Portfolio Breakdown · Team Leader · Kandy · Consultant

14Awarded14Total
Team Leader 14 awarded of 14 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %Kick Off PendingMobilization PendingWorks Not Started
Emergency12120100%1,791.61,520.31,105.2329.622% of contract62.1%30.8%111
DC - Roads0000%0.00.0———————
DC - Slope220100%1,094.51,015.610.4—1.4%9.3%111
PD(CP) - Slope0000%0.00.0———————
Team Leader14140100%2,886.12,535.91,115.6329.613% of contract53.4%27.7%222

Project-wise Progress · Team Leader · Kandy (14 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear

Project-wise Physical Progress: Actual vs Planned (%) · Team Leader · Kandy

Average Physical Progress by EE Division · Team Leader · Kandy

Average District-wise Physical Progress (Kandy District)

Kandy district baseline — all categories (consultant filter excluded for comparison)

Portfolio Timeline· 12 scheduled projects · Team Leader · Kandy Toggle
Portfolio · Awarded Works

Awarded Projects

2 projects

2/2 (filtered)

Filter awarded works

2 matching projects1 active

ActiveOn Progress
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/KDY/KDY/19
Rehabilitation / Improvement of Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)
5%
67,935,586.7764,393,315.70Awarded
RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09
MITIGATION OF FAILURES ALONG RDA ROADS DUE TO CYCLONE DITWAH GAMPOLA NAWALAPITIYA ROAD (AB013) CHAINAGE 10+350 KM
9.3%
386,699,553.58479,898,195.86Awarded
Showing 1–2 of 2
Per page:
Source: DRRRP • 14 projects • Data updated 2026-11-04 12:46 • 13:24:47