DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 17 awarded projects

2026-11-04
19:05:39Live2026-11-04
0 / 17Advance Pendingpending advance projects / total projects
0 / 17IPC Pendingpending IPC projects / total projects
6 / 17IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

Portfolio Breakdown — Financial (Exclusive Vat) · Western Province · Province

171Projects34,005.3Contract Mn
Reset
Western Province 17 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency162,880.4449.216% of contract—1111324.610656.1100.0%13.2%
DC - Roads1666.6————————0.0%0.0%
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
Western Province173,547.0449.213% of contract0.01111324.610656.194.1%10.7%
Emergency16 projects2,880.4Mn
16% paid449.2 Mn
Pending—
Planned Fin100.0%
Actual Fin13.2%
Advance & IPC
Advance paid11 proj · 324.6 Mn
IPC paid6 proj · 56.1 Mn
Open filtered view
DC - Roads1 project666.6Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Western Province17 projects3,547.0Mn
13% paid449.2 Mn
Pending0.0Mn
Planned Fin94.1%
Actual Fin10.7%

Avg Physical Progress per Province · Western Province

Graphs reflect current view:17 awarded · Western Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 171 projects

41–50/171

Filter financial register

171 matching projects

S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
41RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenk…
Weebadda Construction
22,481,370.00————————————
42RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Galaha-Pupuressa-Delpiti…
J. Kodithuwakkuarachchi & Sons (Pvt) Ltd
17,724,816.00————————————
43RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Atabage-Ulapane Road (B …
Bandaranayake Builders and Construction
24,796,315.46————————————
44RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenk…
Weebadda Construction
28,806,688.50————————————
45RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Kandy-Mahiyangana-Padiya…
J. Kodithuwakkuarachchi & Sons (Pvt) Ltd
25,255,788.00————————————
46RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Kandy – Mahiyangana – Pa…
J. Kodithuwakkuarachchi & Sons (Pvt) Ltd
19,636,680.00————————————
47RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along KandyMahiyanganaPadiyath…
J. Kodithuwakkuarachchi & Sons (Pvt) Ltd
12,938,500.00————————————
48RDA/DC/DRP/SLOPE/PD(CP)/KDY/…
Construction of Slope failure mitigation measures along Aladeniya-Eriyagama Road…
Weebadda Construction
26,072,370.00————————————
49RDA/DRP/SAB/KEG/KEG/14
Rehabilitation / Improvement of Damaged Locations in Colombo Kandy Road from 56+…
Tudawe Brothers (Pvt) Ltd
261,228,130.7847,252,023.7855,757,388.06——20,746,920.9124,481,366.67——67,998,944.69—
80.24Mn
30.7%
Watch
80.24Mn
30.7%
50RDA/DRP/UVA/BAD/BAD/02
Rehabilitation / Improvement of Demodara SpringValley Badulla Road (16+145-20+80…
Priyankara Industries & Contractors
241,775,532.44————30,108,187.0035,527,660.65——30,108,187.00—
35.53Mn
14.7%
Behind
35.53Mn
14.7%
Total34,005,299,486.172,787,819,645.293,289,427,166.63113,218,826.01133,598,214.691,049,943,508.601,238,847,524.5163,842,351.1873,647,937.023,837,763,153.89177,061,177.19
4,528.27Mn
13.3%
4,735.52Mn
13.9%
Showing 41–50 of 171 projects · page 5/18