Physical Progress

25 Jun 2026

Physical Progress

Manage physical progress for 1 awarded projects

RDA/DRP/CEN/NUE/NUE/69

Ulapane Pussallawa Road (B431)

Southern group civil construction (Pvt) Ltd

NuwaraEliya NuwaraEliya Awarded
Current Progress
Overall 22%
Critical Issues
Mobilization 100%
Surveying 80%
Site Clearing 80%
Base Construction 0%
Asphalt 0%
Structure Construction 15%
Drainage Construction 33%
Edit Progress
View Project