DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 18 awarded projects

2026-11-04
23:54:45Live2026-11-04
0 / 18Advance Pendingpending advance projects / total projects
0 / 18IPC Pendingpending IPC projects / total projects
0 / 18Advance Paidadvance paid projects / total projects
0 / 18IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Nuwara Eliya · District

579Projects23,829.3Contract Mn
Nuwara Eliya 18 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn6494.6111.923% of contract382.7——————66.7%0.0%
Tender Below 50Mn398.847.048% of contract51.8——————100.0%0.0%
DL Stage 013184.3186.1101% of contract-1.8——————100.0%0.0%
DL Stage 02140.745.3111% of contract-4.6——————100.0%0.0%
DL Stage 035126.760.147% of contract66.6——————100.0%0.0%
DL Stage 0400.0——————————
PIU00.0——————————
Nuwara Eliya18945.1450.548% of contract494.6000.0000.088.9%0.0%
Tender Above 50Mn6 projects494.6Mn
23% paid111.9 Mn
Pending382.7Mn
Planned Fin66.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn3 projects98.8Mn
48% paid47.0 Mn
Pending51.8Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 013 projects184.3Mn
101% paid186.1 Mn
Pending—
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project40.7Mn
111% paid45.3 Mn
Pending—
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 035 projects126.7Mn
47% paid60.1 Mn
Pending66.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Nuwara Eliya18 projects945.1Mn
48% paid450.5 Mn
Pending494.6Mn
Planned Fin88.9%
Actual Fin0.0%

Avg Physical Progress per Province · Nuwara Eliya

Graphs reflect current view:18 awarded · Nuwara Eliya
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 291 projects (filtered from 579)

31–40/291 (filtered from 579)
ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
31RR/RDA/STA II/16/25/04/AKK/A…
Lahugala Hulannuge Roundabout road
Zaka Engineering Consultancy
26,597,958.20————————————
32RR/RDA/16/25/10KM/06/AKK/AKK
Hulannuge School Road
Gama Construction & Consultant pvt Ltd
11,406,166.73————————————
33RR/RDA/16/25/10KM/09/AKK/AKK
Road behind Necode Institute (Navatkadu Akkarapattu)
SMA Careem Engineering Consultancy Servi…
15,228,903.25————————————
34RR/RDA/15/25/01/EP/BTC
Concreting to Vipulananthar road
SSK Construction
29,074,090.89————————————
35RR/RDA/15/25/07/EP/BTC
Concreting to Thakwa masjith Cross Road
Nazeeha Hardware and Construction
22,206,567.30————————————
36RR/RDA/17/25/01/EP/TRN
Pillayar Road Renovation
Rina Construction
23,425,921.56————————————
37RR/RDA/17/25/02/EP/TRN
Kathirkamathambi Road
Fareed
28,809,738.00————————————
38RR/RDA/17/25/03/EP/TRN
Hospital Road
Pragash Construction
18,557,253.77————————————
39RR/RDA/17/25/07/EP/TRN
Kanthamalawa Main Road
SSK Construction
9,161,570.00————————————
40RR/RDA/17/25/10/EP/TRN
From Medagama temple to Peramaduwa
Soyuru Sampath Construction & Suppliers
24,197,635.00————————————
Total8,230,991,569.86——————————
—Mn
0%
—Mn
0%
Showing 31–40 of 291 projects · page 4/30