DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 15 awarded projects

2026-11-04
11:44:58Live2026-11-04
0 / 15Advance Pendingpending advance projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

Portfolio Breakdown — Financial (Exclusive Vat) · Emergency · Team Leader · Consultant

31Projects4,646.7Contract Mn
Reset
Team Leader 15 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency152,082.2381.018% of contract43.877213.4156109.661.9%15.5%
DC - Roads00.0——————————
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
Team Leader152,082.2381.018% of contract43.877213.4156109.661.9%15.5%
Emergency15 projects2,082.2Mn
18% paid381.0 Mn
Pending43.8Mn
Planned Fin61.9%
Actual Fin15.5%
Advance & IPC
Advance paid7 proj · 213.4 Mn
IPC paid6 proj · 109.6 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Team Leader15 projects2,082.2Mn
18% paid381.0 Mn
Pending43.8Mn
Planned Fin61.9%
Actual Fin15.5%

Avg Physical Progress per Province · Emergency · Team Leader

Project-wise Financials · Emergency · Team Leader (92 Projects)

Clear

Project-wise Contract Value vs. Expenditure and Pending Payments · Emergency · Team Leader (Mn · incl. VAT)

Scroll horizontally — 92 projects

Team Leader · Emergency · Team Leader (Mn · incl. VAT)

Kandy District Summary (Mn · incl. VAT)

District baseline — overall Emergency (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:15 awarded · Emergency · Team Leader
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 92 projects (filtered from 171)

1–10/92 (filtered from 171)

Filter financial register

92 matching projects1 active

ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
1RDA/DRP/CEN/KDY/KAD/11
Rehabilitation / Improvement of Nawalapitiya - Dolosbage Road ( B -318) ( 10+50…
Tiasa Construction (Pvt) Ltd
193,404,194.9633,346,525.5439,348,900.14——15,954,390.2918,826,180.55——49,300,915.83—
58.18Mn
30.1%
Watch
58.18Mn
30.1%
2RDA/DRP/CEN/KDY/KUN/21
Improvement of Pitiyegedara-Waththegama-Iriyagasthenna Road (0+000-5+400)
Jayasinghe Construction (Pvt) Ltd
257,721,453.9646,231,491.4254,553,159.88————8,483,606.8010,010,656.0246,231,491.428,483,606.80
54.55Mn
21.2%
Watch
64.56Mn
25.1%
3RDA/DRP/CEN/KDY/KUN/22
Improvement to Damaged Road Section on Weeragantota - Randenigala Road. (From CH…
SD Civil Construction (Pvt) Ltd
224,968,435.7840,192,882.6347,427,601.50——34,738,972.1940,991,987.18——74,931,854.82—
88.42Mn
39.3%
Watch
88.42Mn
39.3%
4RDA/DRP/CEN/KDY/KUN/25
Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LH…
S N O Builders (Pvt) Ltd
157,909,825.0128,346,587.8033,448,973.60——25,922,264.5430,502,481.3810,705,591.4711,041,226.8354,268,852.3410,705,591.47
63.95Mn
40.5%
On Track
74.99Mn
47.5%
5RDA/DRP/CEN/KDY/KUN/27
Improvement to Structures on Kandy - Jaffna Road 6+500 - 9+910
Gihan Enterprise
113,434,139.4020,128,022.3723,751,066.40——2,934,355.863,462,539.91——23,062,378.23—
27.21Mn
24%
Watch
27.21Mn
24%
6RDA/DRP/CEN/MTL/MTL/32
Rehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodap…
Lahiru Construction and Consultants (Pvt…
292,279,354.0852,461,047.8461,904,036.46——23,455,869.7327,677,926.2714,693,549.1617,243,721.7475,916,917.5714,693,549.16
89.58Mn
30.6%
Watch
106.83Mn
36.5%
7RDA/DRP/CEN/MTL/MTL/33
Rehabilitation / Improvement of Wattegama Matale Road (5+280 - 13+160) and Ukuwe…
Jayasinghe Construction (Pvt) Ltd
165,006,430.7929,068,239.7134,300,522.86——————29,068,239.71—
34.30Mn
20.8%
Watch
34.30Mn
20.8%
8RDA/DRP/CEN/MTL/MTL/35
Rehabilitation / Improvement of Rattota Gammaduwa Road (7+100 - 11+260)
Kanwel Constructions & Civil Engineering…
266,607,902.1546,351,528.3654,694,803.46——29,493,532.2434,802,368.04——75,845,060.60—
89.50Mn
33.6%
Watch
89.50Mn
33.6%
9RDA/DRP/CEN/MTL/NAL/51
Rehabilitation /Improvement of Retaining wall , drains and shoulder construction…
Platinum Holdings Lanka (Private) Limite…
17,458,592.782,700,844.133,186,956.07——2,081,765.362,456,483.122,488,679.182,936,641.434,782,609.492,488,679.18
5.64Mn
32.3%
Watch
8.58Mn
49.1%
10RDA/DRP/CEN/NUE/HAN/57
Rehabilitation / Improvement of Keerthibandarapura Naranthalawa Road ( B -511…
Samindra Construction
47,755,538.967,835,575.379,245,978.94——————7,835,575.37—
9.25Mn
19.4%
Behind
9.25Mn
19.4%
Total16,799,029,680.142,276,780,837.162,686,401,372.89——905,188,809.071,068,036,979.0652,935,451.9660,777,795.943,181,969,646.2352,935,451.96
3,754.44Mn
22.3%
3,815.22Mn
22.7%
Showing 1–10 of 92 projects · page 1/10