Dashboard
Physical Progress
Physical Progress
2026-08-11
1
Awarded Projects
1 / 1
In Progress
45.0%
Avg Progress
1
Overdue
| Contract No. | Contractor | Commencement Date | Completion Date | Overall Progress | Action |
|---|---|---|---|---|---|
| RDA/DRP/CEN/NUE/NUE/66 | KSJ Construction (Pvt) L… | 2026-05-02 | 2026-07-31 |
45%
|
Update |
RDA/DRP/CEN/NUE/NUE/66
Nuwara Eliya Town Road (B331)
KSJ Construction (Pvt) Ltd
NuwaraEliya
NuwaraEliya
Awarded
Current Progress
Overall
45%
Critical Issues
—
Mobilization
100%
Surveying
100%
Site Clearing
100%
Base Construction
0%
Asphalt
0%
Structure Construction
50%
Drainage Construction
30%