Project Monitoring Dashboard

Comprehensive overview of 2 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-04 16:23Live
Graphs reflect current view:2 awarded · Southern Province
50%

0

On Progress

1 / 2 awarded

50%

0

Delay

1 / 2 awarded

0%

0

Critical Delay

0 / 2 awarded

50%

0

Completed

1 / 2 awarded

Portfolio Breakdown · Southern Province · Province

171Awarded266Total
Southern Province 2 awarded of 2 Open filtered view
CategoryTotal PortfolioAwarded PortfolioPendingAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
TotalEstimate LKR MnAwardedAwarded Est LKR MnContract LKR Mn
Emergency232.5232.528.40100%28.4—100.0%99.0%11——
DC - Roads00.000.00.000%————————
DC - Slope00.000.00.000%————————
PD(CP) - Slope00.000.00.000%————————
Southern Province232.5232.528.40100%28.40.00% of contract100.0%99.0%1100

Avg Physical Progress per EE Division · Southern Province

At-Risk Projects · Southern Province

92
Portfolio Timeline· 2 scheduled projects · Southern Province Toggle
2026-07-06 today2026-11-04
Portfolio · Awarded Works

Awarded Projects

1 projects

1/1 (filtered)

Filter awarded works

1 matching project1 active

ActiveDelayed only
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/SP/GAL/HIN/03
Rehabilitation / Improvement of Gabbion Walls along Udugama - Hiniduma (9+920- 9+938-LHS), (7+450-7+472-LHS), (5+150-5+17 LHS)
98%
19,453,314.5422,102,879.06Awarded
Showing 1–1 of 1
Per page:
Source: DRRRP • 2 projects • Data updated 2026-11-04 16:23 • 16:28:55