DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 23 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 15:53Live
Graphs reflect current view:23 awarded · Badulla

Portfolio Breakdown · Badulla · District

171Awarded266Total
Badulla 23 awarded of 26 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp ex-VATPlanned %Actual %
Emergency23230100%5,770.95,411.14,826.7967.818% of contract88.8%52.6%
DC - Roads3030%896.70.0————
DC - Slope0000%0.00.0————
PD(CP) - Slope0000%0.00.0————
Badulla2623388%6,667.65,411.14,826.7967.818% of contract88.8%52.6%

Avg Physical Progress per EE Division · Badulla

At-Risk Projects · Badulla

14
Portfolio Timeline· 23 scheduled projects · Badulla Toggle
Portfolio · Awarded Works

Awarded Projects

1 projects

1/1 (filtered)

Filter awarded works

1 matching project1 active

ActiveDelay
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/UVA/BAD/BAN/15R
Rehabilitation / Improvement of Bandarawela Welimada Road (6+000-20+200) (B-044)
12%
228,783,135.84237,954,791.68Awarded
Showing 1–1 of 1
Per page:
Source: DRRRP • 26 projects • Data updated 2026-11-02 15:53 • 09:47:07