DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 59 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-02 10:30Live
Graphs reflect current view:59 awarded · North Western Province
74.7% awarded
0
Awarded
79 total projects 79 roads in portfolio
Awarded projects59
RR/RDA/18/25/01/NWP/KRGDevelopment of Egodagama Talakolawewa roadRR/RDA/18/25/02/NWP/KRGRoad from Parakumpura to Yaya 04RR/RDA/18/25/04/NWP/KRGThe road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa Beligahaya to Mee Oya bridgeRR/RDA/18/25/07/NWP/KRGRoad from Moragolla Junction to Nabadewa Girilla Carpet Road via KirindaRR/RDA/18/25/08/NWP/KRGPaving of road from Nammuawa to Nagansole templeRR/RDA/18/25/09/NWP/KRGPaving the road from Pahala Galapitiyagama to Tharanagolla Sports GroundRR/RDA/18/25/11/NWP/KRGDevelopment of road from Dambulu Road to Havanathenna via EhelagollayaRR/RDA/18/25/16/NWP/KRGDevelopment of concrete road from near Wadawa temple to the lakeRR/RDA/18/25/22/NWP/KRGPaving of culverts and sidewalls at the necessary places on the road from near Moragane Samiti Hall to Siyambalaweva via Galkadulla.RR/RDA/18/25/24/NWP/KRGPaving and developing the road from Seelarathana Mawatha to Girana JunctionRR/RDA/18/25/104/NWP/KRGPinnagolla Junction to Kokowaththa Junction VIA AlakolapelessaRR/RDA/18/25/106/NWP/KRGThagahinna Temple RoadRR/RDA/18/25/NWP/KRG/10Uyandana YaggapitiyaRR/RDA/18/25/135/NWP/KRGKelegedara Gamameda Road (CTB Basaya Dawanaya wana) Kavudumunna, Kunumade, Hungan pitiya haraha diwena Margaya Kapat KirimaRR/RDA/18/25/136/NWP/KRGRanasinghe Hotel Asalin Koralaya Waththe sita Panwala Kubura Dakwa Diwena Margaya Kapat Kirima
+44 more…
Click to filter the awarded table
2,201.9M
2,201.9 Mn
Contract Value
Awarded projects59
RR/RDA/18/25/01/NWP/KRGDevelopment of Egodagama Talakolawewa roadRR/RDA/18/25/02/NWP/KRGRoad from Parakumpura to Yaya 04RR/RDA/18/25/04/NWP/KRGThe road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa Beligahaya to Mee Oya bridgeRR/RDA/18/25/07/NWP/KRGRoad from Moragolla Junction to Nabadewa Girilla Carpet Road via KirindaRR/RDA/18/25/08/NWP/KRGPaving of road from Nammuawa to Nagansole templeRR/RDA/18/25/09/NWP/KRGPaving the road from Pahala Galapitiyagama to Tharanagolla Sports GroundRR/RDA/18/25/11/NWP/KRGDevelopment of road from Dambulu Road to Havanathenna via EhelagollayaRR/RDA/18/25/16/NWP/KRGDevelopment of concrete road from near Wadawa temple to the lakeRR/RDA/18/25/22/NWP/KRGPaving of culverts and sidewalls at the necessary places on the road from near Moragane Samiti Hall to Siyambalaweva via Galkadulla.RR/RDA/18/25/24/NWP/KRGPaving and developing the road from Seelarathana Mawatha to Girana JunctionRR/RDA/18/25/104/NWP/KRGPinnagolla Junction to Kokowaththa Junction VIA AlakolapelessaRR/RDA/18/25/106/NWP/KRGThagahinna Temple RoadRR/RDA/18/25/NWP/KRG/10Uyandana YaggapitiyaRR/RDA/18/25/135/NWP/KRGKelegedara Gamameda Road (CTB Basaya Dawanaya wana) Kavudumunna, Kunumade, Hungan pitiya haraha diwena Margaya Kapat KirimaRR/RDA/18/25/136/NWP/KRGRanasinghe Hotel Asalin Koralaya Waththe sita Panwala Kubura Dakwa Diwena Margaya Kapat Kirima
+44 more…
Click to filter the awarded table
Avg
82.3%
26
works in progress
31 completed
Avg Progress
Awarded projects59
RR/RDA/18/25/01/NWP/KRGDevelopment of Egodagama Talakolawewa roadRR/RDA/18/25/02/NWP/KRGRoad from Parakumpura to Yaya 04RR/RDA/18/25/04/NWP/KRGThe road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa Beligahaya to Mee Oya bridgeRR/RDA/18/25/07/NWP/KRGRoad from Moragolla Junction to Nabadewa Girilla Carpet Road via KirindaRR/RDA/18/25/08/NWP/KRGPaving of road from Nammuawa to Nagansole templeRR/RDA/18/25/09/NWP/KRGPaving the road from Pahala Galapitiyagama to Tharanagolla Sports GroundRR/RDA/18/25/11/NWP/KRGDevelopment of road from Dambulu Road to Havanathenna via EhelagollayaRR/RDA/18/25/16/NWP/KRGDevelopment of concrete road from near Wadawa temple to the lakeRR/RDA/18/25/22/NWP/KRGPaving of culverts and sidewalls at the necessary places on the road from near Moragane Samiti Hall to Siyambalaweva via Galkadulla.RR/RDA/18/25/24/NWP/KRGPaving and developing the road from Seelarathana Mawatha to Girana JunctionRR/RDA/18/25/104/NWP/KRGPinnagolla Junction to Kokowaththa Junction VIA AlakolapelessaRR/RDA/18/25/106/NWP/KRGThagahinna Temple RoadRR/RDA/18/25/NWP/KRG/10Uyandana YaggapitiyaRR/RDA/18/25/135/NWP/KRGKelegedara Gamameda Road (CTB Basaya Dawanaya wana) Kavudumunna, Kunumade, Hungan pitiya haraha diwena Margaya Kapat KirimaRR/RDA/18/25/136/NWP/KRGRanasinghe Hotel Asalin Koralaya Waththe sita Panwala Kubura Dakwa Diwena Margaya Kapat Kirima
+44 more…
Click to filter the awarded table
1,107.0M
1,107.0 Mn
Total Expenditure (incl. VAT)
Awarded projects59
RR/RDA/18/25/01/NWP/KRGDevelopment of Egodagama Talakolawewa roadRR/RDA/18/25/02/NWP/KRGRoad from Parakumpura to Yaya 04RR/RDA/18/25/04/NWP/KRGThe road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa Beligahaya to Mee Oya bridgeRR/RDA/18/25/07/NWP/KRGRoad from Moragolla Junction to Nabadewa Girilla Carpet Road via KirindaRR/RDA/18/25/08/NWP/KRGPaving of road from Nammuawa to Nagansole templeRR/RDA/18/25/09/NWP/KRGPaving the road from Pahala Galapitiyagama to Tharanagolla Sports GroundRR/RDA/18/25/11/NWP/KRGDevelopment of road from Dambulu Road to Havanathenna via EhelagollayaRR/RDA/18/25/16/NWP/KRGDevelopment of concrete road from near Wadawa temple to the lakeRR/RDA/18/25/22/NWP/KRGPaving of culverts and sidewalls at the necessary places on the road from near Moragane Samiti Hall to Siyambalaweva via Galkadulla.RR/RDA/18/25/24/NWP/KRGPaving and developing the road from Seelarathana Mawatha to Girana JunctionRR/RDA/18/25/104/NWP/KRGPinnagolla Junction to Kokowaththa Junction VIA AlakolapelessaRR/RDA/18/25/106/NWP/KRGThagahinna Temple RoadRR/RDA/18/25/NWP/KRG/10Uyandana YaggapitiyaRR/RDA/18/25/135/NWP/KRGKelegedara Gamameda Road (CTB Basaya Dawanaya wana) Kavudumunna, Kunumade, Hungan pitiya haraha diwena Margaya Kapat KirimaRR/RDA/18/25/136/NWP/KRGRanasinghe Hotel Asalin Koralaya Waththe sita Panwala Kubura Dakwa Diwena Margaya Kapat Kirima
+44 more…
Click to filter the awarded table
59.3%
0
On Progress
35 / 59 awarded
On Progress (incl. completed)35
RR/RDA/18/25/02/NWP/KRGRoad from Parakumpura to Yaya 04RR/RDA/18/25/08/NWP/KRGPaving of road from Nammuawa to Nagansole templeRR/RDA/18/25/16/NWP/KRGDevelopment of concrete road from near Wadawa temple to the lakeRR/RDA/18/25/24/NWP/KRGPaving and developing the road from Seelarathana Mawatha to Girana JunctionRR/RDA/18/25/104/NWP/KRGPinnagolla Junction to Kokowaththa Junction VIA AlakolapelessaRR/RDA/18/25/106/NWP/KRGThagahinna Temple RoadRR/RDA/18/25/NWP/KRG/10Uyandana YaggapitiyaRR/RDA/18/25/135/NWP/KRGKelegedara Gamameda Road (CTB Basaya Dawanaya wana) Kavudumunna, Kunumade, Hungan pitiya haraha diwena Margaya Kapat KirimaRR/RDA/18/25/136/NWP/KRGRanasinghe Hotel Asalin Koralaya Waththe sita Panwala Kubura Dakwa Diwena Margaya Kapat KirimaRR/RDA/19/25/26/NWP/PUTAbayarama Mawatha Bomimakka Kovil Road to Sembandaluwa Temple RoadRR/RDA/19/25/28/NWP/PUTSamagi MawathaRR/RDA/19/25/29/NWP/PUTDevelopment of the road from Galkuliya Welameda to Mrs. Deepani's houseRR/RDA/18/25/12Anura Mahaththayalage niwase sita Nalalida dakwa kadurugaha ela dakwa margaya (Ganewatte)RR/RDA/18/25/05158 Digana Grama niladari wasame 3 patumaga (vawa dakwa) (Yapahuwa)RR/RDA/18/25/23Horagasagara Nawarathna handiye sita Ihala kadigamuwa handiya dakwa margaya (Bingiriya)
+20 more…
Click to filter the awarded table
35.6%
0
Critical Delay
21 / 59 awarded
Critical Delay21
RR/RDA/18/25/01/NWP/KRGDevelopment of Egodagama Talakolawewa roadRR/RDA/18/25/04/NWP/KRGThe road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa Beligahaya to Mee Oya bridgeRR/RDA/18/25/07/NWP/KRGRoad from Moragolla Junction to Nabadewa Girilla Carpet Road via KirindaRR/RDA/18/25/09/NWP/KRGPaving the road from Pahala Galapitiyagama to Tharanagolla Sports GroundRR/RDA/18/25/11/NWP/KRGDevelopment of road from Dambulu Road to Havanathenna via EhelagollayaRR/RDA/18/25/22/NWP/KRGPaving of culverts and sidewalls at the necessary places on the road from near Moragane Samiti Hall to Siyambalaweva via Galkadulla.RR/RDA/18/25/137/NWP/KRGDamunugolla Sita Kobbewehera Handiya Dakwa Margaya Kapat KirimaRR/RDA/18/25/138/NWP/KRGPudukkulama Bogas Handiye sita Keppitiya haraha Thihawa Dakwa Margaya Kapat KirimaRR/RDA/19/25/01/NWP/PUTDevelopment of carpeting the Gammedda road up to Anathapara.RR/RDA/19/25/04/NWP/PUTCarpeting of green light carpeted road from Bogus Junction (80 acres).RR/RDA/19/25/05/NWP/PUTDevelopment of the road from near Mr. Chaminda's house to Boga PathahaRR/RDA/19/25/08/NWP/PUTCarpeting of Velasia Main Road from Madurankuliya.RR/RDA/19/25/27/NWP/PUTThe entrance to the Medical Officer's Office in the Galahitiyawa Grama Niladhari DivisionRR/RDA/19/25/30/NWP/PUTDevelopment of carpeting from Mihirajthotupola to Serakkuliya 1 on the Serakkuliya main roadRR/RDA/19/25/31/NWP/PUTDevelopment of carpeting from the point where carpeting has stopped on the Tammana main road
+6 more…
Click to filter the awarded table
52.5%
0
Completed
31 / 59 awarded
Completed31
RR/RDA/18/25/02/NWP/KRGRoad from Parakumpura to Yaya 04RR/RDA/18/25/08/NWP/KRGPaving of road from Nammuawa to Nagansole templeRR/RDA/18/25/16/NWP/KRGDevelopment of concrete road from near Wadawa temple to the lakeRR/RDA/18/25/24/NWP/KRGPaving and developing the road from Seelarathana Mawatha to Girana JunctionRR/RDA/18/25/104/NWP/KRGPinnagolla Junction to Kokowaththa Junction VIA AlakolapelessaRR/RDA/18/25/106/NWP/KRGThagahinna Temple RoadRR/RDA/18/25/NWP/KRG/10Uyandana YaggapitiyaRR/RDA/18/25/136/NWP/KRGRanasinghe Hotel Asalin Koralaya Waththe sita Panwala Kubura Dakwa Diwena Margaya Kapat KirimaRR/RDA/19/25/26/NWP/PUTAbayarama Mawatha Bomimakka Kovil Road to Sembandaluwa Temple RoadRR/RDA/19/25/28/NWP/PUTSamagi MawathaRR/RDA/19/25/29/NWP/PUTDevelopment of the road from Galkuliya Welameda to Mrs. Deepani's houseRR/RDA/18/25/12Anura Mahaththayalage niwase sita Nalalida dakwa kadurugaha ela dakwa margaya (Ganewatte)RR/RDA/18/25/05158 Digana Grama niladari wasame 3 patumaga (vawa dakwa) (Yapahuwa)RR/RDA/18/25/23Horagasagara Nawarathna handiye sita Ihala kadigamuwa handiya dakwa margaya (Bingiriya)RR/RDA/18/25/99Rajanganaya reservoir to Parakumpura Junction (Left bank Road)
+16 more…
Click to filter the awarded table
Portfolio Breakdown · North Western Province · Province
Avg Physical Progress per EE Division · North Western Province
At-Risk Projects · North Western Province
- RR/RDA/15/25/02/EP/BTCConcreting to Samurthi 1st Cross roadDelay636 Days in Delay · 20%
- RR/RDA/15/25/10Concreting to Internal at MMV SchoolDelay354 Days in Delay · 95%
- RR/RDA/25/24/01/SBP/RTPFrom Delgas Junction To Vilehena RoadDelay324 Days in Delay · 90%
- RR/RDA/25/24/03/SBP/RTPFrom Thunaghahena To Temple RoadDelay324 Days in Delay · 95%
- RR/RDA/07/25/02/SP/GALDelgahabedda-Kirimatiya MargayaDelay323 Days in Delay · 93%
- RR/RDA/08/25/05Koggalla bus stand to Sooriyawewa RoadDelay323 Days in Delay · 95%
- RR/RDA/07/25/05/SP/GALAtawalawatta Sri Rewatha Viduhala Idiripita MargayaDelay323 Days in Delay · 95%
- RR/RDA/07/25/09/SP/GALPanwila Hena Pradhana Margaya Lalith Mahathage Niwasa Asala Sita Manjula Jayaweera Mahathage Niwasa Dakwa MargayaDelay323 Days in Delay · 98%
- RR/RDA/07/25/17/SP/GALDasa Kadaya Asala sita Jack Fruit Ceylon (Pvt) ayathanaya dakwa Margaya 1 Km carpert kirimaDelay323 Days in Delay · 47%
- RR/RDA/19/25/01/NWP/PUTDevelopment of carpeting the Gammedda road up to Anathapara.Delay319 Days in Delay · 65%
- RR/RDA/09/25/07Carpeting Dabewelena Gravel RoadDelay308 Days in Delay · 98%
- RR/RDA/04/25/21/CP/KYGalaha group sita finas kotasa Pahalagama-Ihalagama haraha nawa rohala dakwa MargayaDelay308 Days in Delay · 80%
- RR/RDA/05/25/26/CP/MTLPallepola saukya karyalaye sita ekamuthugama dakwa margayaDelay308 Days in Delay · 60%
- RR/RDA/06/25/44Carpeting of Muloya Main Road Section 2Delay308 Days in Delay · 60%
- RR/RDA/06/25/47Carpeting of the road from Gatakula to Madanwala via Diaudagama, KottalaDelay308 Days in Delay · 38%
- RR/RDA/07/25/19/SP/GALSuriEla MargayaDelay300 Days in Delay · 96%
- RR/RDA/08/25/18/SP/MTRDekatukella Margaya Pethibemma sahithawa Sanwardanaya kirimaDelay300 Days in Delay · 0%
- RR/RDA/06/25/40/CP/NEWalapane Samachaithya asalin Arambawana Kurundu oya diyaella dakwa MargayaDelay299 Days in Delay · 10%
- RR/RDA/04/25/19/CP/KYMulgama viduhala Asala sita lewalan dakwaDelay294 Days in Delay · 35%
- RR/RDA/04/25/41/CP/KYKaryala handiya pahala margya concrete kirimaDelay294 Days in Delay · 85%
- RR/RDA/12/25/31/NP/VVNMahakachchakodiya to EttambagaskadaDelay288 Days in Delay · 30%
- RR/RDA/04/25/28/CP/KYDehideniya sita Hedeniya dakwa MargayaDelay285 Days in Delay · 35%
- RR/RDA/05/25/09/CP/MTLIlukkumbura Samurdhi karyalaya asala Patti ela pilama dakwaDelay285 Days in Delay · 80%
- RR/RDA/20/25/03/NCP/ANPThalawa - Eppawala margaye kele Amunukola handiyen aramba vee kele amunukola viddiyalayen divena margayaDelay281 Days in Delay · 40%
- RR/RDA/20/25/04/NCP/ANPA - 9 maragayen aramba vee wale kade dakwa margayaDelay281 Days in Delay · 45%
- RR/RDA/20/25/06/NCP/ANPUdudumbara boogas handiye sita sarakkugala pasal handiya dakwa margayaDelay281 Days in Delay · 0%
- RR/RDA/20/25/11/NCP/ANPPalayakulama sita halmillakulama dakwa margayaDelay281 Days in Delay · 75%
- RR/RDA/25/25/15/SBP/KGLMoraliya Gagaboda RoadDelay276 Days in Delay · 90%
- RR/RDA/19/25/27/NWP/PUTThe entrance to the Medical Officer's Office in the Galahitiyawa Grama Niladhari DivisionDelay274 Days in Delay · 60%
- RR/RDA/22/25/22/UP/BDLAchchupatti MargayaDelay272 Days in Delay · 20%
- RR/RDA/04/25/20/CP/KYCarpeting road Ratemulla to Wendesiwaththa EndDelay272 Days in Delay · 45%
- RR/RDA/12/25/54/NP/VVNNikawewa Right Village RoadDelay272 Days in Delay · 70%
- RR/RDA/12/25/10/NP/VVNAchchipuram amman temble roadDelay271 Days in Delay · 70%
- RR/RDA/12/25/20/NP/VVNPuthiyakudiyiruppu parasankulam roadDelay271 Days in Delay · 70%
- RR/RDA/12/25/21/NP/VVNBagaswewa 01st 22nd laneDelay271 Days in Delay · 35%
- RR/RDA/12/25/28/NP/VVNFrom Janaudanagama 2nd internal road to end of the free schoolDelay271 Days in Delay · 35%
- RR/RDA/15/25/15/EP/BTCConcrete to the Majma Nagar Mullivattuvan at paper town 210BDelay271 Days in Delay · 80%
- RR/RDA/15/25/05/EP/BTCConcreting to Mailanthanai Sri Muththumariyamman Main RoadDelay271 Days in Delay · 50%
- RR/RDA/15/25/09/EP/BTCConcreting to NHDA Housing Scheme Internal Road 1st 2nd CrossDelay271 Days in Delay · 40%
- RR/RDA/15/25/11/EP/BTCConcreting to Kali Kovil RoadDelay271 Days in Delay · 5%
- RR/RDA/15/25/14/EP/BTCConcreting to Agriculture RoadDelay271 Days in Delay · 60%
- RR/RDA/20/25/28/NCP/ANPDevelopment of Rathnayake MawathaDelay266 Days in Delay · 5%
- RR/RDA/12/25/18/NP/VVNNedunkerny North sandankulam RoadDelay265 Days in Delay · 35%
- RR/RDA/12/25/19/NP/VVNSenaipilavu RoadDelay265 Days in Delay · 70%
- RR/RDA/22/25/07/UP/BDLTharuna Govipola Margaye ithiri Kotasa Sanwardanaya KirieemaDelay264 Days in Delay · 0%
- RR/RDA/12/25/03/NP/VVNPuthiya manipuram, main road (NVSTE481)Delay264 Days in Delay · 35%
- RR/RDA/12/25/24/NP/VVNKanagarayankulam puthuvilankulam road (NVVNE073)Delay264 Days in Delay · 70%
- RR/RDA/12/25/29/NP/VVNKalasiyambalawa RoadDelay264 Days in Delay · 50%
- RR/RDA/25/25/20/SBP/KGLNeluwakkana gama meda RoadDelay259 Days in Delay · 95%
- RR/RDA/15/25/12/EP/BTCConcreting to Muthalaikuda to Munnaikkadu Boundary RoadDelay257 Days in Delay · 40%
- RR/RDA/15/25/13/EP/BTCConcreting to Sangarpuram- VilavadiDelay257 Days in Delay · 10%
- RR/RDA/12/25/25/NP/VVN2nd cross Lane GinigathhenaDelay256 Days in Delay · 70%
- RR/RDA/12/25/35/NP/VVNAwusadapitiya Pubudugama RoadDelay256 Days in Delay · 70%
- RR/RDA/12/25/07/NP/VVNTharanikulam main roadDelay255 Days in Delay · 70%
- RR/RDA/12/25/38/NP/VVNSalalinigama 11 laneDelay255 Days in Delay · 50%
- RR/RDA/12/25/40/NP/VVNHalabagaswewaDelay255 Days in Delay · 5%
- RR/RDA/12/25/43/NP/VVNPavatkulam tack 5 vaarikuttiyoorDelay255 Days in Delay · 70%
- RR/RDA/12/25/48/NP/VVNMukaththankulam 7th lane (NVVPE173)Delay255 Days in Delay · 70%
- RR/RDA/12/25/51/NP/VVNAdappankulam aladi roadDelay255 Days in Delay · 70%
- RR/RDA/05/25/28Adawala Udagama RoadDelay255 Days in Delay · 75%
- RR/RDA/13/25/01/NP/MULAkkaraiveli Paraiyanaru ( Vilaththiyad) Road Package 1Delay247 Days in Delay · 0%
- RR/RDA/18/25/09/NWP/KRGPaving the road from Pahala Galapitiyagama to Tharanagolla Sports GroundDelay246 Days in Delay · 0%
- RR/RDA/12/25/27/NP/VVNFrom Acre 400 7th Lane to cross end of the 2nd internal road close to AndarawewaDelay246 Days in Delay · 30%
- RR/RDA/14/25/06/NP/KLNSkanthapuram Kannan Temple roadDelay246 Days in Delay · 35%
- RR/RDA/14/25/08/NP/KLNKalmadu 7th unit 3rd laneDelay246 Days in Delay · 20%
- RR/RDA/20/25/16/NCP/ANPHiriwadunna handiye sita idigaswewa pansal handiya dakwa margayaDelay245 Days in Delay · 80%
- RR/RDA/19/25/05/NWP/PUTDevelopment of the road from near Mr. Chaminda's house to Boga PathahaDelay245 Days in Delay · 65%
- RR/RDA/19/25/04/NWP/PUTCarpeting of green light carpeted road from Bogus Junction (80 acres).Delay240 Days in Delay · 65%
- RR/RDA/16/25/03/AKK/AMPPolbedda Junction to Galwalayaya RoadDelay239 Days in Delay · 52%
- RR/RDA/14/25/09/NP/KLNNeliyai Amman kovil roadDelay239 Days in Delay · 0%
- RR/RDA/10/25/24/NP/KLNKevil Nithtiyaveddai Road 2.150Delay239 Days in Delay · 0%
- RR/RDA/21/25/03/NCP/POLMahasenpura pradeepika kadaya asala sita Katukeliyawa dakwa margaya Carpart kireemaDelay238 Days in Delay · 80%
- RR/RDA/11/25/09/NP/MNRRenovation of Mathirikiramam internal Road NaruvilikulamDelay238 Days in Delay · 70%
- RR/RDA/05/25/11/CP/MTLHunukete sita Elagala dakwa Pradana MargayaDelay223 Days in Delay · 50%
- RR/RDA/13/25/06/NP/MULPandaravanniyan Silaiyadi RoadDelay223 Days in Delay · 40%
- RR/RDA/13/25/07/NP/MULKanagarayankulam District Boundary Road (Old Kandy road)Delay223 Days in Delay · 60%
- RR/RDA/25/24/35Ilumba Kanda Road from Milinduthalawa TempleDelay218 Days in Delay · 30%
- RR/RDA/25/24/17Pahalawaththa to Batahenkanda RoadDelay218 Days in Delay · 10%
- RR/RDA/25/24/19Wijeriya Iththekanda Margaya Sanwardanaya KirimaDelay218 Days in Delay · 35%
- RR/RDA/25/24/20Godawela Walakada margaya Sanwardanaya Kirima (Walakada Junction to Godawela Junction)Delay218 Days in Delay · 15%
- RR/RDA/17/25/08Concreting of Play Ground Road Mahadiulwewa Stage IIDelay218 Days in Delay · 90%
- RR/RDA/13/25/03/NP/MULNavatkadu RoadDelay217 Days in Delay · 60%
- RR/RDA/13/25/08/NP/MULKumulamunai Akkarayan roadDelay217 Days in Delay · 70%
- RR/RDA/13/25/10/NP/MULPandiyankulam Neddankandal RoadDelay217 Days in Delay · 70%
- RR/RDA/10/25/25/NP/JFNPalaiya Vaikal VeeethyDelay216 Days in Delay · 50%
- RR/RDA/11/25/16/NP/MNRP.P.Potkerny Scheme Internal Road 1Delay216 Days in Delay · 70%
- RR/RDA/11/25/18/NP/MNRAkaththimurippu Internal Road 3Delay216 Days in Delay · 70%
- RR/RDA/10/25/22/NP/JFNAnaivilunthan Sudalai RoadDelay215 Days in Delay · 65%
- RR/RDA/19/25/08/NWP/PUTCarpeting of Velasia Main Road from Madurankuliya.Delay214 Days in Delay · 70%
- RR/RDA/10/25/18/NP/JFNAtchuvely Industrial RoadDelay214 Days in Delay · 70%
- RR/RDA/18/25/137/NWP/KRGDamunugolla Sita Kobbewehera Handiya Dakwa Margaya Kapat KirimaDelay212 Days in Delay · 45%
- RR/RDA/18/25/138/NWP/KRGPudukkulama Bogas Handiye sita Keppitiya haraha Thihawa Dakwa Margaya Kapat KirimaDelay211 Days in Delay · 20%
- RR/RDA/19/25/30/NWP/PUTDevelopment of carpeting from Mihirajthotupola to Serakkuliya 1 on the Serakkuliya main roadDelay206 Days in Delay · 70%
- RR/RDA/19/25/33/NWP/PUTDevelopment of the road from near the Sugatarama Temple, Periyakulam to ThalgaswewaDelay206 Days in Delay · 45%
- RR/RDA/19/25/37/NWP/PUTLawyer Wijayananda's House RoadDelay204 Days in Delay · 70%
- RR/RDA/19/25/38/NWP/PUTNorth Dummaladeniya Cross RoadDelay204 Days in Delay · 90%
- RR/RDA/10/25/06/NP/JFNRenovation of West beach RoadDelay200 Days in Delay · 10%
- RR/RDA/19/25/39/NWP/PUTRenovation of Khemananda RoadDelay199 Days in Delay · 95%
- RR/RDA/03/25/12/WP/KTRConcreting Batawala RoadDelay197 Days in Delay · 39%
- RR/RDA/12/25/13/NP/VVNNanthimiththiragama 2ndDelay196 Days in Delay · 5%
- RR/RDA/12/25/14/NP/VVNNanthimiththiragama 4thDelay196 Days in Delay · 5%
- RR/RDA/05/25/10/CP/MTLSonuththa pradana margaye Shailatharamaya idiriye sita 80 yaya dakwaDelay191 Days in Delay · 70%
- RR/RDA/25/24/10/SBP/RTPFrom Deniya kade Market to Henyaya Road Via Keenagahaella RoadDelay191 Days in Delay · 95%
- RR/RDA/25/25/03/SBP/KGLFrom Kehelpannala Junction to Pahala Kabawita RoadDelay188 Days in Delay · 95%
- RR/RDA/25/24/02/SBP/RTPThundola Varathenna RoadDelay186 Days in Delay · 35%
- RR/RDA/25/25/02/SBP/KGLElagapitiya Colany Road From Debathgama Pallebage to Tea Shakthi Praja ShalawaDelay184 Days in Delay · 85%
- RR/RDA/18/25/01/NWP/KRGDevelopment of Egodagama Talakolawewa roadDelay182 Days in Delay · 60%
- RR/RDA/04/25/25/CP/KYDelgasthenna RoadDelay182 Days in Delay · 0%
- RR/RDA/06/25/34/CP/NEUdupussellawa margaye Amasta handiye sita Ambagasdowa dakwa MargayaDelay182 Days in Delay · 0%
- RR/RDA/06/25/38/CP/NEKetahira Gallella margya palama haraha Udagama dakwa MargayaDelay182 Days in Delay · 0%
- RR/RDA/16/25/10KM/04/AKK/AMPVevinna Boogas Junction Inner RoadDelay180 Days in Delay · 15%
- RR/RDA/11/25/05/NP/MNRKonnayan Kudiyiruppu Internal Main RoadDelay179 Days in Delay · 5%
- RR/RDA/18/25/07/NWP/KRGRoad from Moragolla Junction to Nabadewa Girilla Carpet Road via KirindaDelay176 Days in Delay · 75%
- RR/RDA/19/25/32/NWP/PUTDevelopment of the Bammeyaya RoadDelay176 Days in Delay · 50%
- RR/RDA/19/25/34/NWP/PUTCarpeting & Development of Bodhirajapura 4th LaneDelay176 Days in Delay · 70%
- RR/RDA/01/25/14/WP/COLDevelopment of the section from Arangala Bridge to Mihindu Mawatha in Malabe West DivisionDelay176 Days in Delay · 68%
- RR/RDA/19/25/31/NWP/PUTDevelopment of carpeting from the point where carpeting has stopped on the Tammana main roadDelay175 Days in Delay · 50%
- RR/RDA/01/25/19WP/COLPuwakpitiya Dharmalapala Mawatha Main Road Development of the road from High Level Road to Elstonwatte Volleyball CourtDelay173 Days in Delay · 90%
- RR/RDA/16/25/10KM/07/AKK/AMPBedirakka Malgastalawa RoadDelay173 Days in Delay · 0%
- RR/RDA/18/25/139/NWP/KRGAkkara Panaha Mansandiye Sita Walahamulla Dakwa MargayaDelay170 Days in Delay · 90%
- RR/RDA/18/25/135/NWP/KRGKelegedara Gamameda Road (CTB Basaya Dawanaya wana) Kavudumunna, Kunumade, Hungan pitiya haraha diwena Margaya Kapat KirimaDelay168 Days in Delay · 20%
- RR/RDA/06/25/32/CP/NENanuoya Glaso pahala kotasa MargayaDelay168 Days in Delay · 5%
- Development of the road from Madurankuliya to Velasiya CollegeDelay167 Days in Delay · 30%
- RR/RDA/12/25/63/NP/VVN1st Cross Street Alakarai RoadDelay167 Days in Delay · 30%
- RR/RDA/12/25/12/NP/VVNNanthimiththiragama 1stDelay166 Days in Delay · 5%
- RR/RDA/16/25/10KM/03/AKK/AMPOn the road from Pulungasmulla to Padawala, the road from near Shanta Veladasala towards PadawalaDelay163 Days in Delay · 55%
- RR/RDA/11/25/01/NP/MNRMahilankulam Pallamadhu roadDelay163 Days in Delay · 50%
- RR/RDA/11/25/02/NP/MNRPiramanayankulam Parappukadanthan roadDelay163 Days in Delay · 55%
- RR/RDA/10/25/14/NP/JFNPankuru VeethyDelay162 Days in Delay · 60%
- RR/RDA/STA II/16/25/03/AKK/AMPPadiyathalawa Navinna road from Navinna Junction A5 to Navinna BridgeDelay162 Days in Delay · 65%
- RR/RDA/16/25/10KM/01/AKK/AMPThe road from the bridge near Ridee ela Temple to Island Plot No. 197Delay162 Days in Delay · 17%
- RR/RDA/16/25/10KM/08/AKK/AKKRDS Road Addalachena 6, 8Delay161 Days in Delay · 0%
- RR/RDA/25/25/40/SBP/KGLKabagamuwa 17 Acres Road DevelopmentDelay160 Days in Delay · 95%
- RR/RDA/01/25/26/WP/COLBoraluwathenna Pahala Uda RoadDelay159 Days in Delay · 5%
- RR/RDA/25/25/35/SBP/KGLKudadeniya Adurapola Watta RoadDelay155 Days in Delay · 60%
- RR/RDA/12/25/04/NP/VVNSuntharapuram main roadDelay154 Days in Delay · 35%
- RR/RDA/12/25/17/NP/VVNLyca village enterance RoadDelay154 Days in Delay · 35%
- RR/RDA/12/25/22/NP/VVNMannankerny roadDelay154 Days in Delay · 50%
- RR/RDA/12/25/52/NP/VVNMenanager Malakattu Kalkuwari RoadDelay154 Days in Delay · 65%
- RR/RDA/25/25/38/SBP/KGLDevelopment of the road near the closed tea factory on Edurapola Watta main roadDelay153 Days in Delay · 95%
- RR/RDA/18/25/22/NWP/KRGPaving of culverts and sidewalls at the necessary places on the road from near Moragane Samiti Hall to Siyambalaweva via Galkadulla.Delay153 Days in Delay · 65%
- RR/RDA/11/25/04/NP/MNRTharavankottai to Keeri Main RoadDelay153 Days in Delay · 60%
- RR/RDA/11/25/07/NP/MNRAvithappar Panimayam Internal Road with Culvert - PesalaiDelay153 Days in Delay · 70%
- RR/RDA/11/25/11/NP/MNREruvittan - Vellalakaddu RoadDelay153 Days in Delay · 5%
- RR/RDA/02/25/08Carpeting of the road from near the Buddha Temple towards the Lindara Temple on the Neligama Guru Godella Road started from Halugama Dharmapala Colledge in the Lindara Grama Niladhari Division of the Mirigama Divisional Secretariat.Delay152 Days in Delay · 20%
- Carpeting of road from Bambaragama Moragollahinna to KaramidulaDelay152 Days in Delay · 10%
- Carpeting of Mahathenna to Hapugasdeniya Main RoadDelay152 Days in Delay · 73%
- RR/RDA/16/25/10KM/02/AKK/AMPRoad from Nelum Cafe Junction to NeeththaDelay152 Days in Delay · 20%
- RR/RDA/16/25/10KM/11/AKK/AKKKalyana Road - Periyanilavanai Vishnu Kovil Road to Maradamuna Mashur Maulana RoadDelay151 Days in Delay · 10%
- RR/RDA/16/25/10KM/05/AKK/AMPRoad from Dorapaha Junction to Navagiriya LakeDelay150 Days in Delay · 10%
- RR/RDA/18/25/04/NWP/KRGThe road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa Beligahaya to Mee Oya bridgeDelay148 Days in Delay · 40%
- RR/RDA/05/25/23Manchanayake shed eka asala sita sampath waththa haraha Galketiyawa margayaDelay144 Days in Delay · 60%
- RR/RDA/16/25/10KM/13/AKK/AKKJaica - Tsunami Village RoadDelay144 Days in Delay · 70%
- RR/RDA/09/25/08/SP/HMBCarpeting Pissubedda Medagamgoda roadDelay138 Days in Delay · 98%
- RR/RDA/13/25/11/NP/MULEthawetuvuwewa to SampathnuwaraDelay135 Days in Delay · 30%
- RR/RDA/20/25/18/NCP/ANPPahala Talawa road of Thalawa Andarawewa roadDelay127 Days in Delay · 80%
- RR/RDA/SP/16/25/01/AKK/AMPRectification and Asphalt Surfacing on Ambahagawela -Namaloya Main RoadDelay127 Days in Delay · 34%
- RR/RDA/18/25/11/NWP/KRGDevelopment of road from Dambulu Road to Havanathenna via EhelagollayaDelay126 Days in Delay · 65%
- RR/RDA/03/25/16/WP/KTRDevelopment of carpeting of 1 km from Gane Aramba Road, Bogalla Junction to Ambepitiya PinhenaDelay124 Days in Delay · 0%
- RR/RDA/03/25/18/WP/KTRDevelopment of carpeting of the section (length 800 m) from near Minerithenna temple to Jananandanarama templeDelay124 Days in Delay · 0%
- RR/RDA/12/25/60/NP/VVNSalalinigama lane 12Delay124 Days in Delay · 15%
- RR/RDA/12/25/62/NP/VVNPeriyavilathikulamDelay124 Days in Delay · 35%
- RR/RDA/12/25/64/NP/VVNNedunkulamaDelay124 Days in Delay · 70%
- RR/RDA/04/25/31(1)/CP/KYPaththunupitiya School road to Gampola Road through Pallegama AnguruwalaDelay120 Days in Delay · 30%
- Near Urapana Sisira Coir Mill to Hapugahagama Co-operativeDelay117 Days in Delay · 0%
- Udupila South DolewattaDelay113 Days in Delay · 0%
- Road from Pinnawatta Junction to Mr. Sandaruwan's shop on the Hapitiya entrance roadDelay106 Days in Delay · 0%
- 3 A road carpeted development near the Japanese Montessori at the junction of the North Kadirana Division.Delay106 Days in Delay · 0%
- RR/RDA/09/25/13/SP/HMBDevelopment of the road from Puak Dandawa near Aligerappa house through Weerasijahagoda to Satinamaluwa Kapuduarawatta field.Delay105 Days in Delay · 60%
- Development of 0.8 km carpeting of Newfa MawathaDelay105 Days in Delay · 0%
- Carpeting and development of 500 meters of Moragahakanda watta Bodumaga Senasuna Viharastha RoadDelay105 Days in Delay · 55%
- Development of from Lewis Stadium to Heladiva MalshalawaDelay105 Days in Delay · 55%
- RR/RDA/09/25/09/SP/HMBDevelopment of the road in front of Godawela School to Ambussa WelaDelay104 Days in Delay · 60%
- RR/RDA/06/25/41/CP/NENayapana Gammada tharapara sanwardhanayaDelay98 Days in Delay · 35%
- Wijekoon Mawatha near Narammala Bus Stand and Hospital Mawatha from PeralaswellaDelay94 Days in Delay · 65%
- Development of entrance roads, pedestrian rest areas and parking areas of the Sri Dalada Maligawa premisesDelay89 Days in Delay · 40%
- RR/RDA/05/25/30/CP/MTLGanadewi pilimaya asala Kulathunga mahathage welanda sala dakwaDelay86 Days in Delay · 60%
- RR/RDA/25/25/28/SBP/KGLNaagas thenna RoadDelay84 Days in Delay · 90%
- The road from Thaladuwa Road near Negombo Bus Stand, passing Jude Church, to the cemeteryDelay84 Days in Delay · 0%
- Development of Fenando Road - Picchawala RoadDelay79 Days in Delay · 0%
- RR/RDA/04/25/13/CP/KYGonaala Pasala Asala Sita Kubukkadura Athuru Margayak Wana Gurumada MargayaDelay75 Days in Delay · 37%
- RR/RDA/17/25/09/EP/TRNSchool-Galmetiyawa Main Internal RoadDelay75 Days in Delay · 50%
- RR/RDA/SP/17/25/03/EP/TRNHajra Road (Alhira Jalaira Road)Delay75 Days in Delay · 40%
- RR/RDA/04/25/52/CP/KYBokalawela Road from Hapugoda Junction to Ranawana (Drinage System Development and Road)Delay74 Days in Delay · 60%
- RR/RDA/06/25/42/CP/NEAC Overlaying from Polpitiya Junction to 04th Mile Post (CH 3+700 – 8+700 km)Delay74 Days in Delay · 50%
- RR/RDA/21/25/17/NCP/POLDevelopment of the road from Kaduruwela Muslim Kolaniya road to Pachcha PalliyaDelay72 Days in Delay · 80%
- RR/RDA/01/25/30/WP/COLDevelopment of the road from near the transformer near Seebara Kade, Boralugoda to the Jayanthi RoadDelay67 Days in Delay · 0%
- RR/RDA/25/25/39/SBP/KGLDevelopment of Gatayamulla Jagatpura Pannala Rasnadeniya roadDelay65 Days in Delay · 95%
- RR/RDA/20/25/01/NCP/ANPRoad from Thambuttegama - Nochchiyagama road to the road near the DIG's office of Thambuthegama RajanganayaDelay62 Days in Delay · 30%
- RR/RDA/09/25/11/SP/HMBDevelopment of Walasmulla Daluwakgoda School RoadDelay62 Days in Delay · 20%
- RR/RDA/17/25/11/EP/TRNDevelopment of Road from near the FairDelay62 Days in Delay · 15%
- RR/RDA/17/25/19/EP/TRNPeriya Suwami Kovil Road-ConcreteDelay62 Days in Delay · 20%
- RR/RDA/04/25/53/CP/KYRoad from Amuvandeniya to Magurudeniya (development of the drainage and carpeting of the road)Delay57 Days in Delay · 40%
- RR/RDA/02/25/03/WP/GMPDevelopment of De silva road beginning from Angurukaramulla temble road to Negombo Colombo roadDelay37 Days in Delay · 0%
- RR/RDA/12/25/01/NP/VVNThiruchchenthooran mill road NVSTE541Delay36 Days in Delay · 0%
- RR/RDA/21/25/17/NCP/POLDevelopment of 1 canal Road from Kadurwela Muslim Kolaniya Road to Parakum MawathaDelay34 Days in Delay · 45%
- Development of the Dolapihilla road from Navinnapitiya via DeldeniyaDelay30 Days in Delay · 20%
- RR/RDA/24/25/34/SBP/RTPMatuwagala Mudun Kotu RoadDelay22 Days in Delay · 0%
- RR/RDA/24/25/21/SBP/RTPSudagala Grama Seva Division, From Sudagala to Tunudola Road up the mountain to near the cooperativeDelay22 Days in Delay · 0%
- RR/RDA/02/25/18/WP/GAMPeliyagoda Naranminiya RoadDelay15 Days in Delay · 0%
- Development of first phase of road from Punewa to WarakwewaDelay14 Days in Delay · 25%
- Development of road from Sripura main road to 38 Kolaniya CemeteryDelay13 Days in Delay · 2%
- RR/RDA/25/25/34/SBP/KGLRoad Connecting Ihala Palampitiya and Pahala PalampitiyaDelay13 Days in Delay · 0%
- RR/RDA/15/25/10KM/01/BTCSooriya farm Road sathurukondanDelay12 Days in Delay · 50%
- RR/RDA/15/25/10KM/02/BTCIruthayapuram west 8th crossDelay12 Days in Delay · 30%
- RR/RDA/15/25/10KM/08/BTCPoosakar Road, Kannakipuram, MahiloorDelay12 Days in Delay · 95%
- 241 B Near Weliweriya North Suruwama Junction to Weliweriya TownDelay6 Days in Delay · 0%
- RR/RDA/17/25/10KM/04/EP/TRNKajuwaththa gama meda roadDelay6 Days in Delay · 5%
- RR/RDA/17/25/10KM/06/EP/TRNBudu pilima and 4th lane roadDelay6 Days in Delay · 15%
- RR/RDA/20/25/26/NCP/ANPDevelopment of IV lane from Nuwara Road to Mihinthalaya RoadDelay2 Days in Delay · 6%
- RR/RDA/20/25/29/NCP/ANPDevelopment of the road from Udugama Colony rural road near the A9 road to the front of Mr. Somaratne Senanayake's houseDelay2 Days in Delay · 0%
- Development of road from Wahalkada D6 to Thalapakattialam on Punchimudagama roadDelay2 Days in Delay · 5%
- Development of the road from Punewa Junction to Kudahalmillewa LakeDelay2 Days in Delay · 25%
- Development of the road from near Ikirigollawa Muslim Maha Vidyalaya to Ratmalgahawewa main road from near Ikirigollawa dam to Ratmalgahawa roadDelay2 Days in Delay · 30%
- From Makicchawa Junction to Temple (to Kulumiwakada Junction)Delay2 Days in Delay · 35%
- RR/RDA/15/25/10KM/07/BTCKanady cross Road to Magalingeshwarar kovil RoadDelay1 Day in Delay · 5%
- RR/RDA/17/25/10KM/08/EP/TRNPaththini Amman Kevil roadDelay1 Day in Delay · 25%
- RR/RDA/17/25/10KM/09/EP/TRNBazar mosque roadDelay1 Day in Delay · 40%
Portfolio Timeline· 51 scheduled projects · North Western Province Toggle
2025-06-21 today2026-11-04
Portfolio · Awarded Works
Awarded Projects
21 projects
Filter awarded works
21 matching projects1 active
| # | Contract No. | Package No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|---|---|
| 1 | RR/RDA/18/25/01/NWP/KRG | RR/RDA/18/25/01 | Development of Egodagama Talakolawewa road | 60% | 98,323,766.14 | 156,184,445.89 | Awarded |
| 2 | RR/RDA/18/25/04/NWP/KRG | RR/RDA/18/25/04 | The road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa Beligahaya to Mee Oya bridge | 40% | 59,066,766.74 | 85,865,152.06 | Awarded |
| 3 | RR/RDA/18/25/07/NWP/KRG | RR/RDA/18/25/07 | Road from Moragolla Junction to Nabadewa Girilla Carpet Road via Kirinda | 75% | 59,247,280.29 | 79,393,864.19 | Awarded |
| 4 | RR/RDA/18/25/09/NWP/KRG | RR/RDA/18/25/09 | Paving the road from Pahala Galapitiyagama to Tharanagolla Sports Ground | 0% | 70,405,428.60 | 81,982,091.15 | Awarded |
| 5 | RR/RDA/18/25/11/NWP/KRG | RR/RDA/18/25/11 | Development of road from Dambulu Road to Havanathenna via Ehelagollaya | 65% | 46,193,949.68 | 64,750,199.52 | Awarded |
| 6 | RR/RDA/18/25/22/NWP/KRG | RR/RDA/18/25/22 | Paving of culverts and sidewalls at the necessary places on the road from near Moragane Samiti Hall to Siyambalaweva via Galkadulla. | 65% | 67,074,479.55 | 77,881,819.09 | Awarded |
| 7 | RR/RDA/18/25/137/NWP/KRG | RR/RDA/18/25/137 | Damunugolla Sita Kobbewehera Handiya Dakwa Margaya Kapat Kirima | 45% | 18,425,029.46 | 23,865,719.81 | Awarded |
| 8 | RR/RDA/18/25/138/NWP/KRG | RR/RDA/18/25/138 | Pudukkulama Bogas Handiye sita Keppitiya haraha Thihawa Dakwa Margaya Kapat Kirima | 20% | 30,650,394.06 | 39,359,193.23 | Awarded |
| 9 | RR/RDA/18/25/308 | Wijekoon Mawatha near Narammala Bus Stand and Hospital Mawatha from Peralaswella | 65% | 10,696,008.28 | 11,985,499.69 | Awarded | |
| 10 | RR/RDA/19/25/01/NWP/PUT | RR/RDA/19/25/01 | Development of carpeting the Gammedda road up to Anathapara. | 65% | 27,734,432.55 | 24,961,884.73 | Awarded |
| 11 | RR/RDA/19/25/04/NWP/PUT | RR/RDA/19/25/04 | Carpeting of green light carpeted road from Bogus Junction (80 acres). | 65% | 34,055,720.05 | 59,154,724.51 | Awarded |
| 12 | RR/RDA/19/25/05/NWP/PUT | RR/RDA/19/25/05 | Development of the road from near Mr. Chaminda's house to Boga Pathaha | 65% | 36,592,843.95 | 60,367,316.08 | Awarded |
| 13 | RR/RDA/19/25/08/NWP/PUT | RR/RDA/19/25/08 | Carpeting of Velasia Main Road from Madurankuliya. | 70% | 39,584,083.50 | 61,899,364.50 | Awarded |
| 14 | RR/RDA/19/25/27/NWP/PUT | RR/RDA/19/25/27 | The entrance to the Medical Officer's Office in the Galahitiyawa Grama Niladhari Division | 60% | 38,495,776.00 | 49,714,778.94 | Awarded |
| 15 | RR/RDA/19/25/30/NWP/PUT | RR/RDA/19/25/30 | Development of carpeting from Mihirajthotupola to Serakkuliya 1 on the Serakkuliya main road | 70% | 38,494,009.50 | 45,465,357.54 | Awarded |
| 16 | RR/RDA/19/25/31/NWP/PUT | RR/RDA/19/25/31 | Development of carpeting from the point where carpeting has stopped on the Tammana main road | 50% | 26,013,841.83 | 39,960,885.90 | Awarded |
| 17 | RR/RDA/19/25/32/NWP/PUT | RR/RDA/19/25/32 | Development of the Bammeyaya Road | 50% | 10,904,293.40 | 17,431,257.91 | Awarded |
| 18 | RR/RDA/19/25/33/NWP/PUT | RR/RDA/19/25/33 | Development of the road from near the Sugatarama Temple, Periyakulam to Thalgaswewa | 45% | 24,440,875.25 | 38,370,082.14 | Awarded |
| 19 | RR/RDA/19/25/34/NWP/PUT | RR/RDA/19/25/34 | Carpeting & Development of Bodhirajapura 4th Lane | 70% | 12,568,847.50 | 19,966,435.66 | Awarded |
| 20 | RR/RDA/19/25/37/NWP/PUT | RR/RDA/19/25/37 | Lawyer Wijayananda's House Road | 70% | 7,763,919.68 | 9,913,614.44 | Awarded |
| 21 | RR/RDA/19/25/91 | Development of Fenando Road - Picchawala Road | 0% | 26,046,308.34 | 27,030,199.65 | Awarded |
Showing 1–21 of 21
Source: DRRRP • 79 projects • Data updated 2026-11-02 10:30 • 09:54:01 System live • Sri Lanka • 2 districts