Dashboard Physical Progress

Physical Progress

1

Awarded Projects

0 / 1

In Progress

0.0%

Avg Progress

0

Overdue

Awarded Projects Summary

1 projects

XLSX Clear Showing 1 of 1
Contract No. Contractor Commencement Date Completion Date Overall Progress Action
RDA/DRP/CEN/KDY/KUN/20 Samindra Construction
0%
Update

RDA/DRP/CEN/KDY/KUN/20

Madolkelle - Kabaragala - Kandenuwara Road 5/4 and 8/1

Samindra Construction

Kandy Kundasale Awarded
Current Progress
Overall 0%
Critical Issues
Mobilization 0%
Surveying 0%
Site Clearing 0%
Base Construction 0%
Asphalt 0%
Structure Construction 0%
Drainage Construction 0%
Edit Progress
View Project