Ditwah (CP)

Project Monitoring Dashboard

Comprehensive overview of 16 infrastructure projects under the Disaster Rehabilitation Programme.

Updated 2026-09-24 15:27Live
Graphs reflect current view: 16 awarded · Kandy

Portfolio at a Glance

16 awarded works · Kandy

Completed 2026-09-24 15:27
53.3% awarded

0

Awarded

30 total projects in portfolio

1,854.3M

1,854.3 Mn

Contract Value

Spent 10.8% Remaining 89.2%
Avg
14.8%

11

works in progress

0 completed

Avg Progress

200.9M

200.9 Mn

Total Expenditure (excl. VAT)

10.8% of contract excl. VAT
25%

0

Kick Off Pending

4 / 16 awarded

31.3%

0

Mobilization Pending

5 / 16 awarded

37.5%

0

Works Not Started

6 / 16 awarded

0%

0

Completed

0 / 16 awarded

Portfolio Breakdown · Kandy · District

38Awarded 76Total
Kandy 16 awarded of 30 Open filtered view
Category Total Awarded Pending Awarded % Estimate LKR Mn Contract LKR Mn Planned Exp Mn Actual Exp ex-VAT Planned % Actual %
Emergency 12 11 1 92% 1,651.5 1,371.9 815.5 200.9 15% of contract 53.1% 21.3%
DC 2 0 2 0% 263.6 0.0 — — — —
DC - Slope 1 1 0 100% 0.0 386.7 9.7 — 6.2% 2.3%
PD(CP) 15 4 11 27% 309.5 95.7 — — 0.0% 0.0%
Kandy 30 16 14 53% 2,224.6 1,854.3 825.2 200.9 11% of contract 36.9% 14.8%

Avg Physical Progress per EE Division · Kandy

Portfolio Timeline · 12 scheduled projects · Kandy Toggle
Portfolio · Awarded Works

Awarded Projects

0 projects

0/0 (filtered)
Active filters: Completed
Contract No. Contract Name Progress Amount Status

No matches (Completed only)

Try adjusting your search or filter.

Clear filters
Showing 0–0 of 0
Per page:
Source: ditwah_projects • 30 projects • Data updated 2026-09-24 15:27 • 18:03:34