DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 73 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:73 awarded · Eastern Province

Portfolio Breakdown · Eastern Province · Province

579Awarded739Total
Eastern Province 73 awarded of 86 Open filtered view
CategoryImplementation MethodTotal PortfolioAwarded PortfolioPending RoadsAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
Total RoadsTotal ProjectsEst. Sanctioned ProjectsEst. Sanctioned RoadsPending Sanctioned RoadsSanctioned Length kmSanctioned Amount LKR MnEstimate LKR MnLOA Issued ProjectsLOA Issued RoadsAwarded Est LKR MnContract LKR Mn
TenderTender Above 50Mn16161616037.601,629.11,629.166819.7566.41038%545.9152.027% of contract96.8%43.5%——6—
Tender Below 50Mn58585858039.651,816.61,816.655551,742.61,164.1395%435.5376.332% of contract41.8%55.1%39—16—
PIU000000.000.00.00—0.00.000%————————
Not Specified000000.000.00.00—0.00.000%————————
Tender Total74747474077.253,445.73,445.761612,562.31,730.51382%981.4528.331% of contract47.2%53.9%390220
Direct LabourDL Stage 01666607.48311.7311.766311.7311.70100%140.0220.071% of contract83.3%100.0%6———
DL Stage 02222200.9549.349.32249.349.30100%49.340.181% of contract100.0%97.5%11——
DL Stage 03111101.0048.848.81148.848.80100%—50.6104% of contract0.0%100.0%1———
DL Stage 04333303.1593.993.93393.993.90100%43.272.777% of contract33.3%96.7%21——
Direct Labour Total12121212012.58503.8503.81212503.8503.80100%232.5383.476% of contract66.6%98.8%10200
—Eastern Province86868686089.833,949.53,949.573733,066.12,234.31385%1,214.0911.741% of contract50.4%61.3%492220

Avg Physical Progress per EE Division · Eastern Province

At-Risk Projects · Eastern Province

218
Portfolio Timeline· 73 scheduled projects · Eastern Province Toggle
2025-06-21 today2027-03-11
Portfolio · Awarded Works

Awarded Projects

49 projects

25/49 (filtered)

Filter awarded works

49 matching projects1 active

ActiveOn Progress
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/16/25/04/AKK/AMPRR/RDA/16/25/04
Pokunugama near Mr. Dinesh Tharaga House to Road (From Pokunugama Pre School to up to Mr. Dinesh Tharaga House)
100%
6,435,000.0010,039,653.26Awarded
2RR/RDA/16/25/01/AKK/AMPRR/RDA/16/25/01
Samanalathenna- Road from House No.63 To the Monastery Muwagammana -From First Lane to Cemetry
100%
21,336,681.8736,719,169.87Awarded
3RR/RDA/STA II/16/25/02/AKK/AMPRR/RDA/STA II/16/25/02
Concreting entrance road with culvert at Dehiaththakandiya Kelegama
100%
30,737,790.6047,778,623.73Awarded
4RR/RDA/STA II/16/25/04/AKK/AKKRR/RDA/STA II/16/25/04
Lahugala Hulannuge Roundabout road
100%
26,597,958.2036,508,598.90Awarded
5RR/RDA/16/25/10KM/06/AKK/AKKRR/RDA/16/25/10KM/06
Hulannuge School Road
100%
11,406,166.7317,414,587.68Awarded
6RR/RDA/16/25/10KM/09/AKK/AKKRR/RDA/16/25/10KM/09
Road behind Necode Institute (Navatkadu Akkarapattu)
100%
15,228,903.2524,614,649.47Awarded
7RR/RDA/15/25/01/EP/BTCRR/RDA/15/25/01
Concreting to Vipulananthar road
100%
29,074,090.8944,424,075.79Awarded
8RR/RDA/15/25/07/EP/BTCRR/RDA/15/25/07
Concreting to Thakwa masjith Cross Road
100%
22,206,567.3036,804,461.32Awarded
9RR/RDA/15/25/12/EP/BTCRR/RDA/15/25/12
Concreting to Muthalaikuda to Munnaikkadu Boundary Road
40%
26,564,874.5147,720,744.30Awarded
10RR/RDA/15/25/13/EP/BTCRR/RDA/15/25/13
Concreting to Sangarpuram- Vilavadi
10%
24,189,660.0046,948,339.52Awarded
11RR/RDA/15/25/10KM/01/BTCRR/RDA/15/25/10KM/01
Sooriya farm Road sathurukondan
50%
20,565,497.2429,978,952.90Awarded
12RR/RDA/15/25/10KM/02/BTCRR/RDA/15/25/10KM/02
Iruthayapuram west 8th cross
30%
27,156,544.2537,780,902.59Awarded
13RR/RDA/15/25/10KM/06/BTCRR/RDA/15/25/10KM/06
Al Ameen Vidyaya Road
20%
32,841,084.2148,327,996.29Awarded
14RR/RDA/15/25/10KM/07/BTCRR/RDA/15/25/10KM/07
Kanady cross Road to Magalingeshwarar kovil Road
5%
25,946,118.0036,198,556.07Awarded
15RR/RDA/15/25/10KM/08/BTCRR/RDA/15/25/10KM/08
Poosakar Road, Kannakipuram, Mahiloor
95%
27,673,151.0040,745,256.81Awarded
16RR/RDA/17/25/01/EP/TRNRR/RDA/17/25/01
Pillayar Road Renovation
100%
23,425,921.5630,058,596.03Awarded
17RR/RDA/17/25/02/EP/TRNRR/RDA/17/25/02
Kathirkamathambi Road
100%
28,809,738.0038,871,590.79Awarded
18RR/RDA/17/25/03/EP/TRNRR/RDA/17/25/03
Hospital Road
100%
18,557,253.7723,553,502.50Awarded
19RR/RDA/17/25/07/EP/TRNRR/RDA/17/25/07
Kanthamalawa Main Road
100%
9,161,570.0017,579,515.67Awarded
20RR/RDA/17/25/10/EP/TRNRR/RDA/17/25/10
From Medagama temple to Peramaduwa
100%
24,197,635.0031,162,876.79Awarded
21RR/RDA/17/25/11/EP/TRNRR/RDA/17/25/11
Development of Road from near the Fair
15%
25,280,343.6037,892,493.36Awarded
22RR/RDA/17/25/12/EP/TRNRR/RDA/17/25/12
Improvement of RDS Road
100%
30,166,053.0038,673,984.79Awarded
23RR/RDA/17/25/13/EP/TRNRR/RDA/17/25/13
Concreting from School junction to Boovidya Office
100%
38,264,100.0049,104,899.44Awarded
24RR/RDA/17/25/14/EP/TRNRR/RDA/17/25/14
Amaithusha Road (School road to Vaithiyar road)
100%
5,006,100.006,650,570.02Awarded
25RR/RDA/17/25/15/EP/TRNRR/RDA/17/25/15
Cemetery Road (Sajahan Mowlavi's house to Thajudeen shop)
100%
21,774,456.0027,637,562.79Awarded
Showing 1–25 of 49
Per page:
Source: DRRRP • 86 projects • Data updated 2026-11-02 10:30 • 09:53:19