Ditwah (CP)

Project Monitoring Dashboard

Comprehensive overview of 5 infrastructure projects under the Disaster Rehabilitation Programme. · Norwood EE

Updated 2026-09-24 15:27Live
Graphs reflect current view: 5 awarded · Norwood EE · Nuwara Eliya

Portfolio at a Glance

5 awarded works · Norwood EE · Nuwara Eliya

2026-09-24 15:27
100% awarded

0

Awarded

5 total projects in portfolio

1,348.3M

1,348.3 Mn

Contract Value

Spent 1% Remaining 99%
Avg
15.8%

5

works in progress

0 completed

Avg Progress

14.1M

14.1 Mn

Total Expenditure (excl. VAT)

1% of contract excl. VAT
0%

0

Kick Off Pending

0 / 5 awarded

0%

0

Mobilization Pending

0 / 5 awarded

0%

0

Works Not Started

0 / 5 awarded

0%

0

Completed

0 / 5 awarded

Portfolio Breakdown · Norwood EE · Nuwara Eliya · Consultant

13Awarded 13Total
Norwood EE 5 awarded of 5 Open filtered view
Category Total Awarded Pending Awarded % Estimate LKR Mn Contract LKR Mn Planned Exp Mn Actual Exp ex-VAT Planned % Actual % Kick Off Pending Mobilization Pending Works Not Started
Emergency 3 3 0 100% 435.8 369.1 210.9 14.1 4% of contract 78.7% 24.3% — — —
DC 2 2 0 100% 0.0 979.2 24.4 — 7.4% 3.0% — — —
DC - Slope 0 0 0 0% 0.0 0.0 — — — — — — —
PD(CP) 0 0 0 0% 0.0 0.0 — — — — — — —
Norwood EE 5 5 0 100% 435.8 1,348.3 235.3 14.1 1% of contract 50.2% 15.8% 0 0 0

Project-wise Progress · Norwood EE · Nuwara Eliya (5 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear

Project-wise Physical Progress: Actual vs Planned (%) · Norwood EE · Nuwara Eliya

Average Physical Progress by EE Division · Norwood EE · Nuwara Eliya

Average District-wise Physical Progress (Nuwara Eliya District)

Nuwara Eliya district baseline — all categories (consultant filter excluded for comparison)

Portfolio Timeline · 5 scheduled projects · Norwood EE · Nuwara Eliya Toggle
Portfolio · Awarded Works

Awarded Projects

5 projects

5/5
Contract No. Contract Name Progress Amount Status
RDA/DRP/CEN/NUE/NUR/97
Rehabilitation/Improvement of Nawalapitiya Ginigathena Road (B-319)(7+200-12+200)
40%
93,758,217.76 Awarded
RDA/DRP/CEN/NUE/NUR/98
Rehabilitation/Improvement Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Hrangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)
22%
188,617,394.68 Awarded
RDA/DRP/CEN/NUE/NUR/101
Rehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970)
11%
86,746,198.17 Awarded
RDA/DC/DRP/CP/NE/NRW/02
REHABILITATION/ IMPROVEMENT OF APPROCH ROAD TO LAXAPANA POWER HOUSE ROAD CH 6+100 - 12+000
3%
374,859,845.10 Awarded
RDA/DC/DRP/CP/NE/NRW/03
REHABILITATION/ IMPROVEMENT TO ROZELLA RAILWAY STATION ROAD (0+000 - 3+300) KM AND WATAWALA RAILWAY STATION ROAD (0+000 - 1+850) KM
3%
604,298,969.28 Awarded
Showing 1–5 of 5
Per page:
Source: ditwah_projects • 5 projects • Data updated 2026-09-24 15:27 • 18:19:58