DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 171 awarded projects

2026-11-04
18:56:37Live2026-11-04
3 / 171Advance Pendingpending advance projects / total projects
133.6 Mn

133.60 Mn

Advance Pend (incl. VAT)

Portfolio Breakdown — Financial (Exclusive Vat) · Province

171Projects34,005.3Contract Mn
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency14424,785.94,470.518% of contract207.286832,738.9125621,049.985.3%15.3%
DC - Roads95,783.257.81% of contract—1149.0———0.4%0.8%
DC - Slope103,258.5————————0.3%0.0%
PD(CP) - Slope8177.7————————0.0%0.0%
All Provinces17134,005.34,528.313% of contract207.287842,787.8125621,049.971.9%11.3%
Emergency144 projects24,785.9Mn
18% paid4,470.5 Mn
Pending207.2Mn
Planned Fin85.3%
Actual Fin15.3%
Advance & IPC
Advance paid83 proj · 2,738.9 Mn
IPC paid62 proj · 1,049.9 Mn
Open filtered view
DC - Roads9 projects5,783.2Mn
1% paid57.8 Mn
Pending—
Planned Fin0.4%
Actual Fin0.8%
Advance & IPC
Advance paid1 proj · 49.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope10 projects3,258.5Mn
0% paid0.0 Mn
Pending—
Planned Fin0.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope8 projects177.7Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
All Provinces171 projects34,005.3Mn
13% paid4,528.3 Mn
Pending207.2Mn
Planned Fin71.9%
Actual Fin11.3%

Avg Physical Progress per Province

Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 92 projects (filtered from 171)

41–50/92 (filtered from 171)

Filter financial register

92 matching projects1 active

ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
41RDA/DRP/SAB/RAT/RAT/24
Rehabilitation / Improvement and Asphalt Overlaying on Kalawana - Deepdeen Rakwa…
SSP Engineers (Pvt) Ltd
236,752,750.5941,882,954.6449,421,886.47——31,108,406.9736,707,920.23——72,991,361.61—
86.13Mn
36.4%
Watch
86.13Mn
36.4%
42RDA/DRP/SAB/KEG/RUW/28
Rehabilitation / Improvement of Bulathkohupitiya Dedugala Road, Warakapola Ruwan…
Southern Group Civil Construction (Pvt) …
260,537,133.8444,944,387.9853,034,377.82——11,670,294.0513,770,946.98——56,614,682.03—
66.81Mn
25.6%
Watch
66.81Mn
25.6%
43RDA/DRP/SAB/KEG/RUW/35
Yatiyanthota - Poonagala - Meenagala Road (from 13+400 to 18+200)
Southern Group Civil Construction (Pvt) …
170,714,785.5430,937,051.9236,305,721.27——4,255,880.155,021,913.58——35,192,932.07—
41.33Mn
24.2%
Watch
41.33Mn
24.2%
44RDA/DPR/NCP/ANU/ANU/02
Rehabilitation / Improvement and Construction of Drainge Canal for Kumbichchan K…
SMA Construction (Pvt) Ltd
138,891,057.6521,646,336.3925,542,676.94——————21,646,336.39—
25.54Mn
18.4%
Behind
25.54Mn
18.4%
45RDA/DPR/NCP/ANU/ANU/03
Rehabilitation / Improvement Construction of Drainge Canal for Thambuttegama Tan…
SMA Construction (Pvt) Ltd
132,437,825.5023,099,490.2027,257,398.44——————23,099,490.20—
27.26Mn
20.6%
Watch
27.26Mn
20.6%
46RDA/DRP/WP/GAM/NEG/19
Rehabilitation / Improvement of Negombo-Mirigama Road (5+000-6+000) and Negombo…
Tudawe Brothers (Pvt) Ltd
206,184,462.5737,452,084.1044,193,459.24——————37,452,084.10—
44.19Mn
21.4%
Watch
44.19Mn
21.4%
47RDA/DRP/WP/GAM/NIT/21
Rehabilitation / Improvement of Hanwella Urapola Road (3+000 - 10+100), Structur…
Tudawe Brothers (Pvt) Ltd
221,768,903.8439,283,558.3146,354,598.81——————39,283,558.31—
46.35Mn
20.9%
Watch
46.35Mn
20.9%
48RDA/DRP/WP/GAM/GAM/10
Rehabilitation / Improvement of Old Minuwangoda Gampaha - Miriswatta Road (9+000…
Senarath Engineering (Pvt) Ltd
92,177,672.5216,747,576.8219,762,140.65——————16,747,576.82—
19.76Mn
21.4%
Watch
19.76Mn
21.4%
49RDA/DRP/WP/GAM/GAM/12
Rehabilitation / Improvement of Acces Road to Peliyagoda interchange (0+000 - 2+…
Senarath Engineering (Pvt) Ltd
151,956,608.9227,570,474.3532,533,159.73——————27,570,474.35—
32.53Mn
21.4%
Watch
32.53Mn
21.4%
50RDA/DRP/WP/GAM/NIT/20
Rehabilitation / Improvement of Bothale Mirigama Road (3+750-4+800), Warakapola …
Jeyanthan Construction
217,881,464.96————————————
Total16,799,029,680.142,276,780,837.162,686,401,372.89——905,188,809.071,068,036,979.0652,935,451.9660,777,795.943,181,969,646.2352,935,451.96
3,754.44Mn
22.3%
3,815.22Mn
22.7%
Showing 41–50 of 92 projects · page 5/10