Physical Progress
Physical Progress
2026-08-11
1
Awarded Projects
1 / 1
In Progress
15.0%
Avg Progress
0
Overdue
| Contract No. | Contractor | Commencement Date | Completion Date | Overall Progress | Action |
|---|---|---|---|---|---|
| RDA/DRP/CEN/NUE/NUR/97 | Jayawansa Construction (… | 2026-06-17 | 2026-09-15 |
15%
|
Update |
RDA/DRP/CEN/NUE/NUR/97
Nawalapitiya Ginigathena Road (B-319)
Jayawansa Construction (Pvt) Ltd
NuwaraEliya
Norwood
Awarded
Current Progress
Overall
15%
Critical Issues
—
Mobilization
100%
Surveying
0%
Site Clearing
20%
Base Construction
0%
Asphalt
0%
Structure Construction
0%
Drainage Construction
0%