DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 57 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-04 12:46Live
Graphs reflect current view:57 awarded · Central Province
0%

0

Completed

0 / 57 awarded

Portfolio Breakdown · Central Province · Province

171Awarded266Total
Central Province 57 awarded of 131 Open filtered view
CategoryTotal PortfolioAwarded PortfolioPendingAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
TotalEstimate LKR MnAwardedAwarded Est LKR MnContract LKR Mn
Emergency325,395.4315,395.44,646.7197%3,501.0969.921% of contract74.3%37.7%36211
DC - Roads2613,492.884,220.05,116.61831%14.4—0.5%5.8%3——5
DC - Slope5219,237.7103,073.43,258.54219%10.4—0.3%4.7%1——9
PD(CP) - Slope21478.08181.8177.71338%——0.0%0.0%———8
Central Province13138,603.95712,870.713,199.57444%3,525.8969.97% of contract40.5%22.1%762123

Avg Physical Progress per EE Division · Central Province

At-Risk Projects · Central Province

92
Portfolio Timeline· 34 scheduled projects · Central Province Toggle
Portfolio · Awarded Works

Awarded Projects

6 projects

6/6 (filtered)

Filter awarded works

6 matching projects1 active

ActiveDelay
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/KDY/KAN/14
Rehabilitation /Improvement of Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)
9%
74,836,014.7772,827,654.90Awarded
RDA/DRP/CEN/KDY/KDY/15
Rehabilitation / Improvement of Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)
6%
79,071,437.6879,953,569.86Awarded
RDA/DRP/CEN/KDY/KUN/24R
Rehabilitation / Improvement of Flood damage on Katugastota - Madawala - Bamberella Road (B205) (0-000 - 7+200 and 13+000 - 13+045)
5%
79,507,501.1180,438,429.85Awarded
RDA/DRP/CEN/KDY/KUN/29
Improvement to Structures on Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) and Moragahamula victoria damtop
61%
91,559,621.04100,543,979.99Awarded
RDA/DRP/CEN/MTL/MTL/41
Rehabilitation / Improvement of Matale Illukkumbura Laggala Road (B 274) (4+000 - 18+000)
11%
276,683,432.37265,809,486.28Awarded
RDA/DRP/CEN/MTL/NAL/51
Rehabilitation /Improvement of Retaining wall , drains and shoulder construction Bowathenna Access Road (B-064) (0+000-2+410)
90%
17,458,592.7825,992,198.15Awarded
Showing 1–6 of 6
Per page:
Source: DRRRP • 131 projects • Data updated 2026-11-04 12:46 • 14:23:46