Ditwah (CP)

Project Monitoring Dashboard

Comprehensive overview of 3 infrastructure projects under the Disaster Rehabilitation Programme.

Updated 2026-09-24 15:27Live
Graphs reflect current view: 3 awarded · Matale · EE: Nalanda

Portfolio at a Glance

3 awarded works · Matale · EE: Nalanda

Kick Off Pending 2026-09-24 15:27
60% awarded

0

Awarded

5 total projects in portfolio

112.6M

112.6 Mn

Contract Value

Spent 15.2% Remaining 84.8%
Avg
46%

2

works in progress

0 completed

Avg Progress

17.1M

17.1 Mn

Total Expenditure (excl. VAT)

15.2% of contract excl. VAT
33.3%

0

Kick Off Pending

1 / 3 awarded

33.3%

0

Mobilization Pending

1 / 3 awarded

33.3%

0

Works Not Started

1 / 3 awarded

0%

0

Completed

0 / 3 awarded

Portfolio Breakdown · Matale · EE: Nalanda · EE Office

9Awarded 15Total
Nalanda 3 awarded of 5 Open filtered view
Category Total Awarded Pending Awarded % Estimate LKR Mn Contract LKR Mn Planned Exp Mn Actual Exp ex-VAT Planned % Actual %
Emergency 3 3 0 100% 125.2 112.6 36.0 17.1 15% of contract 54.3% 46.0%
DC 2 0 2 0% 247.6 0.0 — — — —
DC - Slope 0 0 0 0% 0.0 0.0 — — — —
PD(CP) 0 0 0 0% 0.0 0.0 — — — —
Nalanda 5 3 2 60% 372.8 112.6 36.0 17.1 15% of contract 54.3% 46.0%

Avg Physical Progress per EE Division · Matale · EE: Nalanda

At-Risk Projects · Matale · EE: Nalanda

0

No at-risk projects

No open high/critical issues or overdue projects in this view

Portfolio Timeline · 2 scheduled projects · Matale · EE: Nalanda Toggle
2026-06-18 today 2026-11-18
Portfolio · Awarded Works

Awarded Projects

1 projects

1/1 (filtered)
Active filters: Kick Off Pending
Contract No. Contract Name Progress Amount Status
RDA/DRP/CEN/MTL/NAL/48R
Rehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
0%
50,471,466.08 Awarded
Showing 1–1 of 1
Per page:
Source: ditwah_projects • 5 projects • Data updated 2026-09-24 15:27 • 18:08:36