DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 171 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 15:53Live

Portfolio Breakdown · Province

171Awarded266Total
CategoryTotal PortfolioAwarded PortfolioPendingAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
TotalEstimate LKR MnAwardedAwarded Est LKR MnContract LKR Mn
Emergency15328,654.714426,716.524,785.9994%21,227.54,470.518% of contract85.3%38.8%9131193
DC - Roads3920,559.494,690.05,783.23023%14.4—0.4%5.2%3——6
DC - Slope5319,237.7103,073.43,258.54319%10.4—0.3%4.7%1——9
PD(CP) - Slope21478.08181.8177.71338%——0.0%0.0%———8
All Provinces26668,929.917134,661.834,005.39564%21,252.44,470.513% of contract71.9%33.2%131311926

Avg Physical Progress per EE Division

At-Risk Projects

92
Portfolio Timeline· 145 scheduled projects Toggle
2026-02-06 today2028-03-15

Showing first 80 of 145 projects.

Portfolio · Awarded Works

Awarded Projects

3 projects

3/3 (filtered)

Filter awarded works

3 matching projects1 active

ActiveProgress 100–100%
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/SAB/RAT/PEL/19
Rehabilitation / Improvement and Retaining wall Construction of (Galle - Deniyaya - Madampe Road 144/1 - 144/2 RHS, 135-136/1 LHS & RHS, 137/5-137/4 LHS) & Pelmadulla - Embilipitiya - Nonagama Road 10/4 LHS, 18/1-18/2 LHS)
100%
95,082,996.58105,062,690.47Awarded
RDA/DRP/NCP/POL/POL/08
Rehabilitation / Improvement and Reconstruction of 31/1 Culvert, Construction Of Retaining Walls At 31/2 (RHS) on Manampitiya Aralaganwila Maduruoya Road
100%
17,459,311.3717,399,611.61Awarded
RDA/DRP/SP/GAL/GAL/02
Rehabilitation of Gabbion Walls along Galle - Deniyaya - Madampe Road (from7+700-7+730)
100%
8,991,852.3410,402,707.85Awarded
Showing 1–3 of 3
Per page:
Source: DRRRP • 266 projects • Data updated 2026-11-02 15:53 • 08:57:43