Ditwah (CP)

Project Monitoring Dashboard

Comprehensive overview of 5 infrastructure projects under the Disaster Rehabilitation Programme.

Updated 2026-09-24 15:27Live
Graphs reflect current view: 5 awarded · Nuwara Eliya · EE: Norwood

Portfolio at a Glance

5 awarded works · Nuwara Eliya · EE: Norwood

Kick Off Pending 2026-09-24 15:27
45.5% awarded

0

Awarded

11 total projects in portfolio

1,348.3M

1,348.3 Mn

Contract Value

Spent 1% Remaining 99%
Avg
15.8%

5

works in progress

0 completed

Avg Progress

14.1M

14.1 Mn

Total Expenditure (excl. VAT)

1% of contract excl. VAT
0%

0

Kick Off Pending

0 / 5 awarded

0%

0

Mobilization Pending

0 / 5 awarded

0%

0

Works Not Started

0 / 5 awarded

0%

0

Completed

0 / 5 awarded

Portfolio Breakdown · Nuwara Eliya · EE: Norwood · EE Office

11Awarded 29Total
Norwood 5 awarded of 11 Open filtered view
Category Total Awarded Pending Awarded % Estimate LKR Mn Contract LKR Mn Planned Exp Mn Actual Exp ex-VAT Planned % Actual %
Emergency 3 3 0 100% 435.8 369.1 210.9 14.1 4% of contract 78.7% 24.3%
DC 6 2 4 33% 2,767.1 979.2 24.4 — 7.4% 3.0%
DC - Slope 0 0 0 0% 0.0 0.0 — — — —
PD(CP) 2 0 2 0% 62.4 0.0 — — — —
Norwood 11 5 6 45% 3,265.3 1,348.3 235.3 14.1 1% of contract 50.2% 15.8%

Avg Physical Progress per EE Division · Nuwara Eliya · EE: Norwood

Portfolio Timeline · 5 scheduled projects · Nuwara Eliya · EE: Norwood Toggle
Portfolio · Awarded Works

Awarded Projects

2 projects

2/2 (filtered)
Active filters: Kick Off Pending
Contract No. Contract Name Progress Amount Status
RDA/DRP/CEN/NUE/NUE/60R
Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850)
0%
336,313,078.73 Awarded
RDA/DC/DRP/CP/NE/NE/04
REHABILITAION/ IMPROVEMENTS OF LADY MACALUMS DRIVE ROAD (2+850 - 5+600KM)
0%
47,725,380.00 Awarded
Showing 1–2 of 2
Per page:
Source: ditwah_projects • 11 projects • Data updated 2026-09-24 15:27 • 18:12:54