Stabilizing Slopes — Securing Futures
Last Updated
2026-09-24 15:27 · 18:06:00 LIVE
Graphs reflect current view:
3 awarded · Nalanda EE · EE: Nalanda
100% awarded
0
Awarded
3 total projects in portfolio
Awarded projects3
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
RDA/DRP/CEN/MTL/NAL/49Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
RDA/DRP/CEN/MTL/NAL/51Bowathenna Access Road (B-064) (0+000-2+410)
Click to filter the awarded table
112.6M
112.6 Mn
Contract Value
Awarded projects3
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
RDA/DRP/CEN/MTL/NAL/49Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
RDA/DRP/CEN/MTL/NAL/51Bowathenna Access Road (B-064) (0+000-2+410)
Click to filter the awarded table
Avg
46%
2
works in progress
0 completed
Avg Progress
Awarded projects3
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
RDA/DRP/CEN/MTL/NAL/49Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
RDA/DRP/CEN/MTL/NAL/51Bowathenna Access Road (B-064) (0+000-2+410)
Click to filter the awarded table
17.1M
17.1 Mn
Total Expenditure (excl. VAT)
Awarded projects3
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
RDA/DRP/CEN/MTL/NAL/49Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
RDA/DRP/CEN/MTL/NAL/51Bowathenna Access Road (B-064) (0+000-2+410)
Click to filter the awarded table
33.3%
0
Kick Off Pending
1 / 3 awarded
Kick Off Pending1
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
Click to filter the awarded table
33.3%
0
Mobilization Pending
1 / 3 awarded
Mobilization Pending1
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
Click to filter the awarded table
33.3%
0
Works Not Started
1 / 3 awarded
Works Not Started1
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
Click to filter the awarded table
0%
0
Completed
0 / 3 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · Nalanda EE · EE: Nalanda · EE Office
Project-wise Progress · Nalanda EE · EE: Nalanda (3 projects in one graph)
Physical Actual vs Planned per project • Click bar to open project
Project-wise Physical Progress: Actual vs Planned (%) · Nalanda EE · EE: Nalanda
Average Physical Progress by EE Division · Nalanda EE · EE: Nalanda
Average District-wise Physical Progress (Matale District)
Matale district baseline — all categories · EE: Nalanda (consultant filter excluded for comparison)
At-Risk Projects · Nalanda EE · EE: Nalanda
No at-risk projects
No open high/critical issues or overdue projects in this view
Portfolio Timeline · 2 scheduled projects · Nalanda EE · EE: Nalanda Toggle
2026-06-18
today
2026-11-18
Portfolio · Awarded Works
Awarded Projects
1 projects
| Contract No. | Contract Name | Progress | Amount | Status |
|---|---|---|---|---|
| RDA/DRP/CEN/MTL/NAL/48R | Rehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950) |
0%
|
50,471,466.08 | Awarded |
Showing 1–1 of 1