DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 59 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:59 awarded · North Western Province
74.7% awarded

0

Awarded

79 total projects 79 roads in portfolio

2,201.9M

2,201.9 Mn

Contract Value

Spent 50.3% Remaining 49.7%
1,107.0M

1,107.0 Mn

Total Expenditure (incl. VAT)

50.3% of contract incl. VAT
35.6%

0

Critical Delay

21 / 59 awarded

Portfolio Breakdown · North Western Province · Province

579Awarded739Total
North Western Province 59 awarded of 79 Open filtered view
CategoryImplementation MethodTotal PortfolioAwarded PortfolioPending RoadsAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
Total RoadsTotal ProjectsEst. Sanctioned ProjectsEst. Sanctioned RoadsPending Sanctioned RoadsSanctioned Length kmSanctioned Amount LKR MnEstimate LKR MnLOA Issued ProjectsLOA Issued RoadsAwarded Est LKR MnContract LKR Mn
TenderTender Above 50Mn18181818046.851,299.21,299.213131,003.1690.6572%593.593.113% of contract84.6%62.9%4—9—
Tender Below 50Mn34343434031.67956.2956.22424689.5529.01071%529.0229.043% of contract100.0%77.6%9312—
PIU000000.000.00.00—0.00.000%————————
Not Specified550050.000.00.00—0.00.050%————————
Tender Total57575252578.522,255.42,255.437371,692.61,219.62065%1,122.6322.126% of contract94.6%72.4%133210
Direct LabourDL Stage 016666014.24445.0444.766444.7445.00100%132.2385.387% of contract83.3%100.0%6———
DL Stage 02777708.45264.3264.477264.4264.30100%122.7212.580% of contract42.9%100.0%7———
DL Stage 03111101.1025.225.21125.225.20100%—17.971% of contract0.0%100.0%1———
DL Stage 04888809.43247.8247.888247.8247.80100%—169.268% of contract0.0%94.0%8———
Direct Labour Total22222222033.22982.3982.02222982.0982.30100%254.9784.980% of contract36.4%97.8%22000
—North Western Province797974745111.743,237.63,237.459592,674.72,201.92075%1,377.51,107.050% of contract72.9%81.9%353210

Avg Physical Progress per EE Division · North Western Province

At-Risk Projects · North Western Province

218
Portfolio Timeline· 51 scheduled projects · North Western Province Toggle
Portfolio · Awarded Works

Awarded Projects

35 projects

25/35 (filtered)

Filter awarded works

35 matching projects1 active

ActiveOn Progress
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/18/25/02/NWP/KRGRR/RDA/18/25/02
Road from Parakumpura to Yaya 04
100%
20,126,522.2424,748,740.38Awarded
2RR/RDA/18/25/08/NWP/KRGRR/RDA/18/25/08
Paving of road from Nammuawa to Nagansole temple
100%
33,899,382.0049,176,148.86Awarded
3RR/RDA/18/25/16/NWP/KRGRR/RDA/18/25/16
Development of concrete road from near Wadawa temple to the lake
100%
25,583,393.0031,595,236.77Awarded
4RR/RDA/18/25/24/NWP/KRGRR/RDA/18/25/24
Paving and developing the road from Seelarathana Mawatha to Girana Junction
100%
37,201,129.8057,963,603.67Awarded
5RR/RDA/18/25/104/NWP/KRGRR/RDA/18/25/104
Pinnagolla Junction to Kokowaththa Junction VIA Alakolapelessa
100%
24,010,872.6030,550,483.75Awarded
6RR/RDA/18/25/106/NWP/KRGRR/RDA/18/25/106
Thagahinna Temple Road
100%
13,370,813.5016,225,030.21Awarded
7RR/RDA/18/25/NWP/KRG/10RR/RDA/18/25/107
Uyandana Yaggapitiya
100%
45,801,928.2071,428,674.02Awarded
8RR/RDA/18/25/135/NWP/KRGRR/RDA/18/25/135
Kelegedara Gamameda Road (CTB Basaya Dawanaya wana) Kavudumunna, Kunumade, Hungan pitiya haraha diwena Margaya Kapat Kirima
20%
41,750,386.7055,779,764.12Awarded
9RR/RDA/18/25/136/NWP/KRGRR/RDA/18/25/136
Ranasinghe Hotel Asalin Koralaya Waththe sita Panwala Kubura Dakwa Diwena Margaya Kapat Kirima
100%
21,718,130.5022,994,794.21Awarded
10RR/RDA/19/25/26/NWP/PUTRR/RDA/19/25/26
Abayarama Mawatha Bomimakka Kovil Road to Sembandaluwa Temple Road
100%
26,275,458.0742,010,632.00Awarded
11RR/RDA/19/25/28/NWP/PUTRR/RDA/19/25/28
Samagi Mawatha
100%
25,908,850.0036,001,594.79Awarded
12RR/RDA/19/25/29/NWP/PUTRR/RDA/19/25/29
Development of the road from Galkuliya Welameda to Mrs. Deepani's house
100%
8,675,871.6013,481,102.43Awarded
13RR/RDA/19/25/40
Development of the road from Madurankuliya to Velasiya College
30%
55,254,878.0090,437,412.35Awarded
14RR/RDA/18/25/12—
Anura Mahaththayalage niwase sita Nalalida dakwa kadurugaha ela dakwa margaya (Ganewatte)
100%
23,242,484.2023,242,484.20Awarded
15RR/RDA/18/25/05—
158 Digana Grama niladari wasame 3 patumaga (vawa dakwa) (Yapahuwa)
100%
11,774,916.2811,443,000.00Awarded
16RR/RDA/18/25/23—
Horagasagara Nawarathna handiye sita Ihala kadigamuwa handiya dakwa margaya (Bingiriya)
100%
61,588,475.9261,588,475.92Awarded
17RR/RDA/18/25/99—
Rajanganaya reservoir to Parakumpura Junction (Left bank Road)
100%
312,810,182.55312,810,182.55Awarded
18RR/RDA/19/25/09—
Water front Mawatha (wennappuwa)
100%
12,072,583.1012,072,583.10Awarded
19RR/RDA/19/25/03—
Nawagattegama Rohala Pare sita Thapal Karyalaya Dakwa margaya (Nawagattegama)
100%
23,512,239.7923,512,239.79Awarded
20RR/RDA/18/25/06—
Walaliya Piduruwellewa road to the middle of the village
100%
19,431,074.9619,537,451.95Awarded
21RR/RDA/18/25/17—
No. 245 from near Jeevan Lasantha's house no. 37 Development of the main road up to Mr. Nihal's house with five (5) side roads.
100%
51,911,526.6751,911,526.67Awarded
22RR/RDA/18/25/21—
Wattakkawatta Road - Paving of Road (ABC Paving) from near Kelimune Pustalaya.
100%
39,422,351.3239,422,351.32Awarded
23RR/RDA/18/25/103—
Wellawa Thalatuwa Junction to Gepellawa Road
100%
31,387,050.8931,387,050.89Awarded
24RR/RDA/18/25/105—
Thihawa Junction to Mailamada
100%
33,866,057.6133,866,057.61Awarded
25RR/RDA/19/25/02—
Concrete development of the road from Hopper Kada junction to Elu Farm.
100%
33,229,489.5433,229,489.54Awarded
Showing 1–25 of 35
Per page:
Source: DRRRP • 79 projects • Data updated 2026-11-02 10:30 • 13:25:51