Comprehensive overview of 31 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:31 awarded · EE: Trincomalee

Portfolio Breakdown · EE: Trincomalee · EE Office

567Awarded667Total
Trincomalee 31 awarded of 37 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn84450%788.5304.7284.346.715% of contract95.2%40.5%
Tender Below 50Mn2624292%745.7521.5—195.738% of contract0.0%61.5%
DL Stage 01110100%32.232.232.230.194% of contract100.0%100.0%
DL Stage 02110100%15.415.415.415.6101% of contract100.0%100.0%
DL Stage 030000%0.00.0————
DL Stage 04110100%43.243.243.228.967% of contract100.0%90.0%
Not Specified0000%0.00.0————
Trincomalee3731684%1,625.1917.1375.1317.035% of contract22.0%62.2%

Avg Physical Progress per EE Division · EE: Trincomalee

Portfolio Timeline· 31 scheduled projects · EE: Trincomalee Toggle
Portfolio · Awarded Works

Awarded Projects

9 projects

9/9 (filtered)

Filter awarded works

9 matching projects1 active

ActiveDelayed only
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/17/25/09/EP/TRNRR/RDA/17/25/09
School-Galmetiyawa Main Internal Road
50%
53,122,107.5077,200,000.00Awarded
2RR/RDA/17/25/11/EP/TRNRR/RDA/17/25/11
Development of Road from near the Fair
15%
25,280,343.6037,892,493.36Awarded
3RR/RDA/17/25/19/EP/TRNRR/RDA/17/25/19
Periya Suwami Kovil Road-Concrete
20%
25,774,146.0039,914,113.43Awarded
4RR/RDA/SP/17/25/03/EP/TRNRR/RDA/SP/17/25/03
Hajra Road (Alhira Jalaira Road)
40%
38,692,742.0051,948,669.36Awarded
5RR/RDA/17/25/10KM/04/EP/TRNRR/RDA/17/25/10KM/04
Kajuwaththa gama meda road
5%
22,770,000.0029,466,015.30Awarded
6RR/RDA/17/25/10KM/06/EP/TRNRR/RDA/17/25/10KM/06
Budu pilima and 4th lane road
15%
17,520,285.6428,351,870.49Awarded
7RR/RDA/17/25/10KM/08/EP/TRNRR/RDA/17/25/10KM/08
Paththini Amman Kevil road
25%
30,365,709.0046,089,014.73Awarded
8RR/RDA/17/25/10KM/09/EP/TRNRR/RDA/17/25/10KM/09
Bazar mosque road
40%
32,616,074.7044,293,054.87Awarded
9RR/RDA/17/25/08—
Concreting of Play Ground Road Mahadiulwewa Stage II
90%
43,210,842.7543,210,842.75Awarded
Showing 1–9 of 9
Per page:
Source: DRRRP • 37 projects • Data updated 2026-11-02 10:30 • 09:49:00