Dashboard Physical Progress

Physical Progress

1

Awarded Projects

1 / 1

In Progress

45.0%

Avg Progress

1

Overdue

Awarded Projects Summary

1 projects

XLSX Clear Showing 1 of 1
Contract No. Contractor Commencement Date Completion Date Overall Progress Action
RDA/DRP/CEN/NUE/NUE/66 KSJ Construction (Pvt) L… 2026-05-02 2026-07-31
45%
Update

RDA/DRP/CEN/NUE/NUE/66

Nuwara Eliya Town Road (B331)

KSJ Construction (Pvt) Ltd

NuwaraEliya NuwaraEliya Awarded
Current Progress
Overall 45%
Critical Issues
Mobilization 100%
Surveying 100%
Site Clearing 100%
Base Construction 0%
Asphalt 0%
Structure Construction 50%
Drainage Construction 30%
Edit Progress
View Project