Project Monitoring Dashboard

Comprehensive overview of 38 infrastructure projects under the Disaster Rehabilitation Programme.

Updated 2026-09-24 15:27Live

Portfolio at a Glance

38 awarded works

Works Not Started 2026-09-24 15:27
50% awarded

0

Awarded

76 total projects in portfolio

6,007.6M

6,007.6 Mn

Contract Value

Spent 9.8% Remaining 90.2%
Avg
22.2%

30

works in progress

0 completed

Avg Progress

589.7M

589.7 Mn

Total Expenditure (excl. VAT)

9.8% of contract excl. VAT
18.4%

0

Kick Off Pending

7 / 38 awarded

21.1%

0

Mobilization Pending

8 / 38 awarded

26.3%

0

Works Not Started

10 / 38 awarded

0%

0

Completed

0 / 38 awarded

Portfolio Breakdown · District

38Awarded 76Total
Category Total Awarded Pending Awarded % Estimate LKR Mn Contract LKR Mn Planned Exp Mn Actual Exp ex-VAT Planned % Actual %
Emergency 32 30 2 94% 4,917.0 4,498.3 2,424.3 589.7 13% of contract 61.5% 27.8%
DC 26 3 23 12% 12,074.2 1,026.9 24.4 — 4.9% 2.0%
DC - Slope 1 1 0 100% 0.0 386.7 9.7 — 6.2% 2.3%
PD(CP) 17 4 13 24% 371.9 95.7 — — 0.0% 0.0%
All Districts 76 38 38 50% 17,363.0 6,007.6 2,458.4 589.7 10% of contract 49.1% 22.2%

Avg Physical Progress per EE Division

Portfolio Timeline · 31 scheduled projects Toggle
Portfolio · Awarded Works

Awarded Projects

10 projects

10/10 (filtered)
Active filters: Works Not Started
Contract No. Contract Name Progress Amount Status
RDA/DRP/CEN/KDY/KAN/14
Rehabilitation /Improvement of Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)
0%
74,836,014.77 Awarded
RDA/DRP/CEN/KDY/KDY/19
Rehabilitation / Improvement of Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)
0%
67,935,586.77 Awarded
RDA/DRP/CEN/MTL/MTL/31R
Rehabilitation / Improvement of Matale - Udupihilla Road (AB026) (0+000 - 6+000)
0%
63,704,849.78 Awarded
RDA/DRP/CEN/MTL/NAL/48R
Rehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
0%
50,471,466.08 Awarded
RDA/DRP/CEN/NUE/NUE/60R
Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850)
0%
336,313,078.73 Awarded
RDA/DC/DRP/CP/NE/NE/04
REHABILITAION/ IMPROVEMENTS OF LADY MACALUMS DRIVE ROAD (2+850 - 5+600KM)
0%
47,725,380.00 Awarded
RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/01
Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 0+030 km
0%
22,481,370.00 Awarded
RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/14
Construction of Slope failure mitigation measures along Atabage-Ulapane Road (B 490) at Ch 4+000 km
0%
24,796,315.46 Awarded
RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/29
Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 21+550 km
0%
28,806,688.50 Awarded
RDA/DC/DRP/SLOPE/PD(CP)/KDY/KUN/18,19&20
Construction of Slope failure mitigation measures along Kandy – Mahiyangana – Padiyatalawa Road (A026) at Culvert No 47/5 Culvert No47/10, Culvert No 50/6-51+200 km and Culvert No 52/3-Culvert No 52/5
0%
19,636,680.00 Awarded
Showing 1–10 of 10
Per page:
Source: ditwah_projects • 76 projects • Data updated 2026-09-24 15:27 • 16:23:08