Pending207.2Mn
Planned Fin85.3%
Actual Fin15.3%
Advance & IPC
Advance paid83 proj · 2,738.9 Mn
IPC paid62 proj · 1,049.9 Mn
Monitor financial performance across 171 awarded projects
34,005.30 Mn
Total Contract
2,738.85 Mn
Advance Paid (excl. VAT)
1,049.94 Mn
IPCs Paid (excl. VAT)
3,788.80 Mn
Total Paid (excl. VAT)
4,470.49 Mn
Total Paid (incl. VAT)
133.60 Mn
Advance Pend (incl. VAT)
73.65 Mn
IPCs Pend (incl. VAT)
4,677.74 Mn
Total (Paid+Pend) (incl. VAT)
Paid incl + Adv Pend incl + IPC Pend incl
11.7%
Financial Progress (excl. VAT)
Total (Paid+Pend) excl / Contract
62.5%
Planned Financial Progress
Planned share of contract value
Advance payments, IPCs & expenditure per awarded project · 136 projects (filtered from 171)
Filter financial register
136 matching projects1 active
| S/N | Contract No | Contract Name | Contractor | Contract (LKR) | Advance Paid (excl. VAT) | Advance Paid (incl. VAT) | Advance Pend (excl. VAT) | Advance Pend (incl. VAT) | IPCs Paid (excl. VAT) | IPCs Paid (incl. VAT) | IPCs Pend (excl. VAT) | IPCs Pend (incl. VAT) | Overall Expenditure (excl. VAT) | Pending Payments (excl. VAT) | Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 121 | RDA/DRP/UVA/BAD/BAN/20 | Rehabilitation / Improvement of Bandarawela - Liyangahawela - Poonagala Road (B0… | D K S Construction | 283,401,035.13 | 51,293,460.90 | 60,526,283.86 | — | — | — | — | — | — | 51,293,460.90 | — | 60.53Mn Watch21.4% | 60.53Mn 21.4% |
| 122 | RDA/DRP/NCP/POL/POL/10 | Rehabilitation / Improvement and Construction of New Drainage At 65-78km on Mara… | A.D.M Construction | 29,767,050.53 | 4,266,131.96 | 5,034,035.72 | — | — | 6,804,713.26 | 8,029,561.65 | — | — | 11,070,845.22 | — | 13.06Mn On Track43.9% | 13.06Mn 43.9% |
| 123 | RDA/DRP/UVA/BAD/BAN/24 | Rehabilitation / Improvement of Rendapola Ambewela Road | Gamage Builders | 290,409,872.96 | 52,259,795.07 | 61,666,558.18 | — | — | — | — | — | — | 52,259,795.07 | — | 61.67Mn Watch21.2% | 61.67Mn 21.2% |
| 124 | RDA/DRP/EAS/AMP/AMP/01 | Rehabilitation / Improvement of Ampara Uhana Mahoya Road (from 2+400 to 2+800) &… | Ediriweera Construction | 27,878,955.02 | 5,042,900.91 | 5,950,623.07 | — | — | — | — | — | — | 5,042,900.91 | — | 5.95Mn Watch21.3% | 5.95Mn 21.3% |
| 125 | RDA/DRP/EAS/AKK/AKK/04 | Rehabilitation / Improvement of Newguna – Manikkamadu – Irakkamam Road (0+000-1+… | Jeezan Trading and Transport | 171,572,395.05 | 15,455,490.46 | 18,237,478.74 | — | — | — | — | — | — | 15,455,490.46 | — | 18.24Mn Behind10.6% | 18.24Mn 10.6% |
| 126 | RDA/DRP/EAS/AKK/KAL/05 | Rehabilitation / Improvement and Reconstruction of Box Culvert at 9+780, Constru… | Nazeeha Hardware and Construction | 196,448,155.48 | — | — | — | — | — | — | — | — | — | — | — | — |
| 127 | RDA/DRP/NWP/CHI/PUT/12 | Rehabilitation / Improvement of Puttalam Marichchikaddi Road in Puttalam 6+100-9… | Omega Construction Company (Pvt) Ltd | 141,404,654.67 | — | — | 25,503,937.21 | 30,094,645.91 | — | — | — | — | — | 25,503,937.21 | — | 30.09Mn 21.3% |
| 128 | RDA/DRP/WP/GAM/GAM/13 | Rehabilitation / Improvement and Culvert Constructions on Aluthgama- Vigoda Road… | Venus Enterprise | 34,489,854.85 | — | — | — | — | — | — | — | — | — | — | — | — |
| 129 | RDA/DRP/NCP/POL/POL/11 | Rehabilitation / Improvement and Construction of New Drainage on Polonnaruwa-Tha… | A.D.M Construction | 44,474,738.82 | 7,582,108.44 | 8,946,887.96 | — | — | — | — | — | — | 7,582,108.44 | — | 8.95Mn Watch20.1% | 8.95Mn 20.1% |
| 130 | RDA/DRP/UVA/BAD/BAN/23 | Rehabilitation / Improvement of Colombo Rathnapura Wellawaya Batticaloa Road (AA… | D K S Construction | 322,192,938.69 | 58,090,759.31 | 68,547,095.98 | — | — | — | — | — | — | 58,090,759.31 | — | 68.55Mn Watch21.3% | 68.55Mn 21.3% |
| Total | 25,015,709,448.33 | 2,722,415,585.49 | 3,212,250,375.88 | 113,218,826.01 | 133,598,214.69 | 1,001,703,559.51 | 1,181,924,384.58 | 63,842,351.18 | 73,647,937.02 | 3,724,119,145.00 | 177,061,177.19 | 4,394.17Mn 17.6% | 4,601.42Mn 18.4% | |||