DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 23 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:23 awarded · Kegalle

Portfolio Breakdown · Kegalle · District

579Awarded739Total
Kegalle 23 awarded of 29 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn63350%494.2210.0108.0132.163% of contract66.7%90.0%
Tender Below 50Mn1715288%564.7355.0290.6113.532% of contract66.7%87.9%
DL Stage 01220100%67.671.071.037.753% of contract100.0%100.0%
DL Stage 02220100%63.063.063.047.475% of contract100.0%100.0%
DL Stage 03110100%7.07.07.00.913% of contract100.0%100.0%
DL Stage 040000%0.00.0————
PIU0000%0.00.0————
Not Specified1010%0.00.0————
Kegalle2923679%1,196.5706.0539.5331.747% of contract73.9%90.8%

Avg Physical Progress per EE Division · Kegalle

Portfolio Timeline· 22 scheduled projects · Kegalle Toggle
Portfolio · Awarded Works

Awarded Projects

4 projects

4/4 (filtered)

Filter awarded works

4 matching projects1 active

ActiveDelay
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/25/25/03/SBP/KGLRR/RDA/25/25/03
From Kehelpannala Junction to Pahala Kabawita Road
95%
71,786,959.2096,478,103.45Awarded
2RR/RDA/25/25/15/SBP/KGLRR/RDA/25/25/15
Moraliya Gagaboda Road
90%
38,093,328.6248,285,852.39Awarded
3RR/RDA/25/25/38/SBP/KGLRR/RDA/25/25/38
Development of the road near the closed tea factory on Edurapola Watta main road
95%
22,209,331.1030,599,205.16Awarded
4RR/RDA/25/25/39/SBP/KGLRR/RDA/25/25/39
Development of Gatayamulla Jagatpura Pannala Rasnadeniya road
95%
31,491,651.4032,775,992.83Awarded
Showing 1–4 of 4
Per page:
Source: DRRRP • 29 projects • Data updated 2026-11-02 10:30 • 10:37:54