Physical Progress
Physical Progress
2026-08-11
1
Awarded Projects
1 / 1
In Progress
50.0%
Avg Progress
0
Overdue
| Contract No. | Contractor | Commencement Date | Completion Date | Overall Progress | Action |
|---|---|---|---|---|---|
| RDA/DRP/CEN/MTL/MTL/35 | Kanwel Constructions & C… | 2026-05-02 | 2026-10-30 |
50%
|
Update |
RDA/DRP/CEN/MTL/MTL/35
Rattota Gammaduwa Road B 392
Kanwel Constructions & Civil Engineering (Pvt) Ltd
Matale
Matale
Awarded
Current Progress
Overall
50%
Critical Issues
—
Mobilization
100%
Surveying
100%
Site Clearing
100%
Base Construction
0%
Asphalt
0%
Structure Construction
15%
Drainage Construction
27%