DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 171 awarded projects

2026-11-04
17:22:14Live2026-11-04
3 / 171Advance Pendingpending advance projects / total projects
133.6 Mn

133.60 Mn

Advance Pend (incl. VAT)

Portfolio Breakdown — Financial (Exclusive Vat) · Province

171Projects34,005.3Contract Mn
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency14424,785.94,470.518% of contract207.286832,738.9125621,049.985.3%15.3%
DC - Roads95,783.257.81% of contract—1149.0———0.4%0.8%
DC - Slope103,258.5————————0.3%0.0%
PD(CP) - Slope8177.7————————0.0%0.0%
All Provinces17134,005.34,528.313% of contract207.287842,787.8125621,049.971.9%11.3%
Emergency144 projects24,785.9Mn
18% paid4,470.5 Mn
Pending207.2Mn
Planned Fin85.3%
Actual Fin15.3%
Advance & IPC
Advance paid83 proj · 2,738.9 Mn
IPC paid62 proj · 1,049.9 Mn
Open filtered view
DC - Roads9 projects5,783.2Mn
1% paid57.8 Mn
Pending—
Planned Fin0.4%
Actual Fin0.8%
Advance & IPC
Advance paid1 proj · 49.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope10 projects3,258.5Mn
0% paid0.0 Mn
Pending—
Planned Fin0.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope8 projects177.7Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
All Provinces171 projects34,005.3Mn
13% paid4,528.3 Mn
Pending207.2Mn
Planned Fin71.9%
Actual Fin11.3%

Avg Physical Progress per Province

Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 136 projects (filtered from 171)

111–120/136 (filtered from 171)

Filter financial register

136 matching projects1 active

ActiveIn progress
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
111RDA/DRP/NCP/POL/HAB/04
Rehabilitation / Improvement of washed out section between 30/1 & 30/2 Bridges o…
Lahiru Construction and Consultants (Pvt…
49,203,550.22————————————
112RDA/DRP/NCP/ANU/MAR/05R
Rehabilitation / Improvement and Rectification of Flood Damage on Thonigala - Ka…
NMST Contractors
89,094,024.31————————————
113RDA/DRP/NCP/ANU/MAR/06
Rehabilitation / Improvement and Retaining wall Construction of bridge No. 3/1 &…
W.M.B. Contractors & Transporter
112,693,093.1128,343,103.0833,444,861.63——6,175,897.387,287,558.91——34,519,000.46—
40.73Mn
36.1%
Watch
40.73Mn
36.1%
114RDA/DRP/NCP/ANU/MED/07
Rehabilitation / Improvement of Flood Damaged - Shoulder & Embankment Protection…
The Crown Construction
38,223,285.38————————————
115RDA/DRP/SAB/RAT/PEL/17
Rehabilitation / Improvement of Balangoda - Bowatta -Kalthota Road (B038) (24+00…
DKS Nishantha Construction
92,061,086.6116,248,379.3819,173,087.67——————16,248,379.38—
19.17Mn
20.8%
Watch
19.17Mn
20.8%
116RDA/DRP/SAB/RAT/RAT/23
Rehabilitation / Improvement Construction of Retaining structures on Thiruwanake…
AKC Construction
52,340,066.909,310,375.8010,986,243.44——————9,310,375.80—
10.99Mn
21%
Watch
10.99Mn
21%
117RDA/DRP/NWP/CHI/CHI/07
Rehabilitation / Improvement of Nainamadama – Iranavila - Chilaw Road (B640) (6+…
Jayawansa Construction (Pvt) Ltd
214,608,362.18————38,125,702.2144,988,328.61——38,125,702.21—
44.99Mn
21%
Watch
44.99Mn
21%
118RDA/DRP/NWP/CHI/PUT/09R
Rehabilitation / Improvement of Peliyagoda Puttalam Road ((A003)) (95+000 - 97+0…
RCDC Construction Company (Pvt) Ltd
219,322,470.61————————————
119RDA/DRP/NWP/CHI/PUT/10
Rehabilitation / Improvement of Palavi - Kalpitiya Road (B349) and Etalai - Tala…
ST MARY Construction
136,011,633.1123,243,388.0027,427,197.84——————23,243,388.00—
27.43Mn
20.2%
Watch
27.43Mn
20.2%
120RDA/DRP/NWP/CHI/PUT/11
Rehabilitation / Improvement of Town Roads (Saltern Road, Marikkar Street, Poles…
Omega Construction Company (Pvt) Ltd
303,043,337.30——54,762,788.6064,620,090.54—————54,762,788.60—
64.62Mn
21.3%
Total25,015,709,448.332,771,382,827.733,270,031,721.91113,218,826.01133,598,214.691,001,703,559.511,181,924,384.5863,842,351.1873,647,937.023,773,086,387.24177,061,177.19
4,451.96Mn
17.8%
4,659.20Mn
18.6%
Showing 111–120 of 136 projects · page 12/14