Ditwah (CP)

Project Monitoring Dashboard

Comprehensive overview of 3 infrastructure projects under the Disaster Rehabilitation Programme. · Nalanda EE

Updated 2026-09-24 15:27Live
Graphs reflect current view: 3 awarded · Nalanda EE · Matale

Portfolio at a Glance

3 awarded works · Nalanda EE · Matale

Mobilization Pending 2026-09-24 15:27
100% awarded

0

Awarded

3 total projects in portfolio

112.6M

112.6 Mn

Contract Value

Spent 15.2% Remaining 84.8%
Avg
46%

2

works in progress

0 completed

Avg Progress

17.1M

17.1 Mn

Total Expenditure (excl. VAT)

15.2% of contract excl. VAT
33.3%

0

Kick Off Pending

1 / 3 awarded

33.3%

0

Mobilization Pending

1 / 3 awarded

33.3%

0

Works Not Started

1 / 3 awarded

0%

0

Completed

0 / 3 awarded

Portfolio Breakdown · Nalanda EE · Matale · Consultant

9Awarded 10Total
Nalanda EE 3 awarded of 3 Open filtered view
Category Total Awarded Pending Awarded % Estimate LKR Mn Contract LKR Mn Planned Exp Mn Actual Exp ex-VAT Planned % Actual % Kick Off Pending Mobilization Pending Works Not Started
Emergency 3 3 0 100% 125.2 112.6 36.0 17.1 15% of contract 54.3% 46.0% 1 1 1
DC 0 0 0 0% 0.0 0.0 — — — — — — —
DC - Slope 0 0 0 0% 0.0 0.0 — — — — — — —
PD(CP) 0 0 0 0% 0.0 0.0 — — — — — — —
Nalanda EE 3 3 0 100% 125.2 112.6 36.0 17.1 15% of contract 54.3% 46.0% 1 1 1

Project-wise Progress · Nalanda EE · Matale (3 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear

Project-wise Physical Progress: Actual vs Planned (%) · Nalanda EE · Matale

Average Physical Progress by EE Division · Nalanda EE · Matale

Average District-wise Physical Progress (Matale District)

Matale district baseline — all categories (consultant filter excluded for comparison)

At-Risk Projects · Nalanda EE · Matale

0

No at-risk projects

No open high/critical issues or overdue projects in this view

Portfolio Timeline · 2 scheduled projects · Nalanda EE · Matale Toggle
2026-06-18 today 2026-11-18
Portfolio · Awarded Works

Awarded Projects

1 projects

1/1 (filtered)
Active filters: Mobilization Pending
Contract No. Contract Name Progress Amount Status
RDA/DRP/CEN/MTL/NAL/48R
Rehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
0%
50,471,466.08 Awarded
Showing 1–1 of 1
Per page:
Source: ditwah_projects • 3 projects • Data updated 2026-09-24 15:27 • 18:08:59