21Pitiyegedara-Waththegama-Iriyagasthenna Road (B369)Delay7 Days in Delay · 12%
- RDA/DRP/CEN/KDY/KUN/25Katugastota - Madawala - Bamberella RoadDelay3 Days in Delay · 59%
Portfolio Timeline· 12 scheduled projects · Team Leader · Kandy Toggle
2026-03-25 today2027-06-30
Portfolio · Awarded Works
Awarded Projects
14 projects
Filter awarded works
14 matching projects
| Contract No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|
| RDA/DRP/CEN/KDY/KAD/11 | Rehabilitation / Improvement of Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 ) | 26.5% | 193,404,194.96 | 275,515,701.42 | Awarded |
| RDA/DRP/CEN/KDY/KAN/14 | Rehabilitation /Improvement of Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370) | 9% | 74,836,014.77 | 72,827,654.90 | Awarded |
| RDA/DRP/CEN/KDY/KDY/15 | Rehabilitation / Improvement of Galagedara Rambukkana ( B 122) ( 0+000 - 18+000) | 6% | 79,071,437.68 | 79,953,569.86 | Awarded |
| RDA/DRP/CEN/KDY/KDY/19 | Rehabilitation / Improvement of Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000) | 5% | 67,935,586.77 | 64,393,315.70 | Awarded |
| RDA/DRP/CEN/KDY/KUN/20 | Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000) | 53% | 31,558,227.98 | 28,660,618.70 | Awarded |
| RDA/DRP/CEN/KDY/KUN/21 | Improvement of Pitiyegedara-Waththegama-Iriyagasthenna Road (0+000-5+400) | 12% | 257,721,453.96 | 314,486,807.16 | Awarded |
| RDA/DRP/CEN/KDY/KUN/22 | Improvement to Damaged Road Section on Weeragantota - Randenigala Road. (From CH 19+000 To CH 27+200) | 67% | 224,968,435.78 | 333,005,906.52 | Awarded |
| RDA/DRP/CEN/KDY/KUN/24R | Rehabilitation / Improvement of Flood damage on Katugastota - Madawala - Bamberella Road (B205) (0-000 - 7+200 and 13+000 - 13+045) | 5% | 79,507,501.11 | 80,438,429.85 | Awarded |
| RDA/DRP/CEN/KDY/KUN/25 | Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435) | 59% | 157,909,825.01 | 178,738,774.63 | Awarded |
| RDA/DRP/CEN/KDY/KUN/26R | Improvement to Structures on Kandy - Jaffna Road 11+700 - 11+850 | 0% | 148,430,322.65 | 140,123,428.78 | Awarded |
| RDA/DRP/CEN/KDY/KUN/27 | Improvement to Structures on Kandy - Jaffna Road 6+500 - 9+910 | 66% | 113,434,139.40 | 122,896,558.88 | Awarded |
| RDA/DRP/CEN/KDY/KUN/29 | Improvement to Structures on Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) and Moragahamula victoria damtop | 61% | 91,559,621.04 | 100,543,979.99 | Awarded |
| RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09 | MITIGATION OF FAILURES ALONG RDA ROADS DUE TO CYCLONE DITWAH GAMPOLA NAWALAPITIYA ROAD (AB013) CHAINAGE 10+350 KM | 9.3% | 386,699,553.58 | 479,898,195.86 | Awarded |
| RDA/DC/DRP/SLOPE/CP/KDY/KUN/PACKAGE 06A | REHABILITATION OF SELECTED ROAD SECTIONS ON KANDY-MAHIYANGANA-PADIYATHALAWA ROAD (34th & 35th KM) & MORAGAHAMULA VICTORIA DAMTOP ROAD (6TH KM) AND SLOPE FAILURES DUE TO "DITWAH" CYCLONE- PACKAGE 06A | 0% | 628,900,686.30 | 614,600,000.00 | Awarded |
Showing 1–14 of 14
Source: DRRRP • 14 projects • Data updated 2026-11-02 15:53 • 09:48:32 System live • Sri Lanka • 1 districts