Ditwah (CP)
Project Monitoring Dashboard
Comprehensive overview of 13 infrastructure projects
under the Disaster Rehabilitation Programme. · Team Leader
Updated 2026-09-24 15:27Live
Stabilizing Slopes — Securing Futures
Last Updated
2026-09-24 15:27 · 17:20:14 LIVE
Graphs reflect current view:
13 awarded · Team Leader
· KPIs, EE / District charts, distribution, timeline and at-risk list all use the same filters as the table
Portfolio at a Glance
13 awarded works · Team Leader
92.9% awarded
0
Awarded
14 total projects in portfolio
Awarded projects13
RDA/DRP/CEN/KDY/KAD/11Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )
RDA/DRP/CEN/KDY/KAN/14Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)
RDA/DRP/CEN/KDY/KDY/15Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)
RDA/DRP/CEN/KDY/KDY/19Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)
RDA/DRP/CEN/KDY/KUN/20Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)
RDA/DRP/CEN/KDY/KUN/21Pitiyegedara-Waththegama-Iriyagasthenna Road (B369)
RDA/DRP/CEN/KDY/KUN/22Weraganthota-Randenigala Road (B474)
RDA/DRP/CEN/KDY/KUN/24RKatugastota Madawala Bamberella Road
RDA/DRP/CEN/KDY/KUN/25Katugastota - Madawala - Bamberella Road
RDA/DRP/CEN/KDY/KUN/27Kandy - Jaffna Road
RDA/DRP/CEN/KDY/KUN/29Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) A026 and Moragahamula victoria damtop B493
RDA/DRP/CEN/MTL/MTL/31RMatale Udupihilla Road (AB 026)
RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09
Click to filter the awarded table
1,822.3M
1,822.3 Mn
Contract Value
Spent 11% Remaining 89%
Awarded projects13
RDA/DRP/CEN/KDY/KAD/11Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )
RDA/DRP/CEN/KDY/KAN/14Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)
RDA/DRP/CEN/KDY/KDY/15Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)
RDA/DRP/CEN/KDY/KDY/19Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)
RDA/DRP/CEN/KDY/KUN/20Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)
RDA/DRP/CEN/KDY/KUN/21Pitiyegedara-Waththegama-Iriyagasthenna Road (B369)
RDA/DRP/CEN/KDY/KUN/22Weraganthota-Randenigala Road (B474)
RDA/DRP/CEN/KDY/KUN/24RKatugastota Madawala Bamberella Road
RDA/DRP/CEN/KDY/KUN/25Katugastota - Madawala - Bamberella Road
RDA/DRP/CEN/KDY/KUN/27Kandy - Jaffna Road
RDA/DRP/CEN/KDY/KUN/29Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) A026 and Moragahamula victoria damtop B493
RDA/DRP/CEN/MTL/MTL/31RMatale Udupihilla Road (AB 026)
RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09
Click to filter the awarded table
Avg
18.2%
12
works in progress
0 completed
Avg Progress
Awarded projects13
RDA/DRP/CEN/KDY/KAD/11Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )
RDA/DRP/CEN/KDY/KAN/14Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)
RDA/DRP/CEN/KDY/KDY/15Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)
RDA/DRP/CEN/KDY/KDY/19Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)
RDA/DRP/CEN/KDY/KUN/20Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)
RDA/DRP/CEN/KDY/KUN/21Pitiyegedara-Waththegama-Iriyagasthenna Road (B369)
RDA/DRP/CEN/KDY/KUN/22Weraganthota-Randenigala Road (B474)
RDA/DRP/CEN/KDY/KUN/24RKatugastota Madawala Bamberella Road
RDA/DRP/CEN/KDY/KUN/25Katugastota - Madawala - Bamberella Road
RDA/DRP/CEN/KDY/KUN/27Kandy - Jaffna Road
RDA/DRP/CEN/KDY/KUN/29Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) A026 and Moragahamula victoria damtop B493
RDA/DRP/CEN/MTL/MTL/31RMatale Udupihilla Road (AB 026)
RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09
Click to filter the awarded table
200.9M
200.9 Mn
Total Expenditure (excl. VAT)
11% of contract excl. VAT
Awarded projects13
RDA/DRP/CEN/KDY/KAD/11Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )
RDA/DRP/CEN/KDY/KAN/14Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)
RDA/DRP/CEN/KDY/KDY/15Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)
RDA/DRP/CEN/KDY/KDY/19Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)
RDA/DRP/CEN/KDY/KUN/20Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)
RDA/DRP/CEN/KDY/KUN/21Pitiyegedara-Waththegama-Iriyagasthenna Road (B369)
RDA/DRP/CEN/KDY/KUN/22Weraganthota-Randenigala Road (B474)
RDA/DRP/CEN/KDY/KUN/24RKatugastota Madawala Bamberella Road
RDA/DRP/CEN/KDY/KUN/25Katugastota - Madawala - Bamberella Road
RDA/DRP/CEN/KDY/KUN/27Kandy - Jaffna Road
RDA/DRP/CEN/KDY/KUN/29Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) A026 and Moragahamula victoria damtop B493
RDA/DRP/CEN/MTL/MTL/31RMatale Udupihilla Road (AB 026)
RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09
Click to filter the awarded table
0%
0
Kick Off Pending
0 / 13 awarded
Kick Off Pending0
No projects
Click to filter the awarded table
7.7%
0
Mobilization Pending
1 / 13 awarded
Mobilization Pending1
RDA/DRP/CEN/KDY/KDY/19Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)
Click to filter the awarded table
23.1%
0
Works Not Started
3 / 13 awarded
Works Not Started3
RDA/DRP/CEN/KDY/KAN/14Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)
RDA/DRP/CEN/KDY/KDY/19Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)
RDA/DRP/CEN/MTL/MTL/31RMatale Udupihilla Road (AB 026)
Click to filter the awarded table
0%
0
Completed
0 / 13 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · Team Leader · Consultant
13Awarded
14Total
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 13 | 12 | 1 | 92% | 1,651.5 | 1,435.6 | 821.2 | 200.9 14% of contract | 50.5% | 19.5% |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC - Slope | 1 | 1 | 0 | 100% | 0.0 | 386.7 | 9.7 | — | 6.2% | 2.3% |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| All Districts | 14 | 13 | 1 | 93% | 1,651.5 | 1,822.3 | 830.8 | 200.9 11% of contract | 47.1% | 18.2% |
Kandy
·
12 awarded of 13
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 12 | 11 | 1 | 92% | 1,651.5 | 1,371.9 | 815.5 | 200.9 15% of contract | 53.1% | 21.3% |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC - Slope | 1 | 1 | 0 | 100% | 0.0 | 386.7 | 9.7 | — | 6.2% | 2.3% |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| Kandy | 13 | 12 | 1 | 92% | 1,651.5 | 1,758.6 | 825.2 | 200.9 11% of contract | 49.2% | 19.7% |
Matale
·
1 awarded of 1
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 1 | 1 | 0 | 100% | 0.0 | 63.7 | 5.7 | — | 22.3% | 0.0% |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| Matale | 1 | 1 | 0 | 100% | 0.0 | 63.7 | 5.7 | 0.0 0% of contract | 22.3% | 0.0% |
34Awarded
36Total
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % | Kick Off Pending | Mobilization Pending | Works Not Started |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 32 | 30 | 2 | 94% | 4,917.0 | 4,498.3 | 2,424.3 | 589.7 13% of contract | 61.5% | 27.8% | 2 | 3 | 5 |
| DC | 3 | 3 | 0 | 100% | 0.0 | 1,026.9 | 24.4 | — | 4.9% | 2.0% | 1 | 1 | 1 |
| DC - Slope | 1 | 1 | 0 | 100% | 0.0 | 386.7 | 9.7 | — | 6.2% | 2.3% | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| All Consultants | 36 | 34 | 2 | 94% | 4,917.0 | 5,911.8 | 2,458.4 | 589.7 10% of contract | 54.9% | 24.8% | 3 | 4 | 6 |
Team Leader
·
13 awarded of 14
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % | Kick Off Pending | Mobilization Pending | Works Not Started |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 13 | 12 | 1 | 92% | 1,651.5 | 1,435.6 | 821.2 | 200.9 14% of contract | 50.5% | 19.5% | — | 1 | 3 |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| DC - Slope | 1 | 1 | 0 | 100% | 0.0 | 386.7 | 9.7 | — | 6.2% | 2.3% | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| Team Leader | 14 | 13 | 1 | 93% | 1,651.5 | 1,822.3 | 830.8 | 200.9 11% of contract | 47.1% | 18.2% | 0 | 1 | 3 |
Nuwara Eliya EE
·
7 awarded of 7
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % | Kick Off Pending | Mobilization Pending | Works Not Started |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 6 | 6 | 0 | 100% | 1,213.2 | 1,251.4 | 719.4 | 225.1 18% of contract | 76.5% | 35.8% | 1 | 1 | 1 |
| DC | 1 | 1 | 0 | 100% | 0.0 | 47.7 | — | — | 0.0% | 0.0% | 1 | 1 | 1 |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| Nuwara Eliya EE | 7 | 7 | 0 | 100% | 1,213.2 | 1,299.1 | 719.4 | 225.1 17% of contract | 65.6% | 30.7% | 2 | 2 | 2 |
Matale EE
·
5 awarded of 6
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % | Kick Off Pending | Mobilization Pending | Works Not Started |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 6 | 5 | 1 | 83% | 1,446.6 | 1,281.7 | 613.3 | 132.3 10% of contract | 61.8% | 32.6% | — | — | — |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| Matale EE | 6 | 5 | 1 | 83% | 1,446.6 | 1,281.7 | 613.3 | 132.3 10% of contract | 61.8% | 32.6% | 0 | 0 | 0 |
Norwood EE
·
5 awarded of 5
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % | Kick Off Pending | Mobilization Pending | Works Not Started |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 3 | 3 | 0 | 100% | 435.8 | 369.1 | 210.9 | 14.1 4% of contract | 78.7% | 24.3% | — | — | — |
| DC | 2 | 2 | 0 | 100% | 0.0 | 979.2 | 24.4 | — | 7.4% | 3.0% | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| Norwood EE | 5 | 5 | 0 | 100% | 435.8 | 1,348.3 | 235.3 | 14.1 1% of contract | 50.2% | 15.8% | 0 | 0 | 0 |
Nalanda EE
·
3 awarded of 3
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % | Kick Off Pending | Mobilization Pending | Works Not Started |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 3 | 3 | 0 | 100% | 125.2 | 112.6 | 36.0 | 17.1 15% of contract | 54.3% | 46.0% | 1 | 1 | 1 |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| Nalanda EE | 3 | 3 | 0 | 100% | 125.2 | 112.6 | 36.0 | 17.1 15% of contract | 54.3% | 46.0% | 1 | 1 | 1 |
Hanguranketha EE
·
1 awarded of 1
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % | Kick Off Pending | Mobilization Pending | Works Not Started |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 1 | 1 | 0 | 100% | 44.7 | 47.8 | 23.6 | — | 72.8% | 10.0% | — | — | — |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — | — | — | — |
| Hanguranketha EE | 1 | 1 | 0 | 100% | 44.7 | 47.8 | 23.6 | 0.0 0% of contract | 72.8% | 10.0% | 0 | 0 | 0 |
13Awarded
14Total
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 13 | 12 | 1 | 92% | 1,651.5 | 1,435.6 | 821.2 | 200.9 14% of contract | 50.5% | 19.5% |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC - Slope | 1 | 1 | 0 | 100% | 0.0 | 386.7 | 9.7 | — | 6.2% | 2.3% |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| All EE Offices | 14 | 13 | 1 | 93% | 1,651.5 | 1,822.3 | 830.8 | 200.9 11% of contract | 47.1% | 18.2% |
Kundasale
·
7 awarded of 8
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 8 | 7 | 1 | 88% | 1,158.8 | 956.7 | 615.1 | 164.8 17% of contract | 65.7% | 29.7% |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| Kundasale | 8 | 7 | 1 | 88% | 1,158.8 | 956.7 | 615.1 | 164.8 17% of contract | 65.7% | 29.7% |
Kandy
·
3 awarded of 3
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 3 | 3 | 0 | 100% | 217.2 | 221.8 | 7.0 | — | 7.9% | 1.2% |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| Kandy | 3 | 3 | 0 | 100% | 217.2 | 221.8 | 7.0 | 0.0 0% of contract | 7.9% | 1.2% |
Gampola
·
1 awarded of 1
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC - Slope | 1 | 1 | 0 | 100% | 0.0 | 386.7 | 9.7 | — | 6.2% | 2.3% |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| Gampola | 1 | 1 | 0 | 100% | 0.0 | 386.7 | 9.7 | 0.0 0% of contract | 6.2% | 2.3% |
Kadugannawa
·
1 awarded of 1
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 1 | 1 | 0 | 100% | 275.5 | 193.4 | 193.4 | 36.1 19% of contract | 100.0% | 23.0% |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| Kadugannawa | 1 | 1 | 0 | 100% | 275.5 | 193.4 | 193.4 | 36.1 19% of contract | 100.0% | 23.0% |
Matale
·
1 awarded of 1
Open filtered view
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 1 | 1 | 0 | 100% | 0.0 | 63.7 | 5.7 | — | 22.3% | 0.0% |
| DC | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| Matale | 1 | 1 | 0 | 100% | 0.0 | 63.7 | 5.7 | 0.0 0% of contract | 22.3% | 0.0% |
Project-wise Progress · Team Leader (13 projects in one graph)
Physical Actual vs Planned per project • Click bar to open project
Project-wise Physical Progress: Actual vs Planned (%) · Team Leader
Average Physical Progress by EE Division · Team Leader
Average District-wise Physical Progress (Kandy District)
Kandy district baseline — all categories (consultant filter excluded for comparison)
Portfolio Timeline · 13 scheduled projects · Team Leader Toggle
2026-03-25
today
2027-06-30
Portfolio · Awarded Works
Awarded Projects
0 projects
| Contract No. | Contract Name | District | EE Division | Contractor | Consultant | Progress | Amount | Status | Mobilized | Kick Off | Active | Commenced | Scheduled End | Category |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Showing 0–0 of 0
Source: ditwah_projects • 14 projects • Data updated 2026-09-24 15:27 • 17:20:14
System live • Central Province • 2 districts
Esc
Pages
Dashboard
Financial Dashboard
All Projects
Physical Progress
Report Builder
Progress Ministry
Contractors
Projects
No pages or projects found