Dashboard
Physical Progress
Physical Progress
2026-08-11
1
Awarded Projects
0 / 1
In Progress
0.0%
Avg Progress
0
Overdue
| Contract No. | Contractor | Commencement Date | Completion Date | Overall Progress | Action |
|---|---|---|---|---|---|
| RDA/DRP/CEN/KDY/KUN/20 | Samindra Construction | — | — |
0%
|
Update |
RDA/DRP/CEN/KDY/KUN/20
Madolkelle - Kabaragala - Kandenuwara Road 5/4 and 8/1
Samindra Construction
Kandy
Kundasale
Awarded
Current Progress
Overall
0%
Critical Issues
—
Mobilization
0%
Surveying
0%
Site Clearing
0%
Base Construction
0%
Asphalt
0%
Structure Construction
0%
Drainage Construction
0%