Comprehensive overview of 6 infrastructure projects
under the Disaster Rehabilitation Programme.
Updated 2026-09-24 15:27Live
Stabilizing Slopes — Securing Futures
Last Updated
2026-09-24 15:27 · 18:07:14 LIVE
Graphs reflect current view:
6 awarded · EE: Matale
60% awarded
0
Awarded
10 total projects in portfolio
Awarded projects6
RDA/DRP/CEN/MTL/MTL/31RMatale Udupihilla Road (AB 026)
RDA/DRP/CEN/MTL/MTL/32Kandy Jaffna Road A 009 (17+710 - 46+450), Thalgodapitiya Yatawatta Dombawela road B 409 (15+030 - 26+800),Palapathwela Galewela road B 346 (0+000 - 8+100)
RDA/DRP/CEN/MTL/MTL/33Wattegama Matale Road B 462,Approch road to Ukuwela Railway station B 027
RDA/DRP/CEN/MTL/MTL/35Rattota Gammaduwa Road B 392
RDA/DRP/CEN/MTL/MTL/38Kalalpitiya Ukuwela Elkaduwa Road
RDA/DRP/CEN/MTL/MTL/41Matale-Illukkumbura- Laggala Road (B-274)
Click to filter the awarded table
1,345.4M
1,345.4 Mn
Contract Value
Awarded projects6
RDA/DRP/CEN/MTL/MTL/31RMatale Udupihilla Road (AB 026)
RDA/DRP/CEN/MTL/MTL/32Kandy Jaffna Road A 009 (17+710 - 46+450), Thalgodapitiya Yatawatta Dombawela road B 409 (15+030 - 26+800),Palapathwela Galewela road B 346 (0+000 - 8+100)
RDA/DRP/CEN/MTL/MTL/33Wattegama Matale Road B 462,Approch road to Ukuwela Railway station B 027
RDA/DRP/CEN/MTL/MTL/35Rattota Gammaduwa Road B 392
RDA/DRP/CEN/MTL/MTL/38Kalalpitiya Ukuwela Elkaduwa Road
RDA/DRP/CEN/MTL/MTL/41Matale-Illukkumbura- Laggala Road (B-274)
Click to filter the awarded table
Avg
27.2%
6
works in progress
0 completed
Avg Progress
Awarded projects6
RDA/DRP/CEN/MTL/MTL/31RMatale Udupihilla Road (AB 026)
RDA/DRP/CEN/MTL/MTL/32Kandy Jaffna Road A 009 (17+710 - 46+450), Thalgodapitiya Yatawatta Dombawela road B 409 (15+030 - 26+800),Palapathwela Galewela road B 346 (0+000 - 8+100)
RDA/DRP/CEN/MTL/MTL/33Wattegama Matale Road B 462,Approch road to Ukuwela Railway station B 027
RDA/DRP/CEN/MTL/MTL/35Rattota Gammaduwa Road B 392
RDA/DRP/CEN/MTL/MTL/38Kalalpitiya Ukuwela Elkaduwa Road
RDA/DRP/CEN/MTL/MTL/41Matale-Illukkumbura- Laggala Road (B-274)
Click to filter the awarded table
132.3M
132.3 Mn
Total Expenditure (excl. VAT)
Awarded projects6
RDA/DRP/CEN/MTL/MTL/31RMatale Udupihilla Road (AB 026)
RDA/DRP/CEN/MTL/MTL/32Kandy Jaffna Road A 009 (17+710 - 46+450), Thalgodapitiya Yatawatta Dombawela road B 409 (15+030 - 26+800),Palapathwela Galewela road B 346 (0+000 - 8+100)
RDA/DRP/CEN/MTL/MTL/33Wattegama Matale Road B 462,Approch road to Ukuwela Railway station B 027
RDA/DRP/CEN/MTL/MTL/35Rattota Gammaduwa Road B 392
RDA/DRP/CEN/MTL/MTL/38Kalalpitiya Ukuwela Elkaduwa Road
RDA/DRP/CEN/MTL/MTL/41Matale-Illukkumbura- Laggala Road (B-274)
Click to filter the awarded table
0%
0
Kick Off Pending
0 / 6 awarded
Kick Off Pending0
No projects
Click to filter the awarded table
0%
0
Mobilization Pending
0 / 6 awarded
Mobilization Pending0
No projects
Click to filter the awarded table
16.7%
0
Works Not Started
1 / 6 awarded
Works Not Started1
RDA/DRP/CEN/MTL/MTL/31RMatale Udupihilla Road (AB 026)
Click to filter the awarded table
0%
0
Completed
0 / 6 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · EE: Matale · EE Office
Avg Physical Progress per EE Division · EE: Matale
At-Risk Projects · EE: Matale
Portfolio Timeline · 6 scheduled projects · EE: Matale Toggle
2026-05-02
today
2027-03-02
Portfolio · Awarded Works
Awarded Projects
8 projects
| Contract No. | Contract Name | Progress | Amount | Status |
|---|---|---|---|---|
| RDA/DRP/CEN/KDY/KDY/19 | Rehabilitation / Improvement of Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000) |
0%
|
67,935,586.77 | Awarded |
| RDA/DRP/CEN/MTL/NAL/48R | Rehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950) |
0%
|
50,471,466.08 | Awarded |
| RDA/DRP/CEN/NUE/NUE/60R | Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850) |
0%
|
336,313,078.73 | Awarded |
| RDA/DC/DRP/CP/NE/NE/04 | REHABILITAION/ IMPROVEMENTS OF LADY MACALUMS DRIVE ROAD (2+850 - 5+600KM) |
0%
|
47,725,380.00 | Awarded |
| RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/01 | Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 0+030 km |
0%
|
22,481,370.00 | Awarded |
| RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/14 | Construction of Slope failure mitigation measures along Atabage-Ulapane Road (B 490) at Ch 4+000 km |
0%
|
24,796,315.46 | Awarded |
| RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/29 | Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 21+550 km |
0%
|
28,806,688.50 | Awarded |
| RDA/DC/DRP/SLOPE/PD(CP)/KDY/KUN/18,19&20 | Construction of Slope failure mitigation measures along Kandy – Mahiyangana – Padiyatalawa Road (A026) at Culvert No 47/5 Culvert No47/10, Culvert No 50/6-51+200 km and Culvert No 52/3-Culvert No 52/5 |
0%
|
19,636,680.00 | Awarded |
Showing 1–8 of 8
Source: ditwah_projects • 10 projects • Data updated 2026-09-24 15:27 • 18:07:14