DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 73 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:73 awarded · Eastern Province

Portfolio Breakdown · Eastern Province · Province

579Awarded739Total
Eastern Province 73 awarded of 86 Open filtered view
CategoryImplementation MethodTotal PortfolioAwarded PortfolioPending RoadsAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
Total RoadsTotal ProjectsEst. Sanctioned ProjectsEst. Sanctioned RoadsPending Sanctioned RoadsSanctioned Length kmSanctioned Amount LKR MnEstimate LKR MnLOA Issued ProjectsLOA Issued RoadsAwarded Est LKR MnContract LKR Mn
TenderTender Above 50Mn16161616037.601,629.11,629.166819.7566.41038%545.9152.027% of contract96.8%43.5%——6—
Tender Below 50Mn58585858039.651,816.61,816.655551,742.61,164.1395%435.5376.332% of contract41.8%55.1%39—16—
PIU000000.000.00.00—0.00.000%————————
Not Specified000000.000.00.00—0.00.000%————————
Tender Total74747474077.253,445.73,445.761612,562.31,730.51382%981.4528.331% of contract47.2%53.9%390220
Direct LabourDL Stage 01666607.48311.7311.766311.7311.70100%140.0220.071% of contract83.3%100.0%6———
DL Stage 02222200.9549.349.32249.349.30100%49.340.181% of contract100.0%97.5%11——
DL Stage 03111101.0048.848.81148.848.80100%—50.6104% of contract0.0%100.0%1———
DL Stage 04333303.1593.993.93393.993.90100%43.272.777% of contract33.3%96.7%21——
Direct Labour Total12121212012.58503.8503.81212503.8503.80100%232.5383.476% of contract66.6%98.8%10200
—Eastern Province86868686089.833,949.53,949.573733,066.12,234.31385%1,214.0911.741% of contract50.4%61.3%492220

Avg Physical Progress per EE Division · Eastern Province

At-Risk Projects · Eastern Province

218
Portfolio Timeline· 73 scheduled projects · Eastern Province Toggle
2025-06-21 today2027-03-11
Portfolio · Awarded Works

Awarded Projects

30 projects

25/30 (filtered)

Filter awarded works

30 matching projects1 active

ActiveCompleted
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/16/25/04/AKK/AMPRR/RDA/16/25/04
Pokunugama near Mr. Dinesh Tharaga House to Road (From Pokunugama Pre School to up to Mr. Dinesh Tharaga House)
100%
6,435,000.0010,039,653.26Awarded
2RR/RDA/16/25/01/AKK/AMPRR/RDA/16/25/01
Samanalathenna- Road from House No.63 To the Monastery Muwagammana -From First Lane to Cemetry
100%
21,336,681.8736,719,169.87Awarded
3RR/RDA/STA II/16/25/02/AKK/AMPRR/RDA/STA II/16/25/02
Concreting entrance road with culvert at Dehiaththakandiya Kelegama
100%
30,737,790.6047,778,623.73Awarded
4RR/RDA/STA II/16/25/04/AKK/AKKRR/RDA/STA II/16/25/04
Lahugala Hulannuge Roundabout road
100%
26,597,958.2036,508,598.90Awarded
5RR/RDA/16/25/10KM/06/AKK/AKKRR/RDA/16/25/10KM/06
Hulannuge School Road
100%
11,406,166.7317,414,587.68Awarded
6RR/RDA/16/25/10KM/09/AKK/AKKRR/RDA/16/25/10KM/09
Road behind Necode Institute (Navatkadu Akkarapattu)
100%
15,228,903.2524,614,649.47Awarded
7RR/RDA/15/25/01/EP/BTCRR/RDA/15/25/01
Concreting to Vipulananthar road
100%
29,074,090.8944,424,075.79Awarded
8RR/RDA/15/25/07/EP/BTCRR/RDA/15/25/07
Concreting to Thakwa masjith Cross Road
100%
22,206,567.3036,804,461.32Awarded
9RR/RDA/17/25/01/EP/TRNRR/RDA/17/25/01
Pillayar Road Renovation
100%
23,425,921.5630,058,596.03Awarded
10RR/RDA/17/25/02/EP/TRNRR/RDA/17/25/02
Kathirkamathambi Road
100%
28,809,738.0038,871,590.79Awarded
11RR/RDA/17/25/03/EP/TRNRR/RDA/17/25/03
Hospital Road
100%
18,557,253.7723,553,502.50Awarded
12RR/RDA/17/25/07/EP/TRNRR/RDA/17/25/07
Kanthamalawa Main Road
100%
9,161,570.0017,579,515.67Awarded
13RR/RDA/17/25/10/EP/TRNRR/RDA/17/25/10
From Medagama temple to Peramaduwa
100%
24,197,635.0031,162,876.79Awarded
14RR/RDA/17/25/12/EP/TRNRR/RDA/17/25/12
Improvement of RDS Road
100%
30,166,053.0038,673,984.79Awarded
15RR/RDA/17/25/13/EP/TRNRR/RDA/17/25/13
Concreting from School junction to Boovidya Office
100%
38,264,100.0049,104,899.44Awarded
16RR/RDA/17/25/14/EP/TRNRR/RDA/17/25/14
Amaithusha Road (School road to Vaithiyar road)
100%
5,006,100.006,650,570.02Awarded
17RR/RDA/17/25/15/EP/TRNRR/RDA/17/25/15
Cemetery Road (Sajahan Mowlavi's house to Thajudeen shop)
100%
21,774,456.0027,637,562.79Awarded
18RR/RDA/17/25/16/EP/TRNRR/RDA/17/25/16
Valuvar Road (Main road to Kovil road)
100%
10,783,850.0013,997,601.51Awarded
19RR/RDA/17/25/18/EP/TRNRR/RDA/17/25/18
Sooranagar Main Road (Muththuchenai Junction to Thuvaraka Vithiyalayam)-Concrete
100%
25,155,240.0038,483,392.50Awarded
20RR/RDA/SP/17/25/01/EP/TRNRR/RDA/SP/17/25/01
Alankerny faisal Main Road (Koof Nagar)
100%
26,879,843.9735,125,795.85Awarded
21RR/RDA/16/25/05—
Jannah Road from Annor Road to Jannah Mosque Junction
100%
15,746,511.3615,746,511.36Awarded
22RR/RDA/16/25/06—
Improvement of Mosque Lane from beach Road to Jummah Mosque Lane (0+500)m
100%
22,306,322.1722,306,322.17Awarded
23RR/RDA/SP/16/25/02—
Karana junction south pahalawela palanoya road (From near Pahalalanda post office junction to Karanagama)
100%
171,722,366.66171,722,366.66Awarded
24RR/RDA/16/25/02—
Muwagammana First Lane to Cemetry
100%
37,324,257.1237,324,257.12Awarded
25RR/RDA/STA II/17/25/01—
Hira Village Road
100%
48,842,501.7848,842,501.78Awarded
Showing 1–25 of 30
Per page:
Source: DRRRP • 86 projects • Data updated 2026-11-02 10:30 • 11:40:07