Financial Dashboard

Monitor financial performance across 57 awarded projects

2026-11-04
10:39:04Live2026-11-04
0 / 57Advance Pendingpending advance projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

Portfolio Breakdown — Financial (Exclusive Vat) · Central Province · Province

171Projects34,005.3Contract Mn
Reset
Central Province 57 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency314,646.7969.921% of contract73.61919566.43213255.674.4%17.7%
DC - Roads85,116.6————————0.5%0.0%
DC - Slope103,258.5————————0.3%0.0%
PD(CP) - Slope8177.7————————0.0%0.0%
Central Province5713,199.5969.97% of contract73.61919566.43213255.640.6%6.2%
Emergency31 projects4,646.7Mn
21% paid969.9 Mn
Pending73.6Mn
Planned Fin74.4%
Actual Fin17.7%
Advance & IPC
Advance paid19 proj · 566.4 Mn
IPC paid13 proj · 255.6 Mn
Open filtered view
DC - Roads8 projects5,116.6Mn
0% paid0.0 Mn
Pending—
Planned Fin0.5%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope10 projects3,258.5Mn
0% paid0.0 Mn
Pending—
Planned Fin0.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope8 projects177.7Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Central Province57 projects13,199.5Mn
7% paid969.9 Mn
Pending73.6Mn
Planned Fin40.6%
Actual Fin6.2%

Avg Physical Progress per Province · Central Province

Graphs reflect current view:57 awarded · Central Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 3 projects (filtered from 171)

1–3/3 (filtered from 171)

Filter financial register

3 matching projects1 active

ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
1RDA/DRP/SAB/RAT/PEL/19
Rehabilitation / Improvement and Retaining wall Construction of (Galle - Deniya…
Solinro Builders
95,082,996.5816,436,817.5619,395,444.72——38,373,715.8845,280,984.74——54,810,533.44—
64.68Mn
68%
On Track
64.68Mn
68%
2RDA/DRP/NCP/POL/POL/08
Rehabilitation / Improvement and Reconstruction of 31/1 Culvert, Construction Of…
Sawsiri Construction
17,459,311.37————9,866,233.2111,642,155.19——9,866,233.21—
11.64Mn
66.7%
On Track
11.64Mn
66.7%
3RDA/DRP/SP/GAL/GAL/02
Rehabilitation of Gabbion Walls along Galle - Deniyaya - Madampe Road (from7+700…
Ceylon Construction Industry Development…
8,991,852.34————————————
Total121,534,160.2916,436,817.5619,395,444.72——48,239,949.0956,923,139.93——64,676,766.65—
76.32Mn
62.8%
76.32Mn
62.8%