Ditwah (CP)

Financial Dashboard

Monitor financial performance across 5 awarded projects

2026-09-27
17:20:02Live 2026-09-27
1,281.7 Mn

1,281.74 Mn

Total Contract

127.9 Mn

127.88 Mn

Advance Paid (excl. VAT)

4.4 Mn

4.44 Mn

IPCs Paid (excl. VAT)

132.3 Mn

132.33 Mn

Total Paid (excl. VAT)

156.1 Mn

156.14 Mn

Total Paid (incl. VAT)

49.9 Mn

49.86 Mn

Advance Pend (excl. VAT)

4.3 Mn

4.32 Mn

IPCs Pend (excl. VAT)

186.5 Mn

186.51 Mn

Total (Paid+Pend) (excl. VAT)

Paid excl + Adv Pend excl + IPC Pend excl

14.6%

14.6%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

47.8%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Matale EE · Consultant

34Projects 5,911.8Contract Mn
Matale EE 5 projects Open filtered view
Category Projects Contract LKR Mn Paid & Pending Advance IPC Planned Fin % Actual Fin %
Paid Mn + % Pending Mn Adv Req Adv Paid Adv Paid Mn IPC Req IPC Paid IPC Paid Mn
Emergency 5 1,281.7 156.1 12% of contract 63.9 4 3 127.9 2 1 4.4 52.1% 10.3%
DC 0 0.0 — — — — — — — — — —
DC - Slope 0 0.0 — — — — — — — — — —
PD(CP) 0 0.0 — — — — — — — — — —
Matale EE 5 1,281.7 156.1 12% of contract 63.9 4 3 127.9 2 1 4.4 52.1% 10.3%
Emergency 5 projects 1,281.7Mn
12% paid 156.1 Mn
Pending63.9Mn
Planned Fin52.1%
Actual Fin10.3%
Advance & IPC
Advance paid3 proj · 127.9 Mn
IPC paid1 proj · 4.4 Mn
Open filtered view
DC 0 projects 0.0Mn
0% paid 0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope 0 projects 0.0Mn
0% paid 0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) 0 projects 0.0Mn
0% paid 0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Matale EE 5 projects 1,281.7Mn
12% paid156.1 Mn
Pending63.9Mn
Planned Fin52.1%
Actual Fin10.3%

Avg Physical Progress per EE Division · Matale EE

Project-wise Financials · Matale EE (38 Projects)

Clear

Project-wise Contract Value vs. Expenditure and Pending Payments · Matale EE (Mn · incl. VAT)

Scroll horizontally — 38 projects

Matale EE Division · Matale EE (Mn · incl. VAT)

Matale District Summary (Mn · incl. VAT)

District baseline — overall all categories (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view: 5 awarded · Matale EE
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 38 projects

38 projects
Progress: - %
Contract No Contract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial Progress Financial Progress
with Outstanding
RDA/DRP/CEN/KDY/KAD/11 193,404,194.96 33,346,525.54 39,348,900.14 — — 2,776,135.64 3,275,840.06 3,848,290.21 692,692.24 36,122,661.18 3,848,290.21
42.62Mn
22%
Watch
43.32Mn
22.4%
RDA/DRP/CEN/KDY/KAN/14 74,836,014.77 — — — — — — — — — — — —
RDA/DRP/CEN/KDY/KDY/15 79,071,437.68 — — — — — — — — — — — —
RDA/DRP/CEN/KDY/KDY/19 67,935,586.77 — — — — — — — — — — — —
RDA/DRP/CEN/KDY/KUN/20 31,558,227.98 — — — — — — — — — — — —
RDA/DRP/CEN/KDY/KUN/21 257,721,453.96 46,231,491.42 54,553,159.88 — — — — — — 46,231,491.42 —
54.55Mn
21.2%
Watch
54.55Mn
21.2%
RDA/DRP/CEN/KDY/KUN/22 224,968,435.78 40,192,882.63 47,427,601.50 — — — — 34,738,972.19 40,991,987.18 40,192,882.63 34,738,972.19
47.43Mn
21.1%
Watch
88.42Mn
39.3%
RDA/DRP/CEN/KDY/KUN/24R 79,507,501.11 — — — — — — — — — — — —
RDA/DRP/CEN/KDY/KUN/25 157,909,825.01 28,346,587.80 33,448,973.60 — — 7,822,693.26 9,230,778.05 — — 36,169,281.06 —
42.68Mn
27%
Watch
42.68Mn
27%
RDA/DRP/CEN/KDY/KUN/27 113,434,139.40 20,128,022.37 23,751,066.40 — — — — — — 20,128,022.37 —
23.75Mn
20.9%
Watch
23.75Mn
20.9%
RDA/DRP/CEN/KDY/KUN/29 91,559,621.04 16,157,282.84 19,065,593.75 — — 5,944,519.21 7,014,532.67 — — 22,101,802.05 —
26.08Mn
28.5%
Watch
26.08Mn
28.5%
RDA/DRP/CEN/MTL/MTL/31R 63,704,849.78 — — — — — — — — — — — —
RDA/DRP/CEN/MTL/MTL/32 292,279,354.08 52,461,047.84 61,904,036.46 — — 4,444,918.28 5,245,003.57 4,317,402.29 5,094,534.70 56,905,966.12 4,317,402.29
67.15Mn
23%
Watch
72.24Mn
24.7%
RDA/DRP/CEN/MTL/MTL/33 165,006,430.79 29,068,239.71 34,300,522.86 — — — — — — 29,068,239.71 —
34.30Mn
20.8%
Watch
34.30Mn
20.8%
RDA/DRP/CEN/MTL/MTL/35 266,607,902.15 46,351,528.36 54,694,803.46 — — — — — — 46,351,528.36 —
54.69Mn
20.5%
Watch
54.69Mn
20.5%
RDA/DRP/CEN/MTL/MTL/38 281,166,339.80 — — 49,863,459.10 58,838,881.72 — — — — — 49,863,459.10 —
58.84Mn
20.9%
RDA/DRP/CEN/MTL/MTL/41 276,683,432.37 — — — — — — — — — — — —
RDA/DRP/CEN/MTL/NAL/48R 50,471,466.08 — — — — — — — — — — — —
RDA/DRP/CEN/MTL/NAL/49 44,706,119.13 7,270,523.42 8,579,217.63 — — 5,063,036.56 5,974,383.14 — — 12,333,559.98 —
14.55Mn
32.6%
Watch
14.55Mn
32.6%
RDA/DRP/CEN/MTL/NAL/51 17,458,592.78 2,700,844.13 3,186,956.07 — — 2,081,765.36 2,456,483.12 — — 4,782,609.49 —
5.64Mn
32.3%
Watch
5.64Mn
32.3%
RDA/DRP/CEN/NUE/HAN/57 47,755,538.96 — — — — — — — — — — — —
RDA/DRP/CEN/NUE/NUE/60R 336,313,078.73 — — — — — — — — — — — —
RDA/DRP/CEN/NUE/NUE/66 161,841,095.70 28,951,653.76 34,162,951.44 — — 14,629,744.09 17,263,098.02 — — 43,581,397.85 —
51.43Mn
31.8%
Watch
51.43Mn
31.8%
RDA/DRP/CEN/NUE/NUE/67 239,417,811.34 43,196,511.18 50,971,883.16 — — 23,041,263.85 27,188,691.84 12,851,984.19 15,165,341.34 66,237,775.03 12,851,984.19
78.16Mn
32.6%
Watch
93.33Mn
39%
RDA/DRP/CEN/NUE/NUE/68 213,999,600.01 38,371,088.02 45,277,883.86 — — — — 6,376,287.74 7,524,019.18 38,371,088.02 6,376,287.74
45.28Mn
21.2%
Watch
52.80Mn
24.7%
RDA/DRP/CEN/NUE/NUE/69 266,045,892.19 47,095,300.00 55,572,454.00 — — 29,846,649.63 35,219,046.57 3,965,848.32 4,679,701.02 76,941,949.63 3,965,848.32
90.79Mn
34.1%
Watch
95.47Mn
35.9%
RDA/DRP/CEN/NUE/NUE/86 33,765,626.86 — — — — — — — — — — — —
RDA/DRP/CEN/NUE/NUR/97 93,758,217.76 14,149,694.34 16,696,639.33 — — — — — — 14,149,694.34 —
16.70Mn
17.8%
Behind
16.70Mn
17.8%
RDA/DRP/CEN/NUE/NUR/98 188,617,394.68 — — — — — — — — — — — —
RDA/DRP/CEN/NUE/NUR/101 86,746,198.17 — — — — — — — — — — — —
RDA/DC/DRP/CP/NE/NRW/02 374,859,845.10 — — — — — — — — — — — —
RDA/DC/DRP/CP/NE/NE/04 47,725,380.00 — — — — — — — — — — — —
RDA/DC/DRP/SLOPE/CP/KDY/GAMP… 386,699,553.58 — — — — — — — — — — — —
RDA/DC/DRP/CP/NE/NRW/03 604,298,969.28 — — — — — — — — — — — —
RDA/DC/DRP/SLOPE/PD(CP)/KDY/… 22,481,370.00 — — — — — — — — — — — —
RDA/DC/DRP/SLOPE/PD(CP)/KDY/… 24,796,315.46 — — — — — — — — — — — —
RDA/DC/DRP/SLOPE/PD(CP)/KDY/… 28,806,688.50 — — — — — — — — — — — —
RDA/DC/DRP/SLOPE/PD(CP)/KDY/… 19,636,680.00 — — — — — — — — — — — —
Total 6,007,556,181.74 494,019,223.36 582,942,643.54 49,863,459.10 58,838,881.72 95,650,725.88 112,867,857.04 66,098,784.94 74,148,275.66 589,669,949.24 115,962,244.04
695.81Mn
11.6%
828.80Mn
13.8%