Ditwah (CP)
Project Monitoring Dashboard
Comprehensive overview of 3 infrastructure projects
under the Disaster Rehabilitation Programme.
Updated 2026-09-24 15:27Live
Stabilizing Slopes — Securing Futures
Last Updated
2026-09-24 15:27 · 18:04:34 LIVE
Graphs reflect current view:
3 awarded · Matale · EE: Nalanda
60% awarded
0
Awarded
5 total projects in portfolio
Awarded projects3
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
RDA/DRP/CEN/MTL/NAL/49Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
RDA/DRP/CEN/MTL/NAL/51Bowathenna Access Road (B-064) (0+000-2+410)
Click to filter the awarded table
112.6M
112.6 Mn
Contract Value
Awarded projects3
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
RDA/DRP/CEN/MTL/NAL/49Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
RDA/DRP/CEN/MTL/NAL/51Bowathenna Access Road (B-064) (0+000-2+410)
Click to filter the awarded table
Avg
46%
2
works in progress
0 completed
Avg Progress
Awarded projects3
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
RDA/DRP/CEN/MTL/NAL/49Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
RDA/DRP/CEN/MTL/NAL/51Bowathenna Access Road (B-064) (0+000-2+410)
Click to filter the awarded table
17.1M
17.1 Mn
Total Expenditure (excl. VAT)
Awarded projects3
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
RDA/DRP/CEN/MTL/NAL/49Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
RDA/DRP/CEN/MTL/NAL/51Bowathenna Access Road (B-064) (0+000-2+410)
Click to filter the awarded table
33.3%
0
Kick Off Pending
1 / 3 awarded
Kick Off Pending1
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
Click to filter the awarded table
33.3%
0
Mobilization Pending
1 / 3 awarded
Mobilization Pending1
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
Click to filter the awarded table
33.3%
0
Works Not Started
1 / 3 awarded
Works Not Started1
RDA/DRP/CEN/MTL/NAL/48RBelaganwewa- Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
Click to filter the awarded table
0%
0
Completed
0 / 3 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · Matale · EE: Nalanda · EE Office
Avg Physical Progress per EE Division · Matale · EE: Nalanda
At-Risk Projects · Matale · EE: Nalanda
No at-risk projects
No open high/critical issues or overdue projects in this view
Portfolio Timeline · 2 scheduled projects · Matale · EE: Nalanda Toggle
2026-06-18
today
2026-11-18
Portfolio · Awarded Works
Awarded Projects
2 projects
| Contract No. | Contract Name | Progress | Amount | Status |
|---|---|---|---|---|
| RDA/DRP/CEN/MTL/MTL/31R | Rehabilitation / Improvement of Matale - Udupihilla Road (AB026) (0+000 - 6+000) |
0%
|
63,704,849.78 | Awarded |
| RDA/DRP/CEN/MTL/NAL/48R | Rehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950) |
0%
|
50,471,466.08 | Awarded |
Showing 1–2 of 2
Source: ditwah_projects • 5 projects • Data updated 2026-09-24 15:27 • 18:04:34
System live • Central Province • 1 districts