Financial Dashboard

Monitor financial performance across 171 awarded projects

2026-11-04
16:26:23Live2026-11-04
3 / 171Advance Pendingpending advance projects / total projects
133.6 Mn

133.60 Mn

Advance Pend (incl. VAT)

Portfolio Breakdown — Financial (Exclusive Vat) · Province

171Projects34,005.3Contract Mn
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency14424,785.94,470.518% of contract207.286832,738.9125621,049.985.3%15.3%
DC - Roads95,783.257.81% of contract—1149.0———0.4%0.8%
DC - Slope103,258.5————————0.3%0.0%
PD(CP) - Slope8177.7————————0.0%0.0%
All Provinces17134,005.34,528.313% of contract207.287842,787.8125621,049.971.9%11.3%
Emergency144 projects24,785.9Mn
18% paid4,470.5 Mn
Pending207.2Mn
Planned Fin85.3%
Actual Fin15.3%
Advance & IPC
Advance paid83 proj · 2,738.9 Mn
IPC paid62 proj · 1,049.9 Mn
Open filtered view
DC - Roads9 projects5,783.2Mn
1% paid57.8 Mn
Pending—
Planned Fin0.4%
Actual Fin0.8%
Advance & IPC
Advance paid1 proj · 49.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope10 projects3,258.5Mn
0% paid0.0 Mn
Pending—
Planned Fin0.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope8 projects177.7Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
All Provinces171 projects34,005.3Mn
13% paid4,528.3 Mn
Pending207.2Mn
Planned Fin71.9%
Actual Fin11.3%

Avg Physical Progress per Province

Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 136 projects (filtered from 171)

31–40/136 (filtered from 171)

Filter financial register

136 matching projects1 active

ActiveIn progress
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
31RDA/DC/DRP/CP/NE/NRW/02
REHABILITATION/ IMPROVEMENT OF APPROCH ROAD TO LAXAPANA POWER HOUSE ROAD CH 6+10…
U.K.S Lanka Engineering (Pvt) Ltd
374,859,845.10————————————
32RDA/DC/DRP/CP/NE/NE/04
REHABILITAION/ IMPROVEMENTS OF LADY MACALUMS DRIVE ROAD (2+850 - 5+600KM)
KDA Weerasinghe & Co (Pvt) Ltd
636,338,397.00————————————
33RDA/DC/DRP/SLOPE/CP/KDY/GAMP…
MITIGATION OF FAILURES ALONG RDA ROADS DUE TO CYCLONE DITWAH GAMPOLA NAWALAPITIY…
Sanguine Engineering (Pvt) Ltd
386,699,553.58————————————
34RDA/DC/DRP/CP/NE/NRW/03
REHABILITATION/ IMPROVEMENT TO ROZELLA RAILWAY STATION ROAD (0+000 - 3+300) KM A…
Nagma Engineering (Pvt) Ltd
604,298,969.2848,967,242.2457,781,346.03——————48,967,242.24—
57.78Mn
9.6%
Behind
57.78Mn
9.6%
35RDA/DRP/SAB/KEG/KEG/14
Rehabilitation / Improvement of Damaged Locations in Colombo Kandy Road from 56+…
Tudawe Brothers (Pvt) Ltd
261,228,130.7847,252,023.7855,757,388.06——20,746,920.9124,481,366.67——67,998,944.69—
80.24Mn
30.7%
Watch
80.24Mn
30.7%
36RDA/DRP/UVA/BAD/BAD/02
Rehabilitation / Improvement of Demodara SpringValley Badulla Road (16+145-20+80…
Priyankara Industries & Contractors
241,775,532.44————30,108,187.0035,527,660.65——30,108,187.00—
35.53Mn
14.7%
Behind
35.53Mn
14.7%
37RDA/DRP/UVA/BAD/MAH/27
Rehabilitation / Improvement of Dambagahapitiya Pinnagolla arawa Meegahakeula Ro…
EMA Construction (Pvt) Ltd
73,623,757.9012,938,138.0015,267,002.84——11,290,160.0813,322,388.90——24,228,298.08—
28.59Mn
38.8%
Watch
28.59Mn
38.8%
38RDA/DRP/SAB/RAT/PEL/20
Rehabilitation / Improvement of Pelmadulla - Pelmadulla - Embilipitiya - Nonagam…
K.E.P. Construction
194,327,188.5134,694,816.0940,939,882.99——9,204,185.8610,860,939.32——43,899,001.95—
51.80Mn
26.7%
Watch
51.80Mn
26.7%
39RDA/DRP/UVA/BAD/BAN/19
Rehabilitation / Improvement of Bandarawela Liyangahawela Poonagala Road (5+000 …
Senura Civil Engineering (Pvt) Ltd
216,526,489.6739,106,452.6746,145,614.15——3,612,479.504,262,725.81——42,718,932.17—
50.41Mn
23.3%
Watch
50.41Mn
23.3%
40RDA/DRP/UVA/BAD/BAN/15R
Rehabilitation / Improvement of Bandarawela Welimada Road (6+000-20+200) (B-044)
Subasingha Contractors (Pvt) Ltd
228,783,135.8440,429,837.1947,707,207.88——————40,429,837.19—
47.71Mn
20.9%
Watch
47.71Mn
20.9%
Total25,015,709,448.332,771,382,827.733,270,031,721.91113,218,826.01133,598,214.691,001,703,559.511,181,924,384.5863,842,351.1873,647,937.023,773,086,387.24177,061,177.19
4,451.96Mn
17.8%
4,659.20Mn
18.6%
Showing 31–40 of 136 projects · page 4/14