Ditwah (CP)

Project Monitoring Dashboard

Comprehensive overview of 9 infrastructure projects under the Disaster Rehabilitation Programme.

Updated 2026-09-24 15:27Live
Graphs reflect current view: 9 awarded · Matale

Portfolio at a Glance

9 awarded works · Matale

Completed 2026-09-24 15:27
60% awarded

0

Awarded

15 total projects in portfolio

1,458.1M

1,458.1 Mn

Contract Value

Spent 10.2% Remaining 89.8%
Avg
33.4%

8

works in progress

0 completed

Avg Progress

149.4M

149.4 Mn

Total Expenditure (excl. VAT)

10.2% of contract excl. VAT
11.1%

0

Kick Off Pending

1 / 9 awarded

11.1%

0

Mobilization Pending

1 / 9 awarded

22.2%

0

Works Not Started

2 / 9 awarded

0%

0

Completed

0 / 9 awarded

Portfolio Breakdown · Matale · District

38Awarded 76Total
Matale 9 awarded of 15 Open filtered view
Category Total Awarded Pending Awarded % Estimate LKR Mn Contract LKR Mn Planned Exp Mn Actual Exp ex-VAT Planned % Actual %
Emergency 10 9 1 90% 1,571.8 1,458.1 655.0 149.4 10% of contract 54.9% 33.4%
DC 5 0 5 0% 1,957.9 0.0 — — — —
DC - Slope 0 0 0 0% 0.0 0.0 — — — —
PD(CP) 0 0 0 0% 0.0 0.0 — — — —
Matale 15 9 6 60% 3,529.7 1,458.1 655.0 149.4 10% of contract 54.9% 33.4%

Avg Physical Progress per EE Division · Matale

Portfolio Timeline · 8 scheduled projects · Matale Toggle
Portfolio · Awarded Works

Awarded Projects

0 projects

0/0 (filtered)
Active filters: Completed
Contract No. Contract Name Progress Amount Status

No matches (Completed only)

Try adjusting your search or filter.

Clear filters
Showing 0–0 of 0
Per page:
Source: ditwah_projects • 15 projects • Data updated 2026-09-24 15:27 • 18:03:25