Ditwah (CP)
Project Monitoring Dashboard
Comprehensive overview of 3 infrastructure projects
under the Disaster Rehabilitation Programme.
Updated 2026-09-24 15:27Live
Stabilizing Slopes — Securing Futures
Last Updated
2026-09-24 15:27 · 17:19:22 LIVE
Graphs reflect current view:
3 awarded · EE: Nalanda
60% awarded
0
Awarded
5 total projects in portfolio
Awarded projects3
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
RDA/DRP/CEN/MTL/NAL/49Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
RDA/DRP/CEN/MTL/NAL/51Bowathenna Access Road (B-064) (0+000-2+410)
Click to filter the awarded table
112.6M
112.6 Mn
Contract Value
Awarded projects3
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
RDA/DRP/CEN/MTL/NAL/49Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
RDA/DRP/CEN/MTL/NAL/51Bowathenna Access Road (B-064) (0+000-2+410)
Click to filter the awarded table
Avg
46%
2
works in progress
0 completed
Avg Progress
Awarded projects3
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
RDA/DRP/CEN/MTL/NAL/49Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
RDA/DRP/CEN/MTL/NAL/51Bowathenna Access Road (B-064) (0+000-2+410)
Click to filter the awarded table
17.1M
17.1 Mn
Total Expenditure (excl. VAT)
Awarded projects3
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
RDA/DRP/CEN/MTL/NAL/49Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
RDA/DRP/CEN/MTL/NAL/51Bowathenna Access Road (B-064) (0+000-2+410)
Click to filter the awarded table
33.3%
0
Kick Off Pending
1 / 3 awarded
Kick Off Pending1
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
Click to filter the awarded table
33.3%
0
Mobilization Pending
1 / 3 awarded
Mobilization Pending1
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
Click to filter the awarded table
33.3%
0
Works Not Started
1 / 3 awarded
Works Not Started1
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
Click to filter the awarded table
0%
0
Completed
0 / 3 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · EE: Nalanda · EE Office
Avg Physical Progress per EE Division · EE: Nalanda
At-Risk Projects · EE: Nalanda
No at-risk projects
No open high/critical issues or overdue projects in this view
Portfolio Timeline · 2 scheduled projects · EE: Nalanda Toggle
2026-06-18
today
2026-11-18
Portfolio · Awarded Works
Awarded Projects
10 projects
| Contract No. | Contract Name | Progress | Amount | Status |
|---|---|---|---|---|
| RDA/DRP/CEN/KDY/KAN/14 | Rehabilitation /Improvement of Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370) |
0%
|
74,836,014.77 | Awarded |
| RDA/DRP/CEN/KDY/KDY/19 | Rehabilitation / Improvement of Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000) |
0%
|
67,935,586.77 | Awarded |
| RDA/DRP/CEN/MTL/MTL/31R | Rehabilitation / Improvement of Matale - Udupihilla Road (AB026) (0+000 - 6+000) |
0%
|
63,704,849.78 | Awarded |
| RDA/DRP/CEN/MTL/NAL/48R | Rehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950) |
0%
|
50,471,466.08 | Awarded |
| RDA/DRP/CEN/NUE/NUE/60R | Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850) |
0%
|
336,313,078.73 | Awarded |
| RDA/DC/DRP/CP/NE/NE/04 | REHABILITAION/ IMPROVEMENTS OF LADY MACALUMS DRIVE ROAD (2+850 - 5+600KM) |
0%
|
47,725,380.00 | Awarded |
| RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/01 | Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 0+030 km |
0%
|
22,481,370.00 | Awarded |
| RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/14 | Construction of Slope failure mitigation measures along Atabage-Ulapane Road (B 490) at Ch 4+000 km |
0%
|
24,796,315.46 | Awarded |
| RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/29 | Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 21+550 km |
0%
|
28,806,688.50 | Awarded |
| RDA/DC/DRP/SLOPE/PD(CP)/KDY/KUN/18,19&20 | Construction of Slope failure mitigation measures along Kandy – Mahiyangana – Padiyatalawa Road (A026) at Culvert No 47/5 Culvert No47/10, Culvert No 50/6-51+200 km and Culvert No 52/3-Culvert No 52/5 |
0%
|
19,636,680.00 | Awarded |
Showing 1–10 of 10
Source: ditwah_projects • 5 projects • Data updated 2026-09-24 15:27 • 17:19:22
System live • Central Province • 1 districts